| Administrative law - 1974 - 808 pages
...(2) unknown physical conditions at the site, of an unusual nature, differing materially from tliose ordinarily encountered and generally recognized as...conditions, and if he finds that such conditions do materially so differ and cause an increase or decrease in the Contractor's cost of, or the time required... | |
| James O. Mahoy - Government publications - 1975 - 912 pages
...disturbed, notify the Contracting Officer in writing of: (a) subsurface or latent physical conditions at the site differing materially from those indicated in...increase or decrease in the Contractor's cost of, or the time required for performance of this contract, an equitable adjustment shall be made and the contract... | |
| United States. Public Buildings Service - Construction contracts - 1975 - 240 pages
....physical conditions at the site differing materially from those indicated in this contract, or (2) unknown physical conditions at the- site, of an unusual...conditions, and if he finds that such conditions do materially so differ and cause an increase or decrease in the Contractor's cost of, or the time required... | |
| Administrative law - 1975 - 880 pages
...physical conditions at the site differing materially from those Indicated In this contract, or (2) unknown physical conditions at the site, of an unusual...Officer shall promptly Investigate the conditions, and II he finds that such conditions do materially BO differ and cause an Increase or decreas* In the Contractor's... | |
| Administrative law - 1962 - 596 pages
...disturbed, notify the Contracting Officer in writing of: (a) subsurface or latent physical conditions at the site differing materially from those indicated in...increase or decrease in the Contractor's cost of, or the time required for, performance of this contract, an equitable adjustment shall be made and the contract... | |
| Administrative law - 1983 - 544 pages
...ait* diJFcri.ig materially from those indicated in this contract, or (2) unknown physical condition* at the site, of an unusual nature, differing materially...shall promptly investigate the conditions, and if lie finds that such conditions do materially so differ and cause an increase or decrease in the Contractor's... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1983 - 1168 pages
...latent physical conditions at the site differing materially from those indicated in the contract, or (2) Unknown physical conditions at the site, of an unusual...provided for in this contract. The contracting officer refused to make any adjustment, and this suit followed. We are unable to state that interference with... | |
| Administrative law - 1964 - 440 pages
...disturbed, notify the Contracting Officer in writing of: (a) subsurface or latent physical conditions at the site differing materially from those indicated in...increase or decrease in the Contractor's cost of, or the time required for, performance of this contract, an equitable adjustment shall be made and the contract... | |
| Administrative law - 1966 - 648 pages
...notify the Contracting Officer In writing of: <a > subsurface or latent physical conditions at the site differing materially from those indicated in...such conditions do so materially differ and cause nn Increase or decrease in the Contractor's cost of. or the time required for. performance of this... | |
| Administrative law - 1966 - 984 pages
...disturbed, notify the Contracting Officer In writing at: (a) subsurface or latent physical conditions at the site differing materially from those indicated In...If he finds that such conditions do so materially difler and cause an Increase or decrease In the Contractor's cost of, or the time required for, performance... | |
| |