the protest, and conclusions and recommendations, including documentary evidence on which they are based.

(ii) A copy of the IFB or RFP.

(iii) A copy of the abstract of bids or proposals.

(iv) A copy of the bid or proposal of the successful offeror to whom award has been made or is proposed to be made.

(v) A copy of the bid or proposal of the protestant, if any.

(vi) The current status of award. When award has been made, this shall include whether performance has commenced, shipment or delivery has been made, or a stop work order has been issued.

(vii) A copy of any mutual agreement to suspend work on a no-cost basis, when appropriate (see FAR 33.104(c)).

(viii) Copies of the notice of protest given offerors and other parties when the notice is appropriate (see FAR 33.104(a)(3)).

(ix) A copy of the technical evaluation report required by 315.608-76, when applicable, and a copy of each evaluator's rating for all proposals.

(x) A copy of the negotiation memorandum, when applicable (see 315.672).

(xi) The name and telephone number of the person in the contracting office who may be contacted for information relevant to the protest,

[blocks in formation]

333.104(a)(2) to the DPCO within nineteen (19) work days from receipt of the protest. (The contracting activity's protest control officer may provide a written opinion and recommendation on the protest to the DPCO within nineteen (19) work days from receipt of the protest by the contracting officer.) The contracting officer shall clearly identify any documents or portions of documents he or she desires to withhold from the protester, and shall include justification for the withholding of each document or portion of a document in the contracting officer's statement of facts. Since the statute allows only a short time period in which to respond to protests lodged with GAO, the contracting officer shall handle each protest on a priority basis.

The DPCO shall prepare the report and submit it and the protest file to GAO in accordance with FAR 33.104(a)(4).

(5)(i) The DPCO shall take the necessary actions specified in FAR 33.104(a)(5)(i) after receiving all the documentation required by 333.104(a)(2) from the contracting officer.

(ii) Since the DPCO will furnish the report to GAO, the protestor, and other interested parties, comments on the report from the protester and other interested parties will be requested to be sent to the DPCO.

(6) The Office of Procurement and Logistics Policy (OPLP), OPAL, has been designated as the headquarters office, and the DPCO as the individual, that GAO should contact concerning all protests lodged with GAO.

(b) Protests before award. (1) To make an award notwithstanding a protest, the contracting officer shall prepare a finding using the criteria in FAR 33.104(b)(1), have it executed by the head of the contracting activity, and forward it, along with a written request for approval to make the award, to the Director, OPLP.

(2) If the request to make an award notwithstanding the protest is approved by the Director, OPLP, the DPCO shall notify GAO. Whether the request is approved or not, the DPCO shall telephonically notify the contracting activity's protest control offi

cer of the decision by the Director, OPLP, and the contracting activity's protest control officer shall immediately notify the contracting officer. The DPCO shall confirm the decision by memorandum to the contracting activity's protest control officer.

(4) The contracting office shall prepare the protest file in accordance with 333.104(a)(2), and forward it, in duplicate, to the DPCO (see 333.104(a)(4)). The file shall be marked "IMMEDIATE ACTIONPROTEST BEFORE AWARD.”

(c) Protests after award. (2) If the contracting officer believes performance should be allowed to continue notwithstanding the protest, a finding shall be prepared by the contracting officer, executed by the head of the contracting activity, and forwarded, along with a written request for approval, to the Director, OPLP. The same procedures for notification stated in 333.104(b)(2), above shall be followed.

(6) The contracting officer shall prepare the protest file in accordance with 333.104(a)(2), and forward it, in duplicate, to the DPCO (see 333.104(a)(4)). The file shall be marked "IMMEDIATE ACTIONPROTEST AFTER AWARD."

(d) Findings and notice. The contracting officer shall perform the actions required by FAR 33.104(d); however, notification to GAO shall be made by the DPCO.

(f) Notice to GAO. The Deputy Assistant Secretary for Procurement, Assistance, and Logistics shall be the official to comply with the requirements of FAR 33.104(f).

in

(h) Express option. When GAO invokes the express option, the contracting officer shall prepare the complete protest file as described 333.104(a)(2), to include item (i), and deliver it (hand-carry, if necessary) to the DPCO no later than the close of business on the ninth work day after the express option is invoked. The contracting officer shall involve OGCBAL as early as possible after receiving notification of the invocation of the express option, and obtain the concurrence of the cognizant OGCBAL attorney prior to transmitting the protest file to the DPCO. The

DPCO shall prepare the report and submit it and the protest file to GAO.

[50 FR 23133, May 31, 1985, as amended at 50 FR 38004, Sept. 19, 1985]

333.105 Protests to GSBCA.

(a)(1) The contracting officer shall give telephone notification to the DPCO, OGC-BAL, and the contracting activity's protest control officer immediately upon notification of the protest.

(2)(i) The contracting officer is responsible for complying with the requirement in FAR 33.105(a)(2)(i).

(ii) The cognizant OGC-BAL attorney is responsible for complying with the requirement stated in FAR

33.105(a)(2)(ii).

(b) As soon as possible but no later than six (6) work days after the filing of the protest, a copy of the protest file containing all documents (see FAR 33.105(b), especially (b)(7)), and labeled on the cover "FOR USE BY DPCO ONLY”, shall be in the hands of the DPCO for review. Simultaneously, two copies of the same protest file provided to the DPCO shall be provided to the cognizant OGCBAL attorney. These two copies shall be labeled on the cover "FOR USE BY OGC-BAL." After consultation with the cognizant OGC-BAL attorney, the DPCO shall transmit the protest file to the GSBCA.

