" Officer grants a further period of time before the date of final payment under the contract), notifies the Contracting Officer in writing of the causes of delay. The Contracting Officer shall ascertain the facts and the extent of the delay and extend... "
Code of Federal Regulations - Page 491
1965
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1983
...tracing Officer in writing of the causes of delay. Fhe Contracting Officer shall ascertain the [acts and the extent of the delay and extend the time for...parties subject only to appeal as provided in the clause of this contract entitled "Disputes."1 (e) If, after notice of termination of the Contractor's...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1965
...(unless the Contracting Officer granta a further iierfod of time l»efore the date of final iwyment under the contract), notifies the Contracting Officer...In his Judgment, the findings of fact justify such nn extension. and his findings of fact shall lie final and conclusive on the parties, subject only...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1972
...Officer in writing of the causes of delay. The Contracting Officer shall ascertain the facts and trie extent of the delay and extend the time for completing...the parties, subject only to appeal as provided in Clause 6 of these General Provisions. (e) If, after notice of termination of the Contractor's right...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1973
...shall grant a further period of time prior to the date of final settlement of the contract, notify the Contracting Officer In writing of the causes of...Judgment the findings of fact Justify such an extension, ud his findings of fact shall be final and conclusive on the parties hereto, subject onlr to appeal...
Full view - About this book

Code of Federal Regulations

Administrative law - 1965
...shall grant a further period of time prior to the date of final settlement of the contract, notify the Contracting Officer in writIng of the causes of...his judgment the findings of fact Justify such an extentton. and his findings of fact shall be final md conclusive on the parties hereto, subject inly...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1974
...contract, notify the Contracting Officer In writing of the causes of delay. The Contracting Officer ihall ascertain the facts and the extent of the delay and...fact shall be final and conclusive on the parties hereto, subject only to appeal as provided In the clause of this contract entitled "Disputes." (d)...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1979
...the facts and the extent of the delay and extend Title 41 — Public Contracts, Property Management the time for completing the work when, in his judgment,...parties subject only to appeal as provided in the clause of this contract entitled "Disputes." ' (e) If, after notice of termination of the Contractor's...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1978
...days from the beginning of the delay unless otherwise specified), notifies the Contracting Officer of the causes of delay. The Contracting Officer shall...judgment, the findings of fact justify such an extension. Where the Contractor's right to proceed with all or part of the work is terminated within less than...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1983
...days from the beginning of the delay unless otherwise specified), notifies the Contracting Officer of the causes of delay. The Contracting Officer shall...judgment, the findings of fact justify such an extension. Where the Contractor's right to proceed with all or part of the work is terminated within less than...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1964
...Officer in writing of the causes of delay. The Contracting Officer shall ascertain the facts and ihe extent of the delay and extend the time for completing...fact shall be final and conclusive on the parties hereto, subject only to appeal as provided in Clause 3 hereof. . DISPUTES.— Дну dispute concerning...