| Administrative law - 1966 - 648 pages
...progress in the prosecution of the work hereunder which endangers such performance) if such failure arises out of causes beyond the control and without...Contractor. If the failure to perform is caused by the failure of a subcontractor to perform or make progress, and if such failure arises out of causes beyond... | |
| Administrative law - 1972 - 958 pages
...progress in the prosecution of the work hereunder which endangers such performance) if such failure arises out of causes beyond the control and without...Contractor. If the failure to perform Is caused by the failure of a subcontractor to perform or make progress, and if such failure arises out of causes beyond... | |
| Administrative law - 1963 - 876 pages
...progress in the prosecution of the work hereunder which endangers such performance) if such failure arises out of causes beyond the control and without...Contractor If the failure to perform Is caused by the failure of a subcontractor to perform or make progress, and If such failure arises out of causes beyond... | |
| Administrative law - 1967 - 706 pages
...progress in the prosecution of the work hereunder which endangers such performance) if such failure arises out of causes beyond the control and without...Contractor. If the failure to perform is caused by the failure of a subcontractor to perform or make progress, and if such failure arises out of causes beyond... | |
| Administrative law - 1969 - 770 pages
...progress in the prosecution of the work hereunder which endangers such performance) if such failure arises out of causes beyond the control and without...Contractor. If the failure to perform is caused by the failure of a subcontractor to perform or make progress, and if such failure arises out of causes beyond... | |
| Administrative law - 1967 - 674 pages
...progress in the prosecution of the work hereunder which endangers such performance) if such failure arises out of causes beyond the control and without...Contractor. If the failure to perform Is caused by the failure of a subcontractor to perform or make progress, and if such failure arises out of causes beyond... | |
| Administrative law - 1970 - 808 pages
...the fault or negligence of the Contractor. Such causes may include, but are not restricted to, acte of God or of the public enemy, acts of the Government...a subcontractor, and if such default arises out of clauses beyond the control of both the Contractor and subcontractor, and without the fault or negligence... | |
| Aeronautics - 1970 - 776 pages
...Contractor. Such causes may include, but are not restricted to: acts of God or of the public enemy, act* of the Government in either its sovereign or contractual...Contractor. If the failure to perform is caused by the failure of a subcontractor to perform or make progress, and if such failure arises out of causes beyond... | |
| Administrative law - 1972 - 694 pages
...not restricted to, acts of God or of the public enemy, acts of the Government in either its sovertgn or contractual capacity, fires, floods, epidemics,...Contractor. If the failure to perform is caused by the failure of a subcontractor to perform or make progress, and if such failure arises out of causes beyond... | |
| |