its demonstration in accordance with paragraph (b)(5) of this section.

(8) Upon request by the recipient of the proposed prohibition order, the combined public comment periods provided for in this section may be reduced to a minimum of forty-five (45) days from the time of publication of the proposed order.

(9) OFE may terminate a prohibition order proceeding at any time prior to the date upon which a final order shall become effective. Should OFE terminate the proceeding, it will notify the proposed order recipient, and publish a notice in the FEDERAL REGISTER.

(c) Decision to issue a final order. (1) OFE will base its determination to issue an order on consideration of the whole record or those parts thereof cited by a party and supported by and in accordance with reliable, probative and substantial evidence.

(2) OFE shall include in the final order a written statement of the pertinent facts, a statement of the basis upon which the final order is issued, a recitation of the conclusions regarding the required findings and qualifications for exemptions. The final order shall state the effective date of the prohibition contained therein. If it is demonstrated that the facility would have been granted a temporary exemption, the effective date of the prohibition contained in the final order shall be delayed until such time as the temporary exemption would have terminated. If it is demonstrated that a facility will need a period of time to comply with the final order, the effective date of the prohibition contained in the final order may be delayed, in OFE's discretion, so as to allow an order recipient to comply with the final order.

(3) OFE will enclose with a copy of the final order, where appropriate, a schedule of steps that should be taken by a stated date (a compliance schedule) to ensure that the affected facility will be able to comply with the prohibitions stated in the order by the effective date of the prohibition contained in the final order. The compliance schedule may require the affected person to take steps with regard to a unit 60 days after service of the final order. (4) A copy of the final order and a summary of the basis therefore will be

published in the FEDERAL REGISTER. The order will become effective 60 days after publication in the FEDERAL REGISTER.

(d) Request for order. (1) A proceeding for issuance of a prohibition order to a specific unit may be commenced by OFE, in its sole discretion, in response to a request for an order filed by the owner or operator of a facility.

(2) A petition requesting OFE to commence a prohibition order proceeding should include the following information for all units to be covered by the prohibition order:

(i) A statement of the reasons the owner or operator is seeking the issuance of a prohibition order; and

(ii) Sufficient information for OFE to make the findings required by section 301(b) of FUA.

(3) If OFE determines to accept the request, OFE shall publish a proposed order in the FEDERAL REGISTER together with a statement of the reasons for the order.

(Department of Energy Organization Act, Pub. L. 95-91, 91 Stat. 565 (42 U.S.C. 7101 et seq.); Energy Supply and Environmental Coordination Act of 1974; Pub. L. 93-319, as amended by Pub. L. 94-163, Pub. L. 95-70, (15 U.S.C. 719 et seq.); Powerplant and Industrial Fuel Use Act of 1978, Pub. L. 95-620, 92 Stat. 3269 (42 U.S.C. 8301 et seq.); Omnibus Budget Reconciliation Act of 1981, (Pub. L. 97-35); E.O. 12009, 42 FR 46267, Sept. 15, 1977)

[46 FR 59889, Dec. 7, 1981, as amended at 47 FR 17042, Apr. 21, 1982; 47 FR 50848, Nov. 10, 1982; 54 FR 52892, Dec. 22, 1989]

§ 501.52 Prohibitions by order-certifying powerplants.

(a) OFE may prohibit by order the use of petroleum or natural gas as a primary energy source or in amounts in excess of the minimum amount necessary to maintain reliability of operation consistent with maintaining reasonable fuel efficiency in an existing powerplant if the owner or operator of the powerplant certifies, and OFE concurs in such certification in accordance with the requirements of §§ 504.5, 504.6 and 504.8.

(b) Notice of order and participation. (1) OFE may hold a conference with the

197-031 D-01--2

proposed order recipient, at the recipient's election, prior to issuing the proposed order. The conference may resolve any questions regarding the certification required by section 301 of the Act, as amended, and §§ 504.5, 504.6, and 504.8, and OFE's review and concurrence therein.

