" Where the cost of property made obsolete or excess as result of a change is included in the Contractor's claim for adjustment, the Contracting Officer shall have the right to prescribe the manner of disposition of such property. Failure to agree to any... "
The Code of Federal Regulations of the United States of America - Page 388
1982
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1981 - 1018 pages
...receive and act upon any such claim asserted at any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute...nothing In this clause shall excuse the Contractor from proceedlna with the contract as changed. (End of clause) In the foregoing clause, the period of "sixty...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1981 - 1018 pages
...receive and act upon any such claim asserted at any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute'..."Disputes." However, nothing In this clause shall excuse th« Contractor from proceedlna with the contract as changed. (End of clause) In the foregoing clause,...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1983 - 806 pages
...prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's...Contractor from proceeding with the contract as changed. Clause No. 20— Retrocession. (a) The Indian tribe that initially requested this contract may also...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1984 - 764 pages
...payment under this contract. Where the cost of property made obsolete or excess as a result of a chsnge is included in the Contractor's claim for adjustment,...Contractor from proceeding with the contract as changed. In the foregoing clause the period of "30 days" within which any claim for adjustment must be asserted...
Full view - About this book

Justice Department Investigations of Defense Procurement Fraud: A Case Study ...

Armed Forces - 1988 - 976 pages
...Contractor's claim for adjustment, the Contracting Officer shall have the right to prescribe the "(f) Failure to agree to any adjustment shall be a dispute...Contractor from proceeding with the contract as changed as herein provided." The "Changes" provision of the contract is intended to permit the Government to...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1961 - 576 pages
...Government in accordance therewith; (ii) method of shipment or packing; and (iii) place of delivery. If any such change causes an increase or decrease...contract entitled "Disputes." However, nothing in thia clause shall excuse the Contractor from proceeding with the contract as changed. In the foregoing...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1968 - 682 pages
...by the Contractor for adjustment under this clause must be asserted within 30 days from the date or receipt by the Contractor of the notification of change,...Contractor from proceeding with the contract as changed. In the foregoing clause, the period of "30 flays" within which any claim for adjustment must be asserted...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1965 - 806 pages
...by the Contractor for adjustment under this clause must be asserted within 30 days from the date or receipt by the Contractor of the notification of change,...Contractor from proceeding with the contract as changed. In the foregoing clause, the period of "30 days" within which any claim for adjustment must be asserted...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1966 - 984 pages
...by the Contractor for adjustment under this clause must be asserted within 30 days from the date or receipt by the Contractor of the notification of change,...Contractor from proceeding with the contract as changed. In the foregoing clause, the period of "30 days" within which any claim for adjustment must be asserted...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1972 - 858 pages
...by the Contractor for adjustment under this clause must be asserted within 30 days from the date or receipt by the Contractor of the notification of change,...Contractor from proceeding with the contract as changed. In the foregoing clause, the period of "30 days" within which any claim for adjustment must be asserted...
Full view - About this book