| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1983 - 1168 pages
...adjustment either under the termination for convenience clause or under "differing site conditions," ie: (1) Subsurface or latent physical conditions at the...site differing materially from those indicated in the contract, or (2) Unknown physical conditions at the site, of an unusual nature, differing materially... | |
| Administrative law - 1984 - 596 pages
...contract. 4. DIFFERING SITE CONDITIONS (a) The Contractor shall promptly, and before such conditions lire disturbed, notify the Contracting Officer in writing...(1) Subsurface: or latent physical conditions at the sit* dilferi.ig materially from those indicated in this contract, or (2) unknown physical condition*... | |
| Administrative law - 1988 - 872 pages
...shall be allowed if asserted after final payment under this contract. 3. DIFFERING SITE CONDITIONS (a) The contractor shall promptly, and before such conditions are disturbed, notify the owner in writing of: (1) Subsurface or latent physical conditions at the site differing materially... | |
| Robert A. Rubin, Sammie D. Guy, Alfred C. Maevis, Virginia Fairweather - Law - 1992 - 332 pages
...to the Contracting Officer of (1) subsurface or latent physical conditions at the site which differ materially from those indicated in this contract,...unknown physical conditions at the site, of an unusual mature, which differ materially from those ordinarily encountered and generally recognized as inhering... | |
| Administrative law - 1993 - 510 pages
...contractor shall promptly, and before such conditions are disturbed, notify the claimant in writing of: (i) Subsurface or latent physical conditions at the site differing materially from those listed in this contract, or (ii) Unknown physical conditions at the site, of an unusual nature, differing... | |
| John G. Cameron - Building laws - 2000 - 780 pages
...enough of an indication on the face of the contract documents for a bidder reasonably not to expect 'subsurface or latent physical conditions at the site differing materially from those indicated in [the] contract.'"1" Finally, the Supreme Court of Wisconsin held, in Metropolitan Sewerage Commission... | |
| Law - 2001 - 222 pages
...circumstances. Specifically, the contract permits the contractor to receive additional compensation for "subsurface or latent physical conditions at the site differing materially from those indicated in the Contract [quote exact contract language]." A "subsurface" condition is one that exists below the... | |
| Levent Ozdemir - Technology & Engineering - 2002 - 412 pages
...to the Contracting Officer of (I) subsurface or latent physical conditions at the site which differ materially from those indicated in this contract,...physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering in work... | |
| Thomas J. Kelleher, Brian G. Corgan, William E. Dorris - Law - 2002 - 514 pages
...to the Contracting Officer of (1 ) subsurface or latent physical conditions at the site which differ materially from those indicated in this contract,...physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering work... | |
| Michael K. De Chiara, Michael S. Zetlin - Law - 2003 - 456 pages
...Conditions" allows the contractor to receive payment for additional work performed as a result of: (1) latent physical conditions at the site differing materially from those indicated in the contract; or (2) unknown physical conditions at the site of an unusual nature, differing materially... | |
| |