| United States. General Accounting Office - Finance, Public - 1973 - 1288 pages
...changed by any such order, an equitable adjustment shall be made in the contract price or deliver}! schedule, or both, and the contract shall be modified...adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change, provided, however,... | |
| United States. Congress. House. Education and Labor - 1974 - 566 pages
...to the Contractor, and (c) in such other provisions of the contract as may be so affected, and the contract shall be modified in writing accordingly....adjustment under this clause must be asserted within thirty (30) days from the date of receipt by the Contractor of the notification of change: Provided,... | |
| James O. Mahoy - Government publications - 1975 - 912 pages
...an increase or decrease in the cost of, or the time required for, performance of this contract, an equitable adjustment shall be made in the contract...schedule, or both, and the contract shall be modified in writing accordingly. * * * That changes in the specifications were required is clear from the fact... | |
| Administrative law - 1975 - 880 pages
...paid to the Contractor; and (lii) In such other provisions of the contract as may be affected, and the contract shall be modified in writing accordingly. Any claim by the Contractor for adjustment Tinder this clause must be asserted within •thirty (30) days from the date of receipt by the Contractor... | |
| United States. Cost Accounting Standards Board - Cost accounting - 1976 - 386 pages
...other provisions of a contract, such as the requirement in the Changes clause of Standard Form 32, that any "claim by the contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the contractor of the notification of change," are considered to... | |
| Administrative law - 1962 - 596 pages
...performance of any part of the work under this contract, whether changed or not changed by any such order, an equitable adjustment shall be made In the contract...adjustment under this clause must be asserted within 60 days from the date of receipt by the Contractor of the notification of change: Provided, however,... | |
| |