" The Contractor shall promptly, and before such conditions are disturbed, notify the Contracting Officer In writing of: (1) subsurface or latent physical conditions at the site differing materially from those Indicated in this contract, or (2) unknown... "
The Code of Federal Regulations of the United States of America - Page 168
1967
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1969 - 640 pages
...promptly, and before such conditions are disturbed, notify the Contracting Officer in writing of: (a) subsurface or latent physical conditions at the site...materially from those indicated in this contract, or (b) unknown physical conditions at the site, of an unusual nature, differing materially from those...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1999 - 604 pages
...following: (1) The contractor shall promptly, and before such conditions are disturbed, notify the claimant in writing of: (1) Subsurface or latent physical conditions at the site differing materially from those listed in this contract, or (ii) Unknown physical conditions at the site, of an unusual nature, differing...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 2003 - 542 pages
...following: (1) The contractor shall promptly, and before such conditions are disturbed, notify the claimant in writing of: (1) Subsurface or latent physical conditions at the site differing materially from those listed in this contract, or (ii) Unknown physical conditions at the site, of an unusual nature, differing...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1971 - 664 pages
...shall be allowed if asserted after final payment under this contract. 4. DIFFERING SITE CONDITIONS (a) The Contractor shall promptly, and before such conditions are disturbed, notify the Contracting Officer in writing1 of: (1) Subsurface or latent physical conditions at the site differing materially from those...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1968 - 1348 pages
...such conditions are dlslurlted. notify the Contracting Officer in writing of: (a) subsurface or Intent physical conditions at the site differing materially from those indicated In this contract, or (b) unknown physical conditions at the site, of nn unusual nature, din. -nut: materially from those...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 2001 - 580 pages
...contract that does not contain a "differing site conditions" clause equivalent to the following: (1) The contractor shall promptly, and before such conditions are disturbed, notify the claimant in writing of: (1) Subsurface or latent physical conditions at the site differing materially...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1967 - 2356 pages
...before luch conditions are disturbed, notify the Contracting Officer in writing of: (a) sub:irf ace or latent physical conditions at the site differing materially from those Indicated r. this contract, or (b) unknown physical ondltions at the site, of an unusual nature, ilff ertng materially...
Full view - About this book

Air Force Intercontinental Ballistics Missile Base Construction Program ...

United States. Congress. House. Appropriations - 1961 - 336 pages
...herein provided, no charge for any extra work or material will be allowed. > 4. CHANGED CONDITIONS The Contractor shall promptly, and before such conditions...physical conditions at the site, of an unusual nature, ditfering materially from those ordinarily encountered and generally recognized us inhering in work...
Full view - About this book

Standard Specifications for Construction of Roads and Bridges on Federal ...

United States. Bureau of Public Roads - Bridges - 1969 - 472 pages
...shall be allowed if asserted after final payment under this contract. DIFFERING SITE CONDITIONS (a) The Contractor shall promptly, and before such conditions...physical conditions at the site differing materially from these indicated in this contract, or (2) unknown physical conditions at the site, of an unusual nature,...
Full view - About this book

Decisions of the Department of the Interior, Volume 64

United States. Department of the Interior - Natural resources - 1957 - 624 pages
...requirements. Clause 4 stated that, should conditions of the type described in that clause be encountered, "the Contractor shall promptly, and before such conditions...disturbed, notify the Contracting Officer in writing" of the conditions encountered, and that any claim of the Contractor for an equitable adjustment on account...