" Any claim by the Contractor for adjustment under this clause must be asserted within thirty (30) days from the date of receipt by the Contractor of the notification of change; Provided, however, That the Contracting Officer, if he decides that the facts... "
The Code of Federal Regulations of the United States of America - Page 226
1988
Full view - About this book

Hearings, Volume 3

United States. Congress. House. Committee on Appropriations - 1964
...dollar price to be paid to the Contractor, or the time for completion, or both and (ii) in such other provisions of the contract as may be so affected,...adjustment under this clause must be asserted within sixty «10) days from the date of receipt, by the Contractor of the notification of change: Provided,...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1964
...schedule, or both. (11) in the amount of any fee to be paid to the Contractor, and (111) In such other provisions of the contract as may be so affected,...adjustment under this clause must be asserted within sixty (60) days from the date of receipt by the Contractor of the notification of change; Provided...
Full view - About this book

Code of Federal Regulations

Administrative law - 1965
...adjustment shall be made (1) in the contract price or time of performance, or both, and (11) in such other provisions of the contract as may be so affected,...adjustment under this clause must be asserted within sixty (60) Says from the date of receipt by the Contractor of the notification of change; Provided,...
Full view - About this book

Code of Federal Regulations

Administrative law - 1972
...adjustment shall be made (1) in the contract price or time of performance, or both, and (it) In such other provisions of the contract as may be so affected,...adjustment under this clause must be asserted within sixty (60) days from the date of receipt by the Contractor of the notification of change; Provided,...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1970
...equitable adjustment shall be made in the estimated cost, the completion schedule, or both, and the contract shall be modified In writing accordingly....(30) days from the date of receipt by the Contractor oí the notification oí change : Provided, however, That the Contracting Officer, ii he decides that...
Full view - About this book

Code of Federal Regulations

Administrative law - 1969
...or both, (11) in the amount of any fixed fee to be paid to the Contractor, and (111) in such other provisions of the contract as may be so affected,...adjustment under this clause must be asserted within sixty (60) days from the date of receipt by the Contractor of the notification of change: Provided,...
Full view - About this book

Code of Federal Regulations

Administrative law - 1965
...schedule, or both, (11) in the amount of any fee to be paid to the Contractor and/or (111) in such other provisions of the contract as may be so affected,...adjustment under this clause must be asserted within 30 days from the date 61 receipt by tHe Contractor of the notification of change: Provided, however,...
Full view - About this book

Code of Federal Regulations

Administrative law - 1965
...or both, (11) In the amount of any fixed fee to be paid to the Contractor, and (ill) In such other provisions of the contract as may be so affected,...adjustment under this clause must be asserted within sixty (60) days from the date of receipt by the Contractor of the notification of change: Provided,...
Full view - About this book

Code of Federal Regulations

Administrative law - 1970
...adjustment shall be made (1) in the contract price or time of performance, or both, and (ii) in such other provisions of the contract as may be so affected,...contractor for adjustment under this clause must be assorted within thirty (30) days from the date of receipt by the contractor of the notification of...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1960
...made in (1) the estimated cost or schedule of target completion dates, or both; and (11) such other provisions of the contract as may be so affected;...accordingly. Any claim by the Contractor for adjustment under tfaia clause must be asserted within (60) days from the date of receipt by the Contractor of the notification...