| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1962 - 784 pages
...days from the date of receipt by the Contractor of the notification of change : Provided, however, That the Contracting Officer, if he decides that the..."Disputes." However, nothing in this clause shall excuse the Con148 c. Os. Per Cariam tractor from proceeding with the contract as changed. * * * * * 12. DISPUTES... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1959 - 1028 pages
...from the date of receipt by the Contractor of the notification of extra or change : Provided, however, That the Contracting Officer, if he decides that the...upon any such claim asserted at any time prior to the date of final settlement of the contract. If the parties fail to agree upon the adjustment to be... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1968 - 922 pages
...days from the date of receipt by the Contractor of the notification of change : Provided, however, That the Contracting Officer, if he decides that the...receive and act upon any such claim asserted at any time/prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute... | |
| Administrative law - 1983 - 716 pages
...30 days from the date of receipt by the Contractor of the notification of change: Provided, however, That the Contracting Officer, if he decides that the...nothing in this clause shall excuse the Contractor from'proceeding with the contract as changed. § 1-7.703-3 Extras. Insert the clause set forth in 1... | |
| Administrative law - 1978 - 188 pages
...30 days from the date of receipt by the contractor of the notification of change; provided, however, that the Contracting Officer, if he decides that the...clause of this contract entitled "Disputes". However, except as provided in paragraph (c) of this section, nothing in this clause shall excuse the contractor... | |
| Administrative law - 1977 - 1240 pages
...30 days from the date of receipt by the Contractor of the notification of change: Provided, however, That the Contracting Officer. If he decides that the...clause of this contract entitled "Disputes." However, except as provided In paragraph (c) , below, nothing in this clause shall excuse the Contractor from... | |
| Administrative law - 1980 - 976 pages
...(30) days from the date of receipt by the Contractor of the notification of change; provided, however, that the Contracting Officer, if he decides that the...to any adjustment shall be a dispute concerning a question of fact within the meaning of the "Disputes" clause of this contract. However, nothing in... | |
| Administrative law - 1975 - 1236 pages
...Contractor of the notification of change; provided, however, that the Contracting Officer, if he deckles that the facts justify such action, may receive and...to any adjustment shall be a dispute concerning a question of fact within the meaning of the "Disputes" clause of this contract. However, nothing in... | |
| Administrative law - 1982 - 1316 pages
...of the notification of change; provided, however, thai the Contracting Officer, if he decides thai the facts justify such action, may receive and act...to any adjustment shall be a dispute concerning a question of fact within the meaning of the "Disputes" clause of this contract. However, nothing in... | |
| Administrative law - 1968 - 1518 pages
...by the Contractor of the notification of change: Provided, however, That the Contracting Officer, 11 he decides that the facts justify such action, may...contract. Failure to agree to any adjustment shall be S dispute concerning a question of fact withIn the meaning of the “Disputes” clause of this contract.... | |
| |