D. ESTIMATED LIFE-CYCLE COST TO OPERATE AND MAINTAIN THE 766 ($000 10 (PEOPLE) 8,640 ($000) 11,380 4. Contract...... In-house...... CONSTRUCTION START (Planned). 173 58 231 185 46 Apr 83 (month and year) EQUIPMENT ASSOCIATED WITH THIS PROJECT WHICH WILL BE PROVIDED FROM Equipment Nomenclature Procuring FY of Appropriation Cost ($000) F. None 10. DESCRIPTION OF PROPOSED CONSTRUCTION Construct enlisted personnel barracks for 117 personnel, to include billet rooms, laundry rooms, day room, utilities, and communications. Provisions will not be made for the handicapped. Not sited in a flood plain 11. REQUIREMENT: 279 PN Adequate: 36 PN Substandard: 216 MN PROJECT: Construction of three barracks buildings for enlisted personnel. REQUIREMENT: This project is needed to provide adequate available billeting facilities that meet current housing requirements and are operationally and energy efficient. CURRENT SITUATION: Existing billets are deteriorated quonset huts built in the 1950's as temporary structures. The buildings are well beyond their expected life, have leaking roofs and walls, are difficult to heat because of poor insulation, and require frequent, costly repairs. There are no facilities available off-post. IMPACT IF NOT PROVIDED: Existing facilities will continue to be used with a corresponding adverse impact on troop morale. The facilities will continue to require extensive maintenance and repair, and continue to be highly energy inefficient. MAY لی NUMBER OF ADDITIONAL PERSONNEL NECESSARY TO CARRY OUT ESTIMATED LIFE-CYCLE COST TO OPERATE AND MAINTAIN THE D. ESTIMATED LIFE-CYCLE COST TO OPERATE AND MAINTAIN THE ... 163 ($000 0 (PEOPLE) 2,539 ($000) 3,561 ($000) F. (month and year) EQUIPMENT ASSOCIATED WITH THIS PROJECT WHICH WILL BE PROVIDED FROM MAY 10. DESCRIPTION OF PROPOSED CONSTRUCTION Construction of two dining facilities to include dining hall, kitchen area, utilities, communications, and site improvement. existing quonset type structure will be demolished upon completion of this proiect. Not sited in a flood plain. Heating from a self-contained boiler. Substandard: 83,203 SF 11. REQUIREMENT: 88,860 SF Adequate: 28,580 SF PROJECT: Construct a dining facility. REQUIREMENT: This proiect is needed to replace the existing crowded, temporary-type, quonset structure which is inadequate and beyond its intended and economic use. With the decision to maintain troops at Camp Casey, facilities are needed for support that can meet mission requirements. Dining facilities are needed for a total requirement of over 6,160 personnel. CURRENT SITUATION: The existing facility is an aged quonset temporarytype structure that is in a deteriorated condition. The roof and walls leak and are poorly insulated. The facility does not meet the fire/life safety code requirements and does not adequately support kitchen/dining facility requirements. IMPACT IF NOT PROVIDED: The existing facility will remain in use as can best be done with severe detrimental impact upon mission and troop morale. C. ESTIMATED LIFE-CYCLE COST TO OPERATE AND MAINTAIN THE D. ESTIMATED LIFE-CYCLE COST TO OPERATE AND MAINTAIN THE 525 ($000 0 (PEOPLE) 6,689 2 May 81 35 100 Aug 82 No X .......... 4. In-house............ CONSTRUCTION START (Planned)................ ......... ..... 165 55 220 176 44 Apr 83 (month and year) EQUIPMENT ASSOCIATED WITH THIS PROJECT WHICH WILL BE PROVIDED FROM |