| Administrative law - 1973 - 260 pages
...Any claim by the Contractor for adjustment under this clause must be asserted within 30 calendar days from the date of receipt by the Contractor of the...change: Provided, however, That the Contracting Officer, lf he decides that the facts justify such action, may receive and act upon any such claim asserted... | |
| United States. Congress. House. Education and Labor - 1974 - 566 pages
...schedule, or both, (b) in the amount of any fee to be paid to the Contractor, and (c) in such other provisions of the contract as may be so affected,...Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may receive and act upon such claim asserted at any... | |
| Administrative law - 1975 - 456 pages
...Contractor; (Ш) In such other provisions of the contract as may be affected, and the contract snail be modified In writing accordingly. Any claim by the...within thirty (30) days from the date of receipt by tne Contractor of the notification of change; provided that, without prejudicing the right to reject... | |
| United States. Congress. Senate. Committee on Appropriations - Aeronautics, Commercial - 1975 - 146 pages
...completion time, or both; 2. In the amount of any fixed fee to be paid to the OPERATOR; and 3. In such other provisions of the contract as may be so affected,...modified in writing accordingly. Any claim by the OPERATOR for adjustment under this clause must be asserted within thirty (30) days from the date of... | |
| United States. Congress. Senate. Appropriations Committee - 1975 - 134 pages
...completion time, or both; 2. In the amount of any fixed fee to be paid to the OPERATOR; and 3. In such other provisions of the contract as may be so affected,...modified in writing accordingly. Any claim by the OPERATOR for adjustment under this clause must be asserted within thirty (30) days from the date of... | |
| Administrative law - 1975 - 460 pages
...shall be modified in writing accordingly. Any claim by th« Contractor for adjustment under this claus* must be asserted within thirty (30) days from the...receipt by the Contractor of the notification of change; Provides., however, That the Contracting Officer, if h* decides that the facts justify such action,... | |
| Administrative law - 1975 - 880 pages
...fixed fee to be paid to the Contractor; and (lii) In such other provisions of the contract as may be affected, and the contract shall be modified in writing...accordingly. Any claim by the Contractor for adjustment Tinder this clause must be asserted within •thirty (30) days from the date of receipt by the Contractor... | |
| |