" Contractor for adjustment under this clause must be asserted within sixty (60) days from the date of receipt by the Contractor of the notification of change; Provided, however. That the Contracting Officer, if he decides that the facts justify such action,... "
Code of Federal Regulations: Containing a Codification of Documents of ... - Page 333
1971
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 154

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1968 - 922 pages
...accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the...justify such action, may receive and act upon any such claim asserted at any time prior to final payment under this contract. Failure to agree to any...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1965 - 1168 pages
...equitable adjustment shall be made (i) in the contract price or time of performance, or both, and (il) in such other provisions of the contract as may be...Justify such action, may receive and act upon any such claim asserted at any time prior to final payment under this contract. Failure to agree to any...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1972 - 914 pages
...cost or delivery schedule, or both, (2) In the amount of any fee to be paid to the Contractor, and (3) In such other provisions of the contract as may be...Provided., however. That the Contracting Officer, If he decide* that the facts Justify such action, may receive and act upon any such claim asserted at any...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1972 - 1094 pages
...equitable adjustment shall be made (i) in the contract price or time of performance, or both, and (11) in such other provisions of the contract as may be...notification of change; Provided, however, That the Contractlng Officer, if he decides that the facts justify such action, may receive and act upon any...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1978 - 188 pages
...order, an equitable adjustment shall be made (1) in the price or delivery schedule, or both and (2) in such other provisions of the contract as may be...date of receipt by the Contractor of the notification §7-7.5301-8 §7-7.5301-8 Examination of records by Comptroller General. Insert the clause set forth...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1968 - 1518 pages
...(Ii) In the amount be paid to the Contractor, and ther provisions of the contract Lifected, and the contract shall be modified in writing accordingly....of change: Provided, however, That the Contracting Omcer, if he decides that the facts justify such action, may receive and act upon any such claim asserted...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1980 - 976 pages
...delivery schedule, or both, (11) In the amount of any fixed fee to be paid to the Contractor, and (ill) In such other provisions of the contract as may be...adjustment under this clause must be asserted within sixty (6O) days from the date of receipt by the Contractor of the notification of change; provided, however,...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1964 - 676 pages
...writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within (60) days from the date of receipt by the Contractor...justify such action, may receive and act upon any such claim asserted at any time prior to final payment under this contract. Failure to agree at any...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1969 - 256 pages
...delivery schedule, or both, (11) in the amount of any fee to be paid to the contractor and/or (111) in such other provisions of the contract as may be...adjustment under this clause must be asserted within 30 days from the date of receipt by the contractor of the notification of change: Provided, however,...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1980 - 874 pages
...equitable adjustment shall be made (1) in the contract price or time of performance or both, and (11) In such other provisions of the contract as may be...adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change: Provided, however,...
Full view - About this book