| United States. Congress. Senate. Labor and Public Welfare - 1971 - 834 pages
...time for completion of the contract, or in the amount of any fee to be paid the Contractor, and the contract shall be modified in writing accordingly....Provided, however, That the Contracting Officer, if he decides that there are special facts justifying such action, may receive and act upon any such claim... | |
| United States. Tax Court - Government publications - 1970 - 1868 pages
...accordingly. Any claim of the Contractor for adjustment noder this clause must be asserted in writing within 30 days from the date of receipt by the Contractor...Provided, however, That the Contracting Officer, if he determines that the facts justify such action, may receive and consider, and adjust any such claim... | |
| Administrative law - 1971 - 832 pages
...Any claim by the Contractor for adjustment under this clause must be asserted within sixty (60) days from the date of receipt by the Contractor of the...Provided., however, That the Contracting Officer, lf he decides that the facts justify such action, may receive and act upon any such claim asserted... | |
| United States. Congress. House Appropriations - 1972 - 2010 pages
...Contractor for adjustment ux4er this clause must be asserted within thirty (¿) days fron the date of receipt by the Contractor of the notification of...provided, however, that the Contracting Officer, if he decides that the facts justin such action, i¿.y receive and act upon any such claim asserted at... | |
| Administrative law - 1973 - 388 pages
...adjustment shall be made (1) In the contract price or time of performance, or both, and (11) in such other provisions of the contract as may be so affected,...shall be modified in writing accordingly. Any claim by th« Contractor for adjustment under this clause must be asserted within thirty (30) dayi from the... | |
| Administrative law - 1973 - 344 pages
...an equitable adjustment shall be made in the contract price or delivery schedule (or both) and the contract shall be modified in writing accordingly....adjustment under this clause must be asserted within sixty (60) days from the date of receipt by the Contractor of the notification of change; Provided,... | |
| United States. General Accounting Office - Finance, Public - 1973 - 1288 pages
...an equitable adjustment shall be made in the contract price or deliver}! schedule, or both, and the contract shall be modified in writing accordingly....adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change, provided, however,... | |
| |