| United States. Congress. House. Committee on Education and Labor - Minimum wage - 1956 - 582 pages
...paid a rate of wages less than the rate of -wages required by the contract to be paid as aforesaid, the Government may, by written notice to the contractor,...or such part of the work as to which there has been a failure to pay said required wages and to prosecute the work to completion by contract or otherwise,... | |
| United States. Congress. House. Committee on Education and Labor - Clerks (Retail trade) - 1956 - 418 pages
...paid a rate of wages less than the rate of wages required by the contract to be paid as aforesaid, the Government may, by written notice to the contractor,...or such part of the work as to which there has been a failure to pay said required wages and to prosecute the work to completion by contract or otherwise,... | |
| United States. Bureau of Public Roads - Highway law - 1960 - 236 pages
...paid a rate of wages less than the rate of wages required by the contract to be paid as aforesaid, the Government may, by written notice to the contractor,...or such part of the work as to which there has been a failure to pay said required wages and to prosecute the work to completion by contract or otherwise,... | |
| Administrative law - 1961 - 672 pages
...insure its completion within the time specified in this contract, or any extension thereof, or fails to complete said work within such time, the Government...same to completion, by contract or otherwise, and the Contractor and his sureties shall be liable to the Government for any excess cost occasioned the... | |
| United States. Congress. House. Committee on Appropriations - 1961 - 1228 pages
...insure its completion within the time specified in this contract, or any extension thereof, or fails to complete said work within such time, the Government...same to completion, by contract or otherwise, and the Contractor and his sureties shall bo liable to the Government for any excess cost occasioned the... | |
| United States. Congress. House. Appropriations - 1961 - 336 pages
...insure its completion within the time specified in this contract, or any extension thereof, or fails to complete said work within such time, the Government...same to completion, by contract or otherwise, and the Contractor and his sureties shall be liable to the Government for any excess cost occasioned the... | |
| Administrative law - 1961 - 576 pages
...construction contracts. TERMINATION FOR DEFAULT — DAMAGES FOR DELAY — TIME EXTENSIONS (SEPT. 1958) (a) If the Contractor refuses or falls to prosecute...may, by written notice to the Contractor, terminate its right to proceed with the work or such part of the work as to which there has been delay. In such... | |
| United States. Department of the Army - Government purchasing - 1961 - 346 pages
...paid a rate of wages less than the rate of wages required by the contract to be paid as aforesaid, the Government may, by written notice to the contractor,...or such part of the work as to which there has been a failure to pay said required wages and to prosecute the work to completion by contract or otherwise,... | |
| United States. Department of the Interior - Natural resources - 1973 - 936 pages
...by telegram dated September 28, 1965 (Exhibit Xo. 213). 30G «" "5. TERMINATION FOR DEFAULT • * * "(a) If the Contractor refuses or falls to prosecute...Contractor, terminate his right to proceed with the work • » •. (d) The Contractor's right to proceed shall not be so terminated nor the Contractor charged... | |
| |