(2) Pursuant to section 701(b) of FUA, prior to the issuance of a final order to a certifying powerplant owner or operator, OFE must publish in the FEDERAL REGISTER, a proposed prohibition order stating the reasons for such order. OFE will review all of the information submitted by a proposed order recipient within 60 days after receipt by OFE. If the certification is complete, OFE will, within 30 days after the end of the 60 day review period, publish in the FEDERAL REGISTER a Notice of Acceptance of certification together with a proposed prohibition order stating therein the reasons for such order. This commences the prohibition order proceeding. If OFE does not believe it is able to concur in the certification, OFE shall notify the proposed order recipient and shall publish a Notice of Proposed Non-Concurrence in the FEDERAL REGISTER within 30 days after the end of the 60 day review period. If OFE finds that the certification with compliance schedule is incomplete, OFE will notify the proposed prohibition order recipient as to the deficiencies, and provide an additional period of 30 days for the certification to be amended and resubmitted. If a complete certification is not submitted within this period, the proceeding shall be terminated in accordance with §501.52(b)(5). OFE will notify the proposed order recipient and other parties to the proceeding of the termination and publish a notice in the FEDERAL REGISTER. OFE, on its own motion, may extend any period of time by publishing a notice to that effect in the FEDERAL REGISTER.

(3) The publication of the Notice of Acceptance or Notice of Proposed NonConcurrence commences a period of 45 days during which interested persons may submit written comments or request a public hearing. During this period, the recipient of the proposed order and any other interested person may submit any evidence that they

of

have available relating to the proposed order, the certification or the concurrence that OFE must make. A proposed order recipient may submit additional new evidence at any time prior to the close of the public comment period which follows the commencement the proceeding or prior to the close of the record of any public hearing, whichever occurs later. A request for an extension of the 45 day period may be granted at OFE's discretion. In the case of a Notice of Acceptance, as set forth in §504.9, no final prohibition order can be issued until any necessary environmental review pursuant to the National Environmental Policy Act of 1969, 42 U.S.C 4321 et seq. (NEPA) has been completed. Upon completion of the NEPA review and unless OFE determines on the basis of the record of the proceeding that the certification fails to meet the requirements of §§ 504.5, 504.6, and 504.8, OFE shall publish a final prohibition order, together with the information required by paragraph (c) of this section. In the case of a Notice of Proposed Non-Concurrence, at the end of the 45 day comment period, OFE will notify the proposed order recipient and parties to the proceeding and publish a final Notice of Non-Concurrence in the FEDERAL REGISTER, if OFE determines it cannot concur in the certification based upon additional information submitted during the proceeding. If, at the end of the 45 day period, OFE believes it can concur in the certification, OFE will notify the proposed order recipient and parties to the proceeding and publish a Notice of Acceptance followed by a new 45 day comment period.

(4) If a hearing has been requested, OFE shall provide interested persons with an opportunity to present oral data, views and arguments at a public hearing held in accordance with subpart C of this part. The hearing may consider, among other matters, the sufficiency of the certification of the owner or operator of the powerplant required by section 301 of FUA, as amended, and §§ 504.5, 504.6, and 504.8 of these regulations.

(5) OFE may terminate a prohibition order proceeding at any time prior to the date upon which a final prohibition order is issued whenever OFE believes,

from any information contained in the record of the proceeding, that the certification does not meet the requirements of section 301 of the Act, as amended, or §§ 504.5, 504.6, and 504.8 of these regulations. If OFE terminates the proceeding or publishes a final Notice of Non-Concurrence, or the proposed order recipient fails to submit a complete certification, OFE will notify the proposed order recipient and other parties to the proceeding and publish a notice in the FEDERAL REGISTER. In such event, the proposed order recipient may submit a new certification under any provision of section 301 of the Act, as amended, at a later date. Specifically, a Notice of Non-Concurrence under either section 301(b) or 301(c) shall not affect a proposed order recipient's ability to make a certification under the other subsection.

(c) Record and decision to issue a final order. (1) OFE will base its determination to issue an order on consideration of the whole record or those parts thereof cited by a party and supported by and in accordance with reliable, probative and substantial evidence.

(2) OFE shall include in the final order a written statement of the basis upon which the final order is issued, and its concurrence in the required certification. A copy of the final order and a summary of the basis therefor will be published in the FEDERAL REGISTER. While the prohibition order is final for purposes of judicial review under section 702 of FUA, the prohibitions contained in the final order shall not become effective for purposes of amendment under section 301(d) of FUA, as amended, and § 501.52(d) of these regulations until the effective date of the prohibitions stated in the order, or, where the order is subject to one or more conditions subsequent listed in the prohibition order compliance schedule, until all its conditions are met.

