CONTRACTS—Continued
DISPUTES-Continued
Administrative decisions-Continued
Finality of on question of fact-Continued
a changed condition was based on conflicting evidence which, taken as a whole, was neither substantial nor persuasive, the decision, adverse to the contractor, was not final or binding.
Where the Armed Services Board of Contract Appeals has deter- mined a question of fact dispute adversely to the contractor and the record made before the Court of Claims contains evidence which provides substantial support for such determination, the Board's decision is final and conclusive despite the fact that the court might have reached a different result. Act of May 11, 1954, 68 Stat. 81, 41 U.S.C. § 321 (Supp. III, 1952). Bateson Construction Co., 514. United States 73 (14)
Question of fact.
What constitutes.
Whether or not defective concrete caissons constructed by the plain- tiff were the result of faulty concrete design furnished by the Gov- ernment or the result of insufficient or improper mixing of other- wise suitable concrete by plaintiff, is a question of fact within the meaning of the Disputes clause of the contract. Bateson Construc- tion Co., 514.
In connection with a contract to perform excavation and embank- ment work for a dam spillway, the contractor cannot maintain that he was misled by the information supplied to bidders if that in- formation was in fact sufficient to alert an experienced contractor of ground and water conditions even though some information in the Government's possession was withheld. Leal, 451. United States 70 (30)
Withholding of information-when actionable.
While the Government has a duty to disclose to prospective bidders all pertinent information in its possession, a withholding of infor- mation which would not reasonably be expected to mislead bidders will not give rise to a claim by the contractor. Ragonese v. United States, 128 C. Cls. 156, 162. Leal, 451. United States
CONTRACTS—Continued
INTERPRETATION.
Obligation to order services.
Requirements contract.
Where the quantity ordered under a requirements contract is con- siderably more or less than that anticipated from a reading of the contract terms, the court will usually protect the aggrieved party from unfair usage by applying a test of good faith to the other party's actions. But where the contract states that the quantities mentioned are estimates only and the obligation of the Government is to order those services which, in the judgment of the contracting officer are needed, the Government is not obligated to pay for more than he orders provided the contracting officer acts in good faith. Shader Contractors, 535.
Where all the payments sought to be recovered by the purchaser of a ship under the Merchant Ship Sales Act, 60 Stat. 41, were made within 6 years of the filing of the petition, the claim is not barred by the six-year statute of limitations applicable to suits in the Court of Claims [28 U.S.C. § 2501]. Colonial Navigation Co., 242.
Interpretation of release.
Although a release may be couched in broad, general terms, it will be interpreted in accordance with the intention of the parties as revealed by the facts of the case. Thus, where the purchaser of a Government owned ship has agreed to pay the purchase price by means of a series of notes, the last group of which notes included an extra charge for slotting and strapping which the Government agreed to refrain from collecting if pending litigation resulted in a decision that the Government was not entitled to make such a charge, and where the purchaser sold its business to a third party who assumed liability on the notes and the Government and the original purchaser executed releases which appeared to ignore the Government's agreement to cancel or refund slotting and strapping costs if the litigation resulted adversely to the Government's posi- tion, the releases did not nullify the Government's obligation to make such refund when there was no indication that the original pur- chaser intended to release the Government from such obligation. Colonial Navigation Co., 242.
Release 38
United States 113
CONTRACTS-Continued
REQUISITES AND VALIDITY.
Nature and grounds of obligation.
Requirements contract.
A requirements contract is one in which one party promises to supply all specific goods or services which the other party may need during a certain period at an agreed price and in which the other party implicitly promises that he will obtain his required goods or services from the first party exclusively. Shader Contractors, 535. Contracts
SUBROGATION.
Creditors' rights-extent of.
Plaintiff as subrogee of a bank which held a valid assignment under a Government contract, acquired only the rights of the bank, if any, and when the United States made a payment which completely discharged its indebtedness to the assignee (the contractor having been declared bankrupt), the plaintiff had no rights against the United States. Berkeley, 549.
United States 111 (8)
Effect of subrogation-in general.
A subrogee stands in the shoes of its subrogor and acquires no greater rights than those acquired by such subrogor. Berkeley, 549. Subrogation ~ 33(2)
SURPLUS WAR PROPERTY.
National security clause.
Dormant estate.
