| Administrative law - 1973 - 1066 pages
...end of the period of work stoppage: Provided, That If the Orante Officer decides the circumstances justify such action, he may receive and act upon any...asserted at any time prior to final payment under this grant. (c) If a stop- work order Is not canceled and the work covered by such order Is terminated,... | |
| Administrative law - 1973 - 1162 pages
...end of the period of work stoppage: Provided, That if the Grant* Officer decides the circumstances justify such action, he may receive and act upon any...asserted at any time prior to final payment under this grant. (c) If a stop-work order Is not canceled and the work covered by such order Is terminated, the... | |
| Administrative law - 1972 - 914 pages
...after the end of the period of work stoppageProvided, That, If the Contracting Offloer decides the facts Justify such action, he may receive and act...asserted at any time prior to final payment under Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning... | |
| Administrative law - 1965
...days after the termination of such suspension; Provided. That If the Contracting Officer decides the facts justify such action, he may receive and act upon any such claim asserted at any time prior to flnal payment under this contract. Failure to agree to any adjustment shall be a dispute concerning... | |
| Administrative law - 1976 - 1202 pages
...provided, however, that the Contracting Officer, if he decides that the facts justify such action, may receive and act upon any such claim asserted at...any time prior to final payment under this contract. Where the cost of property made obsolete or excess as result of a change is included in the Contractor's... | |
| Administrative law - 1976 - 580 pages
...Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may receive and act upon any such claim asserted at any time prior to final payment under the contract. Failure to agree to any adjustment shall be considered a dispute concerning a question... | |
| Administrative law - 1974 - 1020 pages
...after the end of the period of work stoppage : Provided, That, If the Contracting Officer de. cides the facts justify such action, he may receive and act upon any such claim asserted at any tune prior to fl"*' payment under this contract. (c) If a Stop Work Order Is not canceled and the work... | |
| Administrative law - 1974 - 640 pages
...after the end of the period of work stoppage; provided that, If the Contracting Officer decides the facts justify such action, he may receive and act upon any such claim asserted at any tune prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute... | |
| Administrative law - 1970 - 788 pages
...after the end of the period of work stoppage : Provided, That, if the Contracting Officer decides the facts Justify such action, he may receive and act upon any such claim asserted at any tune prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute... | |
| Administrative law - 1967 - 2356 pages
...Provided, however, That the Contracting Officer, If he decides that the fact! justify such action, may receive and act upon any such claim asserted at any time prior to anal payment under this contract. Failure to agree to any adjustment shall be a dispute concerning... | |
| |