(d) Amendment to certifications under §§ 504.5 and 504.6. The proposed prohibition order recipient may amend its compliance schedule under § 504.5(d), or its certification under section 301 of FUA, as amended, and §§ 504.5, 504.6 and 504.8 of these regulations in order to take into account changes in relevant facts and circumstances at any time

prior to the effective date of the prohibitions contained in the final prohibition order.

(e) Rescission of prohibition orders. The rescission or modification of final prohibition orders issued to existing electric powerplants will be governed by the procedure in §501.101 of these regulations.

(Approved by the Office of Management and Budget under control number 1903-0077) (Department of Energy Organization Act, Pub. L. 95-91, 42 U.S.C. 7101 et seq.; Energy Supply and Environmental Coordination Act of 1974, Pub. L. 93-319, as amended by Pub. L. 94-163, Pub. L. 95-70, and Pub. L. 95-620, 15 U.S.C. 719 et seq.; Powerplant and Industrial Fuel Use Act of 1978, Pub. L. 95-620, as amended by Pub. L. 97-35, 42 U.S.C. 8301 et seq.; Omnibus Budget Reconciliation Act of 1981, (Pub. L. 97-35))

[47 FR 17042, Apr. 21, 1982]

§§ 501.53-501.56 [Reserved]

Subpart F-Exemptions and Certifications

§ 501.60 Purpose and scope.

(a) (1) If the owner or operator plans to construct a new baseload powerplant and the unit will not be in compliance with the prohibition contained in section 201(a) of FUA, this subpart establishes the procedures for filing a petition requesting a temporary or permanent exemption under, respectively, sections 211 and 212 of FUA.

(2) Self-certification alternative. If the owner or operator plans to construct a new baseload powerplant not in compliance with the prohibitions contained in section 201(a) of FUA, this subpart establishes the procedures for the filing of a self-certification under section 201(d) of FUA.

(3) If the petitioner owns, operates or controls a new powerplant, this subpart provides the procedures for filing a petition requesting extension of a temporary exemption granted under sections 211 or 311 of FUA.

(4) If the petitioner owns, operates or controls a new or existing powerplant or MFBI, this subpart provides the procedures for filing a petition requesting extension of a temporary exemption granted under section 211 or section 311 of FUA.

(b) If the petition is for an extension of a temporary exemption, the petitioner must apply for this extension at least (90) days prior to the expiration of the temporary exemption.

(Department of Energy Organization Act, Pub. L. 95-91, 91 Stat. 565 (42 U.S.C. 7101 et seq.); Powerplant and Industrial Fuel Use Act of 1978, Pub. L. 95-620, 92 Stat. 3269 (42 U.S.C. 8301 et seq.); Omnibus Budget Reconciliation Act of 1981, Pub. L. 97-35; E.O. 12009, 42 FR 46267, Sept. 15, 1977)

[46 FR 59889, Dec. 7, 1981, as amended at 47 FR 50849, Nov. 10, 1982; 54 FR 52892, Dec. 22, 1989]

§ 501.61

Certification contents.

(a) A self-certification filed under section 201(d) of FUA should include the following information:

(1) Owner's name and address. (2) Operator's name and address. (3) Plant location and address. (4) Plant configuration (combined cycle, simple cycle, topping cycle, etc.) (5) Design capacity in megawatts (MW).

(6) Fuel(s) to be used by the new facility.

(7) Name of utility purchasing electricity from the proposed facility and percent of total output to be sold.

(8) Date unit is expected to be placed in service.

(9) Certification by an officer of the company or his designated representative certifying that the proposed facility:

(i) Has sufficient inherent design characteristics to permit the addition of equipment (including all necessary pollution devices) necessary to render such electric powerplant capable of using coal or another alternate fuel as its primary energy source; and

(ii) Is not physically, structurally, or technologically precluded from using coal or another alternate fuel as its primary energy source.

(b) A self-certification filed pursuant to § 501.61(a) shall be effective to establish compliance with the requirement of section 201(a) of FUA as of the date filed.

(c) OFE will publish a notice in the FEDERAL REGISTER within fifteen days reciting that the certification has been filed. Publication of this notice does

not serve to commence a public comment period.

(d) OFE will notify the owner or operator within 60 days if supporting documentation is needed to verify the certification.

[54 FR 52892, Dec. 22, 1989]

§ 501.62 Petition contents.

(a) A petition for exemption should include the following information:

(1) The name of the petitioner;

(2) The name and location of the unit for which an exemption is being requested;

(3) The specific exemption(s) being requested; and

(4) The name, address, and telephone number of the person who can supply further information.

