" Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's claim for adjustment, the Contracting Officer shall have the right to prescribe the manner of disposition of such property. Failure to agree to... "
The Code of Federal Regulations of the United States of America - Page 210
1965
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1981 - 1018 pages
...receive and act upon any such claim asserted at any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute'..."Disputes." However, nothing In this clause shall excuse th« Contractor from proceedlna with the contract as changed. (End of clause) In the foregoing clause,...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1982 - 876 pages
...however. That the Contracting Officer, if he decides that the facts justify such action, may rereive and act upon any such claim asserted at any time prior...Contractor from proceeding with the contract as changed. Clause No. 20— Retrocession. (a) The Indian tribe that initially requested this contract may also...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1983 - 806 pages
...Contractor for adjustment under this clause must be asserted within thirty (30) days from the date of receipt by the Contractor of the notification of change:...Contractor from proceeding with the contract as changed. Clause No. 14— Notice to the Government of delays. Whenever the Contractor has knowledge that any...
Full view - About this book

Justice Department Investigations of Defense Procurement Fraud: A Case Study ...

Armed Forces - 1988 - 976 pages
...Contractor's claim for adjustment, the Contracting Officer shall have the right to prescribe the "(f) Failure to agree to any adjustment shall be a dispute...Contractor from proceeding with the contract as changed as herein provided." The "Changes" provision of the contract is intended to permit the Government to...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1992 - 668 pages
...he/she decides that the facts justify such action, may receive and act upon any such claim assorted at any time prior to final payment under this contract....Contractor from proceeding with the contract as changed. (End of clause) CLAUSE No. 14— NOTICE TO THE GOVERNMENT OF DELAYS (JUNE 1977) Whenever the Contractor...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1964 - 762 pages
...by the Contractor for adjustment under this clause must be asserted within 60 days from the date of receipt by the Contractor of the notification of change:...Contractor from proceeding with the contract as changed. 8. ASSIGNMENT OF CLAIMS. (a) Pursuant to the provisions of the Assignment of Claims Act of 1940, as...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1960 - 268 pages
...by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change:...Contractor from proceeding with the contract as changed. § 1-7.101-3 Extras. EXTRAS Except as otherwise provided in this contract, no payment for extras shall...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1967 - 674 pages
...by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change:...Contractor from proceeding with the contract as changed. § 1-7.101-3 Extras. EXTRAS Except as otherwise provided In this contract, no payment for extras shall...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1968 - 748 pages
...by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change:...Contractor from proceeding with the contract as changed. § 1-7.101-3 Extras. EXTRAS Except as otherwise provided in this contract, no payment for extras shall...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1965 - 700 pages
...by the Contractor for adjustment under this clause must be asserted within 60 days from the date of receipt by the Contractor of the notification of change:...Contractor from proceeding with the contract as changed. 8. ASSIGNMENT OF CLAIMS. (a) Pursuant to the provisions of the Assignment of Claims Act of 1940. as...
Full view - About this book