[merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][ocr errors][ocr errors][ocr errors][merged small][merged small][merged small][ocr errors][subsumed][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small]

10. DESCRIPTION OF PROPOSED CONSTRUCTION

Acquisition of interest in approximately 445 acres of land.

SUBSTANDARD:

O AC.

11. REQUIREMENT: 12,200 AC. ADEQUATE : 11,700 AC. PROJECT: Acquires ownership of land. REQUIREMENT: Additional land to accommodate the TRIDENT II (D-5) mission at Kings Bay. Land acquisition is required for: (1) development of the site, (2) buffer areas with the surrounding private property, and (3) space so that explosive safety areas will not fall on to private property now under restrictive easement.

CURRENT SITUATION: The existing land held in fee simple and easements by the government does not provide adequate space for the contemplated development of the refit site. This project will not acquire in fee simple existing easements on state-owned marshland or land designated for turnover to the Department of the Interior as the Cumberland Island National Seashore.

IMPACT IF NOT PROVIDED: The strategic weapons area at Kings Bay cannot be developed to accommodate the TRIDENT II (D-5) missile.

ADDITIONAL: An economic analysis has not been prepared as there is no reasonable alternative to satisfy the requirement.

DD.

FORM

1 DEC 76 1391

PREVIOUS EDITIONS MAY BE USED INTERNALLY
UNTIL EXHAUSTED

PAGE NO. 92

[blocks in formation]

A. ESTIMATED ANNUAL COST TO OPERATE THE PROPOSED FACILITY.....

B.

NUMBER OF ADDITIONAL PERSONNEL NECESSARY TO CARRY OUT
THE FUNCTION OF THE PROPOSED FACILITY.

N/A

($000)

N/A

(PEOPLE)

C. ESTIMATED LIFE-CYCLE COST TO OPERATE AND MAINTAIN THE
PROPOSED FACILITY..

D. ESTIMATED LIFE-CYCLE COST TO OPERATE AND MAINTAIN THE
EXISTING FACILITY IF NEW FACILITY IS A REPLACEMENT.

N/A

($000)

N/A

($000)

[blocks in formation]

F.

(month and year)

EQUIPMENT ASSOCIATED WITH THIS PROJECT WHICH WILL BE PROVIDED
FROM OTHER APPROPRIATIONS:

[blocks in formation]
[merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][ocr errors][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small][merged small]

Electric power and communication systems; potable water distribution system expansion; hot and chilled water distribution systems; sanitary waste collection system expansion; two and four lane paved roads, railroad trackage, access drives, surface storm drainage; site improvement and fencing.

11. REQUIREMENT: VARIES.

PROJECT: Provides utility services, roads, and site improvements. REQUIREMENT: Adequate utility services and site improvements to support buildings and structures programmed for development of the East Coast TRIDENT Submarine Base. Provide basic utility and road infrastructure and site improvements before major building construction begins. This project

is critical to the continued orderly development of Kings Bay in the most economical manner possible.

CURRENT SITUATION: Roads and utilities do not exist as required to support programmed facilities.

IMPACT IF NOT PROVIDED: Road access, storm drainage, and utility services will not be available to facilitate building construction, or enable planned occupancy of new buildings; major construction sites will not be developed to permit the orderly start of operational buildings on schedule. ADDITIONAL: An economic analysis has not been prepared as there is no reasonable alternative to satisfy the requirement.

FORM

DD1 DEC 761391

PREVIOUS EDITIONS MAY BE USED INTERNALLY
UNTIL EXHAUSTED

PAGE NO 93

DD FORM 1390 SUPPLEMENTAL DATA

FY 1983 MILITARY CONSTRUCTION PROGRAM

NAVY COMPONENT

NAVAL SUPPORT ACTIVITY
SAN FRANCISCO, CALIFORNIA

INSTALLATION/LOCATION

A.

CHIEF OF NAVAL

OPERATIONS

COMMAND

Estimated Cost of Backlog of Real Property Maintenance (BMAR) (as of September 30, 1981):

Permanent Facilities (
Temporary Facilities (

B. Similar Unused Space:

Real Property Categories

740-XX Community Facilities
812-XX Energy Conservation

($000)

38,100 1,800 ) 36,300)

Quantity/Unit of
Measure

0
N/A

C. Outstanding Pollution and Safety (OSH) Deficiencies:

[blocks in formation]
[graphic]
[blocks in formation]

10. Mission or Major Functions: Provide logistic support for Navy and Naval Reserve activities in the San Francisco area, including personnel support, waterfront, administration, recreation, exchange and security.

[blocks in formation]
« PreviousContinue »