The School Executive's Guide to Performance Contracting |
From inside the book
Results 6-10 of 24
Page 9
... . If , during that ten ( 10 ) day period , contractor disagrees that the student is qualified to par- ticipate because of emotional or mental reasons 8/13/70 unrelated to standardized test results , he may request 9 Contract Number 70-1.
... . If , during that ten ( 10 ) day period , contractor disagrees that the student is qualified to par- ticipate because of emotional or mental reasons 8/13/70 unrelated to standardized test results , he may request 9 Contract Number 70-1.
Page 10
... period of 10 school days or for intermittent periods totalling 20 days in any three- month period ; or parent or guardian requests removal . In all these cases , Contractor shall give written notice to the Project Director when in its ...
... period of 10 school days or for intermittent periods totalling 20 days in any three- month period ; or parent or guardian requests removal . In all these cases , Contractor shall give written notice to the Project Director when in its ...
Page 14
... Period of Performance The Contractor's effort hereunder shall be performed during the period commencing with the date of approval of the program by the Dallas Independent School District School Board and ending June 30 , 1971. The date ...
... Period of Performance The Contractor's effort hereunder shall be performed during the period commencing with the date of approval of the program by the Dallas Independent School District School Board and ending June 30 , 1971. The date ...
Page 16
... period of ap- proximately six ( 6 ) weeks or thirty ( 30 ) hours of instruc- tion in each subject . 3.02 Consideration and Payment This section defines the consideration and payment to the Contractor . The total maximum amount available ...
... period of ap- proximately six ( 6 ) weeks or thirty ( 30 ) hours of instruc- tion in each subject . 3.02 Consideration and Payment This section defines the consideration and payment to the Contractor . The total maximum amount available ...
Page 18
... period being evaluated , it shall be assumed that said student's score is the same as the average test or gain score , whichever is appropriate , for all students in that Accelerated Learning Achievement Center or the same grade level ...
... period being evaluated , it shall be assumed that said student's score is the same as the average test or gain score , whichever is appropriate , for all students in that Accelerated Learning Achievement Center or the same grade level ...
Other editions - View all
Common terms and phrases
1817 LIBRARIES Accelerated Learning Achievement Achievement Motivation and/or assessment Auditing Contractor August 13 Banneker basis Blaschke Central Daylight Century agrees Century's classroom Communications and Mathematics Contractor agrees cost effectiveness criterion-referenced tests Dallas Independent School decision determine documents Education Audit Group equipment evaluation funds grade level Grand Rapids GUARANTEED STUDENT PERFORMANCE Independent School District instructional system interim performance test interim test Junior High Learning Achievement Centers Management Support Group mance Mathematics programs measure Mecklenburger Meredith Corporation munications and Mathematics objectives operations payment percent PERFORMANCE IN EDUCATION personnel Phi Delta Kappan planning post-test procedures Project Administrator Project Director Project Manager Rand Rand Corporation Reading Communications reimbursement reports Request for Proposal responsible schedule school board school system scores specific staff student achievement student dropouts subcontractor submit teachers Texarkana Thiokol Chemical Corporation Thiokol Corporation thirty 30 tract tractor unit price UNIV
Popular passages
Page 21 - Except as otherwise provided in this contract, any dispute concerning a question of fact arising under this contract which is not disposed of by agreement shall be decided...
Page 21 - Such causes may include, but are not restricted to, acts of God or of the public enemy, acts of the Government m either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather...
Page 23 - Contractor shall not be liable for any excess costs if the failure to perform the contract arises out of causes beyond the control and without the fault or negligence of the Contractor. Such causes may include, but are not restricted to, acts of God or of the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather...
Page 22 - The decision of the Secretary or his duly authorized representative for the determination of such appeals shall be final and conclusive unless determined by a court of competent Jurisdiction to have been fraudulent, or capricious, or arbitrary, or so grossly erroneous as necessarily to imply bad faith, or not supported by substantial evidence.
Page 22 - ... agencies maintained by the Contractor for the purpose of securing business. For breach or violation of this warranty the Government shall have the right to annul this contract without liability, or In Its discretion to deduct from the contract price or consideration, or otherwise recover, the full amount of such commission, percentage, brokerage, or contingent fee.
Page 23 - Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather; but in every case the failure to perform must be beyond the control and without the fault or negligence of the Contractor.
Page 20 - The Government, through any authorized representatives, has the right, at all reasonable times, to Inspect, or otherwise evaluate the work performed or being performed hereunder and the premises in which it is being performed. If any Inspection, or evaluation Is made by the Government on the premises of the Contractor or a subcontractor, the Contractor shall provide and shall require...
Page 21 - Except with respect to defaults of subcontractors, the Contractor shall not be in default by reason of any failure in performance of this contract In accordance with its terms (including any failure by the Contractor to make progress in the prosecution of the work hereunder which endangers such performance) If such failure arises out of causes beyond the control and without the fault or negligence of the Contractor. Such causes may Include, but are not restricted to: Acts...
Page 21 - ... is one of a number of subcontracts under this contract with a single subcontractor for the same or related supplies or services which, in the aggregate are expected to exceed $100,000 ; the advance notification required by (a) above shall include...
Page 20 - ... records") to the extent and in such detail as will properly reflect all net costs, direct and indirect, of labor, materials, equipment, supplies and services, and other costs and expenses of whatever nature for which reimbursement is claimed under the provisions of this contract.