" Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change: Provided, however, That the Contracting Officer, if he decides that the facts justify... "
The Code of Federal Regulations of the United States of America - Page 55
1979
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1971 - 664 pages
...adjustment under this clauseNmiAL be ijseerted within 30 days from the date of receipt by the Cim)irector of the notification of change: Provided, however....any time prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1972 - 862 pages
...clause must be asserted within 30 days from the date of receipt by the Contractor of the notlflcatlon of change: Provided, however, That the Contracting...any time prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change Is Included In the Contractor's...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1975 - 252 pages
...Any claim by the Contractor for adjustment under this clause must be asserted within 30 calendar days from the date of receipt by the Contractor of the...justify such action, may receive and act upon any such «laim asserted at any tune prior to final payment •under the contract. Failure to agree to any adjustment...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1976 - 1202 pages
...days from the date of receipt by the Contractor of the notification of change; provided, however, thai the Contracting Officer, if he decides that the facts...prior to final payment under this contract. Failure to 7^104.1 ARMED SERVICES PROCUREMENT REGULATION CONTRACT CLAUSES AND SOLICITATION PROVISIONS agree to...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1980 - 874 pages
...of the notification of change; Provided, however. Title 41 — Public Contract*, Property Management That the Contracting Officer, If he decides that the...any time prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is Included in the Contractor's...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1955 - 1316 pages
...Any claim by the Contractor for adjustment under this clause must be asserted within thirty (30) days from the date of receipt by the Contractor of the...decides that the facts Justify such action, may receive ana act upon any such claim asserted at any time prior to final payment under this contract. Failure...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1978 - 944 pages
...clause must be asserted within 30 days from the date of receipt by the Contractor of the rectification of change, provided, however, that the Contracting...receive and act upon any such claim asserted at any tine prior to final payment under this contract. Where the cost of property made obsolete or excess...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1978 - 880 pages
...Any claim by the Contractor for adjustment under this clause must be asserted within thirty (30) days from the date of receipt by the Contractor of the...Contracting Officer, if he decides that the facts justify sucn action, may receive and act upon any such claim asserted at any time prior to final payment under...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1998 - 656 pages
...Contractor of the notification of change: Provided, however, That the Contracting Officer, if he/she decides that the facts justify such action, may receive...any time prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1981 - 706 pages
...Contractor for adjustment under this clause must be asserted within sixty (60) days from the date of receipt of the notification of change: Provided, however,...justify such action, may receive and act upon any claim asserted at any time prior to final payment under this contract. Failure to agree to any adjustment...
Full view - About this book