(1) Rather than furnishing a decision, the contracting officer shall include a statement of facts and circumstances and a discussion of the merits of the protest, as well as conclusions and recommendations and documentary evidence on which they are based. These statements shall be reviewed by the cognizant OGC-BAL attorney before being finalized.

(7) The DPCO shall provide all parties with a list of documents furnished to the GSBCA for in camera review.

[blocks in formation]

(c) The cognizant OGC-BAL attorney is responsible for complying with the requirement stated in FAR 33.105(c).

(d)(1) If the protest requests a suspension of acquisition authority, the contracting officer must make this known to the DPCO, OGC-BAL, and the contracting activity's protest control officer at the time of the initial telephone notification of the filing of the protest to afford an opportunity for the DPCO, OGC-BAL, principal official responsible for acquisition (PORA), and contracting officer to take appropriate action.

(2) If it can be established that the conditions stated in FAR 33.105(d)(1)(i) and (ii) are present, the contracting officer shall prepare a D&F setting forth the circumstances. The D&F shall be concurred in by the cognizant OGC-BAL attorney before being executed by the PORA (not delegable).

(g) If an appeal is to be made by the Department regarding a final decision issued by the GSBCA, it shall be made by OGC-BAL.

[50 FR 23133, May 31, 1985, as amended at 50 FR 38004, Sept. 19, 1985]

333.106 Solicitation provision and contract clause.

(a) The provision at FAR 52.233-2, Service of Protest, shall be completed by entering the name and complete mailing address of the contracting officer.

[50 FR 23133, May 31, 1985, as amended by 50 FR 38004, Sept. 19, 1985]

Subpart 333.2-Disputes and Appeals

SOURCE: 53 FR 15563, May 2, 1988, unless otherwise noted.

333.203 Applicability.

(c) The Armed Services Board of Contract Appeals (ASBCA) has been designated by the Secretary as the authorized "Board" to hear and determine disputes for the Department.

333.209 Suspected fraudulent claims.

The contracting officer shall submit any instance of a contractor's suspected fraudulent claim to the Office of

the Inspector General for investigation.

333.210 Contracting officer's authority.

The contracting officer shall refer a proposed final decision to the Office of General Counsel, Business and Administrative Law Division (OGC-BAL), or the Regional Attorney in the HHS regional office servicing the region in which the contracting officer is located, for advice as to the legal sufficiency and format before sending the final decision to the contractor. The contracting officer shall provide OGCBAL or the Regional Attorney with the pertinent documents with the submission of each proposed final decision.

333.211 Contracting officer's decision. (a)(2) See 333.210.

(a)(4)(v) When using the paragraph in FAR 33.211(a)(4)(v), the contracting officer shall insert the words "Armed Services" before each mention of the term "Board of Contract Appeals".

(c)(2) The contracting officer does not have jurisdiction to consider a claim from the contractor over $50,000, unless that claim has been certified.

(h) At any time within the period of appeal, the contracting officer may modify or withdraw his/her final decision. If an appeal from the final decision has been taken to the ASBCA, the contracting officer will forward his/her recommended action to OGCBAL or the cognizant Regional Attorney with the supplement to the contract file which supports the recommended correction or amendment.

333.212 Contracting officer's duties upon appeal.

(a) Appeals shall be governed by the rules set forth in the "Rules of the Armed Services Board of Contract Appeals", or by the rules established by the U.S. Claims Court, as appropriate.

(b) OGC-BAL or the cognizant Regional Attorney is designated as the Government Trial Attorney to represent the Government in the defense of appeals before the ASBCA. A decision by the ASBCA will be transmitted by the Government Trial Attorney to the

appropriate contracting officer for compliance in accordance with the ASBCA's decision.

(c) If an appeal is filed with the ASBCA, the contracting officer shall assemble a file within 30 days of receipt of an appeal, or advice that an appeal has been filed, that consists of all documents pertinent to the appeal, including:

(1) The decision and findings of fact from which the appeal is taken;

(2) The contract, including specifications and pertinent modifications, plans and drawings;

(3) All correspondence between the parties pertinent to the appeal, including the letter or letters of claims in response to which the decision was issued;

(4) Transcripts of any testimony taken during the course of proceedings, and affidavits or statements of any witnesses on the matter in dispute made prior to the filing of the notice of appeal with the Board; and

(5) Any additional information considered pertinent.

The contracting officer shall furnish the appeal file to the Government Trial Attorney for review and approval. After approval, the contracting officer shall prepare four copies of the file, one for the ASBCA, one for the appellant, one for the Government Trial Attorney, and one for the contracting office.

(d) At all times after the filing of an appeal, the contracting officer shall render whatever assistance is requested by the Government Trial Attorney. When an appeal is set for hearing, the concerned contracting officer, acting under the guidance of the Government Trial Attorney, shall be responsible for arranging for the presence of Government witnesses and specified physical and documentary evidence at both the pre-hearing conference and the hearing.

(e) If a contractor which has filed an appeal with the ASBCA elects to accept fully the decision from which the appeal was taken, or any modification to it, and gives written notification of acceptance to the Government Trial Attorney or the concerned contracting officer, the Government Trial Attorney will notify the ASBCA of the