Decisions of the Comptroller General of the United States, Volume 69U.S. Government Printing Office, 1990 - Finance, Public Contains a selection of major decisions of the GAO. A digest of all decisions has been issued since Oct. 1989 as: United States. General Accounting Office. Digests of decisions of the Comptroller General of the United States. Before Oct. 1989, digests of unpublished decisions were issued with various titles. |
From inside the book
Results 1-5 of 100
Page 30
... costs and insurance costs when the costs were not adequately substantiated , there is no evidence of fraud , bad faith or mutual mistake , the resulting contract was not plainly or palpably illegal , and the contractor may be paid at ...
... costs and insurance costs when the costs were not adequately substantiated , there is no evidence of fraud , bad faith or mutual mistake , the resulting contract was not plainly or palpably illegal , and the contractor may be paid at ...
Page 37
... costs ; and its average cost per drawing is $ 4,340 , which compares favorably to the Corps ' experience of $ 5,000 per drawing . Inca also agrees , however , that it made certain design assumptions that were unac- ceptable to the ...
... costs ; and its average cost per drawing is $ 4,340 , which compares favorably to the Corps ' experience of $ 5,000 per drawing . Inca also agrees , however , that it made certain design assumptions that were unac- ceptable to the ...
Page 46
... costs of continuing in - house performance with the sum of the total costs associated with the acceptance of EPD's offer plus an OMB im- posed 10 percent conversion differential . The cost comparison , as adjusted by the Marine Corps ...
... costs of continuing in - house performance with the sum of the total costs associated with the acceptance of EPD's offer plus an OMB im- posed 10 percent conversion differential . The cost comparison , as adjusted by the Marine Corps ...
Page 47
... cost comparison omitted the costs associated with op- eration of the bulldozer in question . In response to EPD's cost comparison appeal , the agency review board added $ 11,309.01 to the in - house cost estimate : $ 5,443.77 for ...
... cost comparison omitted the costs associated with op- eration of the bulldozer in question . In response to EPD's cost comparison appeal , the agency review board added $ 11,309.01 to the in - house cost estimate : $ 5,443.77 for ...
Page 48
... cost estimate . Consistent with this guidance , here the Marine Corps review board revised the government estimate to include costs for a bull- dozer which was not entirely dedicated to the function under study , but which was ...
... cost estimate . Consistent with this guidance , here the Marine Corps review board revised the government estimate to include costs for a bull- dozer which was not entirely dedicated to the function under study , but which was ...
Other editions - View all
Common terms and phrases
1990 Procurement 68 Comp acceptable Administration agency's Air Force alleged amendment amount argues Army attorney awardee's BAFO basis best and final bid bond bid opening bidder certification claim clause competitive range concerning concluded considered contends Contract awards contracting agency contracting officer contractor Corp Corporation decision Defense Logistics Agency deny the protest determination discussions employee entitled expenses Federal Acquisition Regulation fees filed firm Flight International funds GAO procedures GSA's Herman Miller Honeywell improperly initial invitation for bids issued Latecoere Magnavox Martin Marietta ment Navy Navy's nonresponsive offerors option payment percent performance personnel prior Procurement Competitive Negotiation protest is denied protester's received record reimbursement rejected relocation relocation services request for proposals responsibility schedule score specific subfactors submitted supra technical tion unacceptable United
Popular passages
Page 237 - If this contract is for the manufacture or furnishing of materials, supplies, articles, or equipment in an amount which exceeds or may exceed $10,000 and is otherwise subject to the Walsh-Healey Public Contracts Act...
Page 273 - ... grown, reprocessed, reused, or produced in the United States or its possessions cannot be procured as and when needed at United States market prices...
Page 266 - Any concern which submits a bid or offer in its own name, other than on a construction or service contract, but which proposes to furnish a product not manufactured by said bidder or offerer, is deemed to be a small business concern when: (1) It is a small business concern within the meaning of...
Page 220 - ... (e) whether the employer or the workman supplies the instrumentalities, tools, and the place of work for the person doing the work ; (f) the length of time for which the person is employed; (g) the method of payment, whether by the time or by the job; (h) whether or not the work is a part of the regular business of the employer ; (i) whether or not the parties believe they are creating the relationship of master and servant; and (j) whether the principal is or is not in business.
Page 643 - executive agency" means any executive department or independent establishment in the executive branch of the Government, including any wholly owned Government corporation. (b) The term "Federal agency...
Page 273 - ... States or its possessions, except to the extent that the Secretary of the Department concerned shall determine that a satisfactory quality and sufficient quantity of any articles of food or clothing...
Page 643 - Federal agency" means any executive agency or any establishment in the Legislative or Judicial Branches of the Government (except the Senate, the House of Representatives, and the architect of the Capitol and any activities under his direction) . §18-1.211 Field installation. "Field installation" means Ames Research Center, Electronics Research Center.
Page 728 - ... if the contracting officer determines that there is a reasonable expectation that...
Page 695 - League has also actively participated before the Interstate Commerce Commission, the Civil Aeronautics Board, the Federal Maritime Commission, and the Federal Courts in major litigation affecting transportation.