" Contractor has failed to submit his claim within the time provided in paragraph (c) above and has failed to request extension of such time, he shall have no such right of appeal. In any case where the Contracting Officer has made a determination of the... "
Code of Federal Regulations: Containing a Codification of Documents of ... - Page 394
1971
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 152

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1963 - 938 pages
...Contractor failed to submit its claim within the time provided in paragraph (c) above and has failed to request extension of such time, he shall have no...Government shall pay to the Contractor the following: (i) if there is no right of appeal hereunder or if no timely appeal has been taken, the amount so determined...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1966 - 968 pages
...settlement proposal; or (B) The portion of the hourly rate allocable to profit for any direct labor houn expended In furnishing materials and services not...amount so determined by the Contracting Officer; or (11) If an appeal has been taken, the amount finally determined on such appeal. (g) In arriving at...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1974 - 1028 pages
...proposal; or (B) The portion of the hourly rate allocable to profit for any direct labor hours cxpended in furnishing materials and services not delivered...Government shall pay to the Contractor the following: (I) if there Is no right of appeal hereunder, or if no timely appeal has been taken, the amount so...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1982 - 712 pages
...hours expended in furnishing materials and services not delivered to and accepted by the Government. (0 The Contractor shall have the right of appeal, under...Government shall pay to the Contractor the following: (i) if there is no right of appeal hereunder, or if no timely appeal has been taken, the amount so...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1972 - 914 pages
...Contractor has failed to submit his claim within the time provided in paragraph (c) above and has failed to request extension of such time, he shall have no...amount so determined by the Contracting Officer, or (2) If any appeal has been taken, the amount finally determined on such appeal. (g) In arriving at...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1982 - 690 pages
...within the time provided in paragraph (c) above and has failed to request extension 90-134 O— 82-36 of such time, he shall have no such right of appeal....amount so determined by the Contracting Officer, or (2) if an appeal has been taken, the amount finally determined on such appeal. (h) In arriving at the...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1964 - 676 pages
...within the time provided in paragraph (c) above, and has failed to request extension of such time, it shall have no such right of appeal. In any case where...amount so determined by the Contracting Officer, or (11) if an appeal has been taken, the amount finally determined on such appeal. (g) In arriving at...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1964 - 1202 pages
...Procurement Regulations (41 CFR 1-15.2); or the corresponding agency regulations; or both. 22-066 O-64— 13 appeal. In any case where the Contracting Officer...amount so determined by the Contracting Officer; or (2) If an appeal has been taken, the amount finally determined on such appeal. (h) In arriving at the...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1980 - 874 pages
...paragraph (c) above and has failed to request extension of such tune, he shall have no such right or appeal. In any case where the Contracting Officer...if no timely appeal has been taken, the amount so deter TIM* 41— Public Contract!, Property Management mined by the Contracting Officer, or (2) If...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1966 - 1420 pages
...Contractor has failed to submit his claim within the time provided In paragraph (c) above and has failed to request extension of such time, he shall have no...to the Contractor the following: (1) If there is no light of appeal hereunder or If no timely appeal has been taken, the amount so determined by the Contracting...
Full view - About this book