| Administrative law - 1967 - 706 pages
...by the Contractor for adjustment under this clause must be asserted within 30 days from the date or receipt by the Contractor of the notification of change:...any time prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's... | |
| Administrative law - 1970 - 818 pages
...by the Contractor for adjustment under this clause must be asserted within 80 days from the date or receipt by the Contractor of the notification of change:...any time prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change Is Included in the Contractor's... | |
| Administrative law - 1969 - 820 pages
...by the Contractor for adjustment under this clause must be asserted within 30 days from the date or receipt by the Contractor of the notification of change:...any time prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's... | |
| Administrative law - 1970 - 796 pages
...by the Contractor for adjustment under this clause must be asserted within SO days from the date or receipt by the Contractor of the notification of change,...asserted at any time prior to final payment under thta contract. Where the cost of property made obsolete or excess as result of a change !G Included... | |
| Administrative law - 1968 - 852 pages
...by the Contractor for adjustment under this clause must be asserted within 30 days from the date or receipt by the Contractor of the notification of change:...upon any such claim asserted at any time prior to anal payment under this contract. Where the cost of property made obsolete or excess as a result of... | |
| Administrative law - 1970 - 808 pages
...by the Contractor for adjustment under this clause must be asserted within 30 days from the date or receipt by the Contractor of the notification of change:...receive and act upon any such claim asserted at any tune prior to final payment under this contract. Where the cost of property made obsolete or excess... | |
| Administrative law - 1971 - 862 pages
...by the Contractor for adjustment under this clause must be asserted within 30 days from the date or receipt by the Contractor of the notification of change,...receive and act upon any such claim asserted at any tune prior to final payment under this contract. Where the cost of property made obsolete or excess... | |
| Administrative law - 1976 - 906 pages
...asserted within thirty (30) days from the date of receipt by the Contractor of the notification ol change; Provided, however. That the Contracting Officer,...asserted at any time prior to final payment under thlsf contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact... | |
| United States. Department of the Interior - Natural resources - 1964 - 710 pages
...provided that claims must be asserted within 30 days from receipt of the notification of change, but that "the Contracting Officer, if he decides that...time prior to final payment under this contract." 80 The Board refused to dismiss, saying : Counsel contends that the power to receive and act upon late... | |
| |