" Contractor for adjustment under this clause must be asserted within thirty (30) days from the date of receipt by the Contractor of the notification of change; provided, however, that the Contracting Officer, if he decides that the facts justify such action,... "
Code of Federal Regulations - Page 410
1965
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1981
...the Contractor for adjustment under thU clause must be asserted within thirty (30) days from the dale of receipt by the Contractor of the notification of...to any adjustment shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled "Disputes." However, except...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1981
...NASA PROCUREMENT REGULATION CONTRACT CLAUSES days from the date of receipt by the Contractor of tht notification of change; provided, however, that the...to any adjustment shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled "Disputes." However. nothing...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1983
...writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor...to any adjustment shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled "Disputes." However, nothing...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 151

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1963
...writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor...to any adjustment shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled "Disputes." However, nothing...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1984
...Contractor for adjustment under this clause must be asserted within thirty (30) days from the dale of receipt by the Contractor of the notification of...of the "Disputes" clause of this contract. However, this clause shall excuse the Contractor from proceeding with the contract as changed Instructions in...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1984
...notification of change; Proridtd. however, that the Contracting Officer, if he decides that the facia justify such action, may receive and act upon any...to any adjustment shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled "Disputes." However, nothing...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1988
...applicable schedule of rates and the contract shall be modified in writing accordingly. Any claims by the Contractor for adjustment under this clause...Contractor from proceeding with the contract as changed. (End of clause) 252.247-7005 Termination. As prescribed at 247.270-9(e), insert the following clause:...
Full view - About this book

Code of Federal Regulations

Administrative law - 1971
...this contract, an equitable adjustment shall be made in the contract price, or time of performance, or both, and the contract shall be modified in writing...Contractor from proceeding with the contract as changed. 1007.5003-11 Inspection. INSPECTION (NOvEMBER 1967) All services, including the preparation of meals,...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1972
...this contract, an equitable adjustment shall be made in the contract price, or time of performance, or both, and the contract shall be modified In writing...Contractor from proceeding with the contract as changed. 1007.5003-11 Inspection. INSPECTION (NOVEMBER 1967) All services. Including the preparation of meals,...
Full view - About this book

Code of Federal Regulations

Administrative law - 1969
...this contract, an equitable adjustment shall be made in the contract price, or time of performance, or both, and the contract shall be modified in writing...Contractor from proceeding with the contract as changed. [33 FR 4179, Mar. 6, 1968] 1007.5003-11 Inspection. INSPECTION (NOVEMBER 1967) All services, including...