Where the deed conveying to a plaintiff-purchaser the title to a surplus war plant contains a so-called "national security clause" (National Industrial Reserve Act of 1948, 62 Stat. 1225, section 4(2)) providing that a dormant estate for a period of years is reserved by the Government-seller and that at the completion of the years specified the purchaser will have clear and complete title; and where it appears that the property in question was sold for less than it would have brought on the market if the entire fee had passed at the time of purchase, the Government need not convey the dormant estate without consideration. Fawick Corp., 623. United States 58
TRANSFER OF CONTRACT TO THIRD PARTY.
When a contractor with the Government transfers to another his right to perform the contract or to require of another its perform- ance and retains no right to control such performance, the contractor has made the type of transfer prohibited by 41 U.S.C. § 15 [Assign- ment of Claims Act of 1940 as amended, 65 Stat. 41], resulting in the annulment of the contract so transferred since the statute is
TRANSFER OF CONTRACT TO THIRD PARTY—Continued
designed to protect the Government from having to deal with strangers to its contracts. McPhail, 179.
COURT OF CLAIMS. See also Taxes-Claims for Refund.
JURISDICTION.
Admiralty claim.
If a claim may be sued on in a court of admiralty, the Court of Claims does not have jurisdiction to entertain it even though the claim might otherwise be within the language of the statutes defin- ing the Court of Claims' jurisdiction. Siljestad, 141.
The claim of a common carrier by water for hire against the Gov- ernment for its failure to remove goods from piers within the "free time" permitted by lawfully published tariffs on file was sufficiently maritime in character to be within the jurisdiction of a court of admiralty and therefore not within the jurisdiction of the Court of Claims. Siljestad, 141.
Executive decision-review of by court.
An executive decision to abolish a position in a Government agency or department and to create a new position to which the incumbent of the abolished position was not transferred, is not a decision which is reviewable by the Court of Claims on the merits. Umbeck, 418.
In general, controversies between private parties are not cognizable by the Court of Claims. Berkeley, 549.
Where the Alien Property Custodian, as agent of the United States, vests a contract under which it acquires the rights of the alien enemy party thereto, it also succeeds to the obligations of such alien enemy party and when those obligations run in favor of a non-enemy not subject to the vesting provisions of the Trading with the Enemy Act, such non-enemy has a claim justiciable in the Court of Claims under the Tucker Act, 28 U.S.C. §§ 1346 and 1491. Carey, 587.
War and National Defense 11
CUSTOMS INSPECTORS. See Civilian Pay.
DELAYS-DAMAGES. See Contracts.
DEMURRAGE. See Carriers.
DESIGN PATENTS. See Patents.
DICK ACT. See Military Pay.
DISMISSAL. See Civilian Pay.
DISPUTES. See Contracts.
DORMANT ESTATE. See Congressional Reference; Contracts. EQUITABLE CLAIMS. See Congressional Reference.
ESTOPPEL. See also Patents.
GROUNDS OF ESTOPPEL.
A party to a contract does not forfeit his rights under it by mis- interpreting the contract nor by acquiescing in the other party's misinterpretation unless he manages to mislead the other party to his detriment. Carey, 587.
EXECUTIVE DECISION. See Court of Claims-Jurisdiction. FRAUD. See also Contracts.
WHAT CONSTITUTES—IN GENERAL.
Lack of candor does not necessarily amount to fraud. Thus, where a factor, who has financed a Government contractor and is the beneficiary of the contractor's assignment of its contract claims against the Government to a bank which had loaned money to the factor, is aware of the fact that the delay in contract payments is due to the fact that there have been shortages in deliveries to the Government, it was proper for the factor to ask the bank to com- municate with the Government to determine its position, particu- larly when it was uncertain what position the Government would take with respect to its obligation to the bank-assignee in the event of fraud by the contractor. The failure of the factor to suggest the possibility of the contractor's fraud in its letter to the assignee bank was somewhat less than candid but it was not fraudulent. Factors, 202.
GOVERNMENT AGENT.
AUTHORITY OF GOVERNMENT AGENT.
Power to incur indebtedness or make expenditures.
A Government agent does not have the power to irrevocably dispose of Government money by mistake. Newark Insurance Co., 170.
United States 40
INDEFINITE APPOINTMENT.
« PreviousContinue » |