(b) Table of contents. Include only those sections contained in the petition.

(c) Introduction. Include the following:

(1) Description of the facility under consideration;

(2) Description of the unit and fuel the petitioner proposes to burn in that unit, including the purpose of and need for the unit; and

(3) Description of the operational requirements for the unit, including size (capacity, input and output in millions of Btu's per hour), output in terms of product or service to be supplied, fuel capability, and operating mode, including capacity factor, utilization factor, and fluctuations in the load.

(d) General requirements. The evidence required under part 503 subpart B for each exemption(s) for which the petitioner is applying:

(1) No alternate power supply (§ 503.8): (2) Use of mixtures (§503.9); (3) Alternative site (§ 503.11); (4) Compliance Plan (§ 503.12); (5) Environmental impact analysis (§ 503.13);

(6) Fuels search (§ 503.14).

(e) Specific evidence. Evidence required for each exemption, segregated by exemption (part 503 subparts C and D).

(f) References. (1) Specify the reports, documents, experts, and other sources consulted in compiling the petition. Cite these sources in accordance with acceptable documentation standards,

[ocr errors]

and indicate the part of the petition to which they apply. If the source is unusual or little known, briefly describe its contents.

(2) Identify at the end of each section of the petition any information or any statement based, in whole or in part, on information or principles which, to petitioner's knowledge, represent significant innovations to or departures from generally accepted facts or principles.

(g) Appendices. Include in the appendices material which the petitioner believes substantiates any analyses fundamental to the petition, materials prepared in connection with it, and any other documents, studies, or analyses which are believed to be relevant to the decision to be made. Also, include in the appendices copies of any forms submitted as part of the petition.

(h) List of preparers. List the names with the qualifications and professional credentials of the principal contributors to the preparation of the petition. Indicate the sections or subject matters for which each principal contributor was responsible.

(i) Incorporation by reference. Pertinent information may be incorporated into the petition by reference when this can be done without impeding agency and public review. Referenced materials must be specifically identified and their contents briefly described in the petition. To incorporate by reference, the material must be submitted with the petition, or if previously submitted, the office to which it was submitted must be identified in the petition. The petitioner cannot incorporate by reference material based on proprietary data not available to OFE for review.

(Department of Energy Organization Act, Pub. L. 95-91, 91 Stat. 565 (42 U.S.C. 7101 et seq.); Powerplant and Industrial Fuel Use Act of 1978, Pub. L. 95-620, 92 Stat. 3269 (42 U.S.C. 8301 et seq.); Omnibus Budget Reconciliation Act of 1981, Pub. L. 97-35; E.O. 12009, 42 FR 46267, Sept. 15, 1977)

[46 FR 59889, Dec. 7, 1981, as amended at 47 FR 50849, Nov. 10, 1982]

§ 501.63 Notice of the commencement of an administrative proceeding on an exemption petition.

(a)(1) When a petition is accepted, OFE will publish in the FEDERAL REGISTER a Notice of Acceptance, or, in the case of a certification exemption, a Notice of Acceptance and Availability of Certification, signifying that an exemption proceeding has commenced. The notice will include a summary of the exemption petition, and publication will commence a public comment period of no less than forty-five (45) days during which interested parties may file written comments concerning the petition. In the case of a certification exemption, interested persons may request a public hearing during this period, pursuant to § 501.33.

(2) OFE will notify the appropriate State agency having apparent primary authority to permit or regulate the construction or operation of a powerplant that an exemption proceeding has commenced and will consult with this agency to the maximum extent practicable. Copies of all accepted petitions also will be forwarded to EPA, as provided in § 501.14(a).

(b) In processing an exemption petition, OFE shall comply with the requirements of the National Environmental Policy Act of 1969 (NEPA), the Council on Environmental Quality's implementing regulations, and the DOE guidelines implementing those regulations (45 FR 20694, Mar. 28, 1980). Compliance with NEPA may involve the preparation of (1) an environmental impact statement (EIS) evaluating the grant or denial of an exemption petition, (2) an environmental assessment (EA), or (3) a memorandum to the file finding that the grant of the requested petition would not be considered a major federal action significantly affecting the quality of the human environment. If an EIS is required, OFE will publish in the FEDERAL REGISTER a Notice of Intent (NOI) to prepare an EIS as soon as practicable after commencement of the proceeding. A public meeting may be held pursuant to 40