" If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted by an act of the Contracting Officer in the administration of... "
Code of Federal Regulations: Containing a Codification of Documents of ... - Page 238
1977
Full view - About this book

The GSA System for Construction Management

United States. Public Buildings Service - Building - 1975 - 50 pages
...delayed, or interrupted by an act of the Contracting Officer in the administration of the project, or by his failure to act within the time specified...time), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by such unreasonable...
Full view - About this book

Alaskan Air Transport: Hearing Before a Subcommittee of the Committee on ...

United States. Congress. Senate. Committee on Appropriations - Aeronautics, Commercial - 1975 - 124 pages
...suspended, delayed or interrupted by an act of the NAVY in the administration of this contract, or by failure to act within the time specified in this contract...time, an adjustment shall be made for any increase in the in the. cost of performance of this contract excluding profit necessarily caused by such unreasonable...
Full view - About this book

Alaskan Air Transport, Fiscal Year 1976, Special Hearing Before ... 94-1, on ...

United States. Congress. Senate. Appropriations Committee - 1975 - 124 pages
...suspended, delayed or interrupted by an act of the NAVY in the administration of this contract, or by failure to act within the time specified in this contract...time, an adjustment shall be made for any increase in the in the cost of performance of this contract excluding profit necessarily caused by such unreasonable...
Full view - About this book

Oversight Hearings on Construction on Trans-Alaska Pipeline: Hearings Before ...

United States. Congress. House. Committee on Interior and Insular Affairs. Subcommittee on Public Lands - Petroleum - 1975
...or any pnrt of the work is, for an unreasonable period of time , suspended, delayed, or interrupted by an act of the Contracting Officer in the administration...this contract, or by his failure to act within the tiim specified in this contract, (or if no time is specified, within a reasonable titts), an adjustment...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1962
...Officer in the administration of the contract, or by his failure to act within the time specified in the contract (or if no time is specified, within a reasonable time) , an adjustment shall be made by the Contracting Officer for any increase in the cost of performance of the contract (excluding profit)...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1977
...is, for an unreasonable period of time, suspended, delayed, or interrupted by an act of the Owner in administration of this contract, or by his failure...time), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by such unreasonable...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1978
...is, for an unreasonable period of time, suspended, delayed, or interrupted by an act of the Owner in administration of this contract, or by his failure...time), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by such unreasonable...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1981
...or any Bart of the work is, for an unreasonable period of time, suspended, delayed, or interrupted by an act of the Contracting Officer in the administration...contract, or by his failure to act within the time apecified in this contract for if no time is specified, within a reasonable time), an adjustment shall...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1981
...suspended or delayed by an aet of the Contracting Officer m the administration of this contract. or by h:s failure to act within the time specified in this contract (or if no time is specified, within .1 reasonable time), an adjustment shall be made for any increase in cost of performance of this contract...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1982
...adjustments. Insert the clause prescribed by FPR 1-7.102-20, modified as set forth in 9-7.102-20. 9-7.802-21 Suspension of work. SUSPENSION OF WORK...reasonable time), an adjustment shall be made for any recreate in coll of performance of Ihis contract (excluding profit) necessarily caused by such unreaionabk...