| Aeronautics - 1970 - 704 pages
...prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's...Contractor from proceeding with the contract as changed. In the foregoing clause the period of "30 days" within which any claim for adjustment must be asserted... | |
| United States. Congress. Senate. Labor and Public Welfare - 1971 - 834 pages
...receive and act upon any such claim asserted at any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute...Contractor from proceeding with the contract as changed. Rights in Data (a) The Contractor shall not include in the information, data and reports in Section... | |
| Administrative law - 1971 - 240 pages
...any such claim asserted at any time prior to final payment under this contract. Failure to agree upon any adjustment shall be a dispute concerning a question...Contractor from proceeding with the contract as changed: Provided, however, That the rights of the Government under this clause in no way diminish the rights... | |
| Administrative law - 1972 - 926 pages
...payment under this contract. Where the coet of property made obsolete or excess as result of a change la Included In the Contractor's claim for adjustment,...Contractor from proceeding with the contract as changed. In the foregoing clause, the period of "30 days" within which any claim for adjustment must be asserted... | |
| United States. General Accounting Office - Finance, Public - 1973 - 1288 pages
...changed by any such order, an equitable adjustment shall be made in the contract price or deliver}! schedule, or both, and the contract shall be modified...Contractor from proceeding with the contract as changed. You maintain that the changes in specifications and delivery accomplished by modification P00123 to... | |
| Administrative law - 1973 - 636 pages
...of a change Is Included In the Contractor's claim for adjustment, the Contracting Officer shall hare the right to prescribe the manner of disposition of...Contractor from proceeding with the contract as changed. 13. .NOTICE TO TBK GOVERNMENT OF DELATE Whenever the Contractor has knowledge that any actual or potential... | |
| Administrative law - 1973 - 344 pages
...receive and act upon any such claim asserted at any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute...the Contractor from proceeding with the contract as modified. (b) In the foregoing clause the period of "sixty (60) days" within which any claim for adjustment... | |
| |