" Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change : Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may... "
The Code of Federal Regulations of the United States of America - Page 435
1978
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1973
...writing accordingly. Any claim by the contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the contractor...upon any such claim asserted at any time prior to flnal payment under this contract. Failure to agree to any adjustment shall be a dispute concerning...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1975
...In such other provisions of the contract as may be so affected, and the contract shall be modifled In writing accordingly. Any claim by the Contractor...upon any such claim asserted at any time prior to fl^ftl payment under this contract. Where the cost of property made obsolete or excess as a result...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1975
...writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor...prior to final payment under this contract. Failure to aerfi« to any adjustment shall be a dispute concerning a question of fact within the meaning of the...
Full view - About this book

GAO Legislation: Hearing Before the Subcommittee on Reports, Accounting, and ...

United States. Congress. Senate. Committee on Government Operations. Subcommittee on Reports, Accounting, and Management - Legislative auditing - 1975
...the Contractor of the notification of change: Provided, however, That the Contracting Officer, if be decides that the facts justify such action, may receive...Failure to agree to any adjustment shall be a dispute conceminz a • question of fact within the meaning of the clause of this contract entitled "Disputes."...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1975
...notification of change: Provided, however, That the Contracting Officer, If he decides that the facts Justlîy such action, may receive and act upon any such claim...to any adjustment shall be a dispute concerning a question of fact within the meanIng of the "Disputes" clause of this contract. However, nothing In...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1976
...equitable adjustment shall be made In the contract price, or time of performance, or both, and the contract shall be modified in writing accordingly....final payment under this contract. Failure to agree 66-012 — 76 12 to any adjustment shall be a dispute concerning a question of fact within the meanIng...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1976
...receipt by the Contractor of the notification of change; Provided, however, That the Contracting Office. If he decides that the facts justify such action,...clause of this contract entitled "Disputes." However, nothing In this clause shall excuse the Contractor from proceeding with the contract as changed. 4....
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1962
...writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor...any time prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's...
Full view - About this book

Solar Energy Research Institute--oversight Hearings: Hearing Before the ...

United States. Congress. House. Committee on Science and Technology. Subcommittee on Energy Research, Development, and Demonstration - Government publications - 1976 - 409 pages
...Contractor for an adjustment under this article must be asserted in writing within ninety (90) days from the date of receipt by the Contractor of the...any time prior to final payment under this contract. A failure to agree on an equitable adjustment under this article shall be deemed to be a dispute within...
Full view - About this book

Implementation of Public Law 93-638, the Indian Self-determination and ...

United States. Congress. Senate. Committee on Interior and Insular Affairs. Subcommittee on Indian Affairs - Indians of North America - 1976 - 609 pages
...Any claim by the Contractor for adjustment under this clause must be asserted within thirty (30) daya from the date of receipt by the Contractor of the...upon any such claim asserted at any time prior to Anal payment under this contract. Where the cost of property mode obsolete or excess a* a result of...