| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1968 - 922 pages
...writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor...clause of this contract entitled "Disputes." However, nothing in this clause shall excuse the Contractor from proceeding with the contract as changed. *****... | |
| Administrative law - 1970 - 260 pages
...price or time of performance, or both, and (i1) in such other provisions of the contract as may be so affected, and the contract shall be modified in writing...clause of this contract entitled "Disputes". However, nothing in this clause shall excuse the contractor from proceeding with the contract as changed. §... | |
| Administrative law - 1969 - 752 pages
...hourly rates, (ill) delivery schedule, and (Iv) In such other provisions of the contract as may be so affected, and the contract shall be modified In writing...to any adjustment shall be a dispute concerning a question of fact within the meaning of the "Disputes" clause of this contract. However, nothing In... | |
| Administrative law - 1983 - 1104 pages
...hourly rates, (iii) delivery schedule, and (iv) in such other provisions of the contract as may be so affected, and the contract shall be modified in writing...to any adjustment shall be a dispute concerning a question of fact within the meaning of the "Disputes" clause of this contract. However, nothing in... | |
| Administrative law - 1970 - 984 pages
...equitable adjustment shall be made In the estimated cost, the completion schedule, or both, and the contract shall be modified In writing accordingly....to any adjustment shall be a dispute concerning a question of fact within the meaning of the "Disputes" clause of this contract. However, nothing In... | |
| Administrative law - 1972 - 1094 pages
...equitable adjustment shall be made in the estimated cost, the completion schedule, or both, and the contract shall be modified in writing accordingly....to any adjustment shall be a dispute concerning a question of fact within the meaning of the "Disputes" clause of this contract. However, nothing in... | |
| Administrative law - 1984 - 232 pages
...writing accordingly. Any claim by the contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the contractor..."Disputes". However, except as provided in paragraph (c) of this section, nothing in this clause shall excuse the contractor from proceeding with the contract... | |
| Administrative law - 1965 - 1168 pages
...Any claim by the Contractor for adjustment under this clause must be asserted within sixty (60) days from the date of receipt by the Contractor of the...clause of this contract entitled "Disputes." However, nothing In this clause shall excuse the Contractor from proceeding with the contract as changed. §... | |
| Administrative law - 1976 - 1202 pages
...the applicable schedule or rates and the contract shall be modified in writing accordingly Any claims by the Contractor for adjustment under this clause...to any adjustment shall be a dispute concerning a question of fact within the meaning of the "Disputes" clause of this contract. However, nothing in... | |
| Administrative law - 1974 - 1028 pages
...under this clause must be aeserted within sIxty (60) days from the date of receipt by the Conż tractor of the notificatIon of change: Provid,ed, however,...of this contract entitled “Disputes.” However, nothing in this clause shall excuse the Contractor from proceeding with the contract as changed. In... | |
| |