" If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted by an act of the Contracting Officer in the administration of... "
The Code of Federal Regulations of the United States of America - Page 242
1977
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1979 - 1186 pages
...Officer in the administration of this contract, which act is not expressly or impliedly authorized by this contract, or by his failure to act within the time specified in this contract (or within a reasonable time if no time is specified), an adjustment (excluding profit) shall be made for...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1971 - 850 pages
...Officer in the administration of the contract, or by his failure to act within the time specified In the contract (or if no time Is specified within a reasonable time), an adjustment shall be made by the Contracting Officer for any Increase in the cost of performance of the contract (excluding profit)...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1970 - 984 pages
...Officer in the administration of this contract, which act is not expressly or Implledly authorized by this contract, or by his failure to act within the time specified in this contract (or within a reasonable time if no time Is specified), and adjustment (excluding profit) shall be made...
Full view - About this book

Standard Specifications for Construction of Roads and Bridges on Federal ...

United States. Bureau of Public Roads - Bridges - 1969 - 472 pages
...or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted by an act of the Contracting Officer in the administration...if no time is specified, within a reasonable time), and adjustment shall be made for any increase in the cost of performance of this contract (excluding...
Full view - About this book

Department of Agriculture: Appropriations for 1962 ..., Volume 1, Part 1

United States. Congress. House. Committee on Appropriations - 1961 - 1228 pages
...Officer in the administration of the contract, or by his failure to act within the time specified in the contract (or if no time is specified, within a reasonable time), an adjustment shall be made by the Contracting Officer for any increase in the cost of performance of the contract (excluding profit)...
Full view - About this book

Air Force Intercontinental Ballistic Missile Base Construction Program ...

United States. Congress. House. Committee on Appropriations, United States. Congress. House. Committee on Appropriations. Subcommittee on Military Construction - Intercontinental ballistic missile bases - 1961 - 386 pages
...Officer in the administration of the contract, or by his failure to act within the time specified in the contract (or if no time is specified, within a reasonable time), an adjustment shall be made by the Contracting Officer for any increase in the cost of performance of the contract (excluding profit)...
Full view - About this book

Air Force Intercontinental Ballistics Missile Base Construction Program ...

United States. Congress. House. Appropriations - 1961 - 336 pages
...Officer in the administration of the contract, or by his failure to act within the time specified in the contract (or if no time is specified, within a reasonable time), an adjustment shall be made by the Contracting Officer for any increase in the cost of performance of the contract (excluding profit)...
Full view - About this book

Decisions of the United States Department of the Interior, Volume 82

United States. Department of the Interior - Natural resources - 1975 - 874 pages
...or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted by an act of the Contracting Officer in the administration...time), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by such unreasonable...
Full view - About this book

Decisions of the United States Department of the Interior, Volume 81

United States. Department of the Interior - Natural resources - 1975 - 1126 pages
...or any part of the work IB, for an unreasonable period of time, suspended, delayed, or interrupted by an act of the Contracting Officer in the administration...this contract (or If no time is specified, within n reasonable time), an adjustment shall he made for any increase in the cost of performance of this...
Full view - About this book

Decisions of the United States Department of the Interior, Volume 75

United States. Department of the Interior - Natural resources - 1969 - 586 pages
...Officer in the administration of the contract, or by his failure to act within the time specified in the contract (or if no time is specified, within a reasonable time), an adjustment shall be made by the Contracting Officer for any increase in the cost of performance of the contract (excluding profit)...