" Contractor for adjustment under this clause must be asserted within thirty (30) days from the date of receipt by the Contractor of the notification of change; provided, however, that the Contracting Officer, if he decides that the facts justify such action,... "
Code of Federal Regulations: Containing a Codification of Documents of ... - Page 287
1979
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1976 - 1228 pages
...Contractor for adjustment under this clause must be asserted within thirty (30) days from the dale of receipt by the Contractor of the notification of...to any adjustment shall be a dispute concerning a question of fact within the meaning of the "Disputes" clause of this contract. However, nothing in...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1971 - 824 pages
...Contracting Officer, If he decides that the facts Justify such action, may receive and act upon an; such claim asserted at any time prior to final payment...Contractor from proceeding with the contract as changed. In the foregoing clause, the period of "thirty (30) days" within which any claim for adjustment must...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1982 - 532 pages
...Contractor for adjustment under this clause must be asserted within thirty (30) days from the date or receipt by the Contractor of the notification of change;...to any adjustment shall be a dispute concerning a question of fact within, the meaning of the "Disputes" clause of this contract. However, nothing in...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1972 - 914 pages
...Any claim by the Contractor for adjustment under this clause must be asserted within sixty (60) days from the date of receipt by the Contractor of the...contract. Failure to agree to any adjustment shall bea dispute concerning a question of fact within the meaning of the clause of this contract entitled...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1977 - 944 pages
...by the Contractor of the notification of change: Prodded, however, That the Contracting Officer, It he decides that the facts justify such action, may...clause of this contract entitled "Disputes." However, except as provided In paragraph (c), below, nothing In this clause shall excuse the Contractor from...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1968 - 1348 pages
...decides that the facts justify such action, may receive and act upon any such claim asserted at any tune prior to final payment under this contract. Failure...contractor from proceeding with the contract as changed. § 2-7.250-3 Limitation of cost. LIMITATION or COST (a) It Is estimated that the total cost to the...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1980 - 874 pages
...that the facts justify such action, may receive and act upon any such claim asserted at any time pi.tr to final payment under this contract. Failure to agree...Contractor from proceeding with the contract as changed. 9. FEDERAL, STATE, AND LOCAL TAXES (Text of this clause is set forth In PPR 111.401-1) 10. DEFAULT...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1993 - 664 pages
...the Contracting Officer shall have the right to prescribe the manner of disposition of such property. Failure to agree to any adjustment shall be a dispute...from proceeding with the contract as changed. (End of clause) CLAUSE No. 20— RETROCESSION (JUNE 1977) (a) The Indian tribe that initially requested...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 2000 - 568 pages
...the Contracting Officer shall have the right to prescribe the manner of disposition of such property. Failure to agree to any adjustment shall be a dispute...from proceeding with the contract as changed. (End of clause) CLAUSE No. 14— NOTICE TO THE GOVERNMENT OF DELAYS (JUN 1977) Whenever the Contractor has...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1971 - 850 pages
...action, may receive and act upon any such claim asserted at any time prior to final payment under thla contract. Failure to agree to any adjustment shall...Contractor from proceeding with the contract as changed. (b> If this contract Is executed by an A.IX). Washington Contracting Officer, valid change orders may...
Full view - About this book




  1. My library
  2. Help
  3. Advanced Book Search
  4. Download EPUB
  5. Download PDF