...any appeal proceeding under this clause, the Contractor shall be afforded an opportunity to be heard and to offer evidence in support of his appeal. Pending final decision of a dispute hereunder, the Contractor shall proceed diligently with the performance of the contract and in accordance with the... | |
| Administrative law - 1974 - 640 pages
...any appeal proceeding under this clause, the Contractor shall be afforded an opportunity to be heard and to offer evidence in support of his appeal. Pending final decision of a dispute hereunder, the Contractor shall proceed diligently with the performance of the contract and In accordance with the... | |
| United States. Marine Corps - 1949 - 858 pages
...offer evidence in support of its appeal. Pending final decision of a dispute hereunder, the Contractor shall proceed diligently with the performance of the...accordance with the Contracting Officer's decision. c. Running Term Contracts for Accumulation Other Than Food Refuse. When all property of a particular... | |
| Administrative law - 1971 - 664 pages
...not supported by substantial evidence. Pending final decision of a dispute hereunder, the Contractor shall proceed diligently with the performance of the...contract and in accordance with the Contracting Officer's de4. RESPONSIBILITY OF CONTRACTOR At his own expense the Contractor shall: (a) obtain any necessary... | |
| Administrative law - 1964 - 432 pages
...offer evidence in support of his appeal. Pending final decision of a dispute hereunder, the Contractor shall proceed diligently with the performance of the...contract and in accordance with the Contracting Officer's derision. (b) This Disputes clause does not preclude consideration of questions of law in connection... | |
| Administrative law - 1976 - 888 pages
...any appeal proceeding under this Section, the appellant shall be afforded an opportunity to be heard and to offer evidence in support of his appeal. Pending final decision of a dispute hereunder, both parties shall proceed diligently with the performance of the Agreement and in accordance with... | |
| Administrative law - 1979 - 1390 pages
...any appeal proceeding under this Section, the appellant shall be afforded an opportunity to be heard and to offer evidence in support of his appeal. Pending final decision of a dispute hereunder, both parties shall proceed diligently with the performance of the Contract and in accordance with the... | |
| Administrative law - 1976 - 1202 pages
...any appeal proceeding under this clause, the Contractor shall be afforded an opportunity to be heard and to offer evidence in support of his appeal. Pending final decision of a dispute hercunder, the Contractor shall proceed diligently with the performance of the contract and in accordance... | |
| Administrative law - 1981 - 524 pages
...any appeal proceedings under this clause, the Contractor shall be afforded an opportunity to be heard and to offer evidence in support of his appeal. Pending final decision of a dispute liereundcr, the Contractor shall proceed diligently with the performance of Ihc contract and in accordance... | |
| Administrative law - 1967 - 2356 pages
...offer evidence in support of his appeal. Pending final decision of a dispute hereunder, the Contractor shall proceed diligently with the performance of the contract and In accordance with the Contracting Ofncen decision. (b) This "Disputes" clause does not preclude consideration of law questions in connection... | |
| |