Page images
PDF
EPUB

within the time allowed, the Contracting Officer may, subject to any review required by the contracting agency's procedures in effect as of the date of execution of this contract, determine, on the basis of information available to him, the amount. if any, due to the Contractor by reason of the termination and shall thereupon pay to the Contractor the amount so determined.

(d) Subject to the provisions of paragraph (c), and subject to any review required by the contracting agency's procedures in effect as of the date of execution of this contract, the Contractor and the Contracting Officer may agree upon the whole or any part of the amount of amounts to be paid (including an allowance for the fee) to the Contractor by reason of the total or partial termination of work pursuant to this clause. The contract shall be amended accordingly, and the Contractor shall be paid the agreed amount.

(e) In the event of the failure of the Contractor and the Contracting Officer to agree in whole or in part, as provided in paragraph (d), as to the amounts with respect to costs and fee, or as to the amount of the fee, to be paid to the Contractor in connection with the termination of work pursuant to this clause, the Contracting Officer shall. subject to any review required by the contracting agency's procedures in effect as of the date of execution of this contract, determine, on the basis of information available to him, the amount, if any, due to the Contractor by reason of the termination and shall pay to the Contractor the amount determined as follows:

(1) If the settlement includes cost and fee

(1) There shall be included therein all costs and expenses reimbursable in accordance with this contract, not previously paid to the Contractor for the performance of this contract prior to the effective date of the Notice of Termination, and such of these costs as may continue for a reasonable time thereafter with the approval of or as directed by the Contracting Officer: Provided, however, That the Contractor shall proceed as rapidly as practicable to discontinue such costs;

(11) There shall be included therein so far as not included under (1) above, the cost of settling and paying claims arising out of the termination of work under subcontracts or orders, as provided in paragraph (b) (5) above, which are properly chargeable to the terminated portion of the contract;

(111) There shall be included therein the reasonable costs of settlement, including accounting, legal, clerical, and other expenses reasonably necessary for the preparation of settlement claims and supporting data with respect to the terminated portion of the contract and for the termination and settlement of subcontracts thereunder, together with reasonable storage, transportation, and other costs incurred in connection

with the protection or disposition of termination inventory: Provided, however, That if the termination is for default of the Contractor there shall not be included any amounts for the preparation of the Contractor's settlement proposal; and

(iv) There shall be included therein a portion of the fee payable under the contract determined as follows

(A) In the event of the termination of this contract for the convenience of the Governmeut and not for the default of the Contractor, there shall be paid a percentage of the fee equivalent to the percentage of the completion of work contemplated by the contract, but exclusive of subcontract effort included in subcontractors' termination claims, less fee payments previously made hereunder; or

(B) In the event of the termination of this contract for the default of the Contractor, the total fee payable shall be such proportionate part of the fee (or, if this contract calls for articles of different types, of such part of the fee as is reasonably allocable to the type of article under consideration) as the total number of articles delivered to and accepted by the Government bears to the total number of articles of a like kind called for by this contract.

If the amount determined under this subparagraph (1) is less than the total payment theretofore made to the Contractor, the Contractor shall repay to the Government the excess amount.

(2) If the settlement includes only the fee, the amount thereof will be determined In accordance with subparagraph (1)(iv)

above.

(f) Costs claimed, agreed to, or determined pursuant to paragraphs (c), (d), and (e) of this clause shall be in accordance with the contract cost principles and procedures in Part 1-15 of the Federal procurement regulations (41 CFR 1-15) in effect on the date of this contract.

(g) The Contractor shall have the right of appeal, under the clause of this contract entitled "Disputes." from any determination made by the Contracting Officer under paragraph (c) or (e) above, except that, if the Contractor has failed to submit his claim within the time provided in paragraph (c) above and has failed to request extension of such time, he shall have no such right of appeal. In any case where the Contracting Oficer has made a determination of the amount due under paragraph (c) or (e) above, the Government shall pay to the Contractor the following: (1) If there is no right of appeal hereunder or if no timely appeal has been taken, the amount so determined by the Contracting Officer, or (2) if an appeal has been taken, the amount finally determined on such appeal.

(h) In arriving at the amount due the Contractor under this clause there shall be deducted (1) all unliquidated advance or other payments theretofore made to the Contractor, applicable to the terminated portion

of this contract, (2) any claim which the Government may have against the Contractor in connection with this contract, and (3) the agreed price for, or the proceeds of sale of, any materials, supplies, or other things acquired by the Contractor or sold pursuant to the provisions of this clause and not otherwise recovered by or credited to the

Government.

(1) In the event of a partial termination, the portion of the fee which is payable with respect to the work under the continued portion of the contract shall be equitably adjusted by agreement between the Contractor and the Contracting Officer, and such adjustment shall be evidenced by an amendment to this contract.

(1) The Government may from time to time, under such terms and conditions as it may prescribe, make partial payments and payments on account against costs incurred by the Contractor in connection with the terminated portion of the contract whenever in the opꞌnion of the Contracting Officer the aggregate of such payments shall be within the amount to which the Contractor will be entitled hereunder. If the total of such payments is in excess of the amount finally determined to be due under this clause, such excess shall be payable by the Contractor to the Government upon demand, together with interest computed at the rate of 6 percent per annum, for the period from the date such excess payment is received by the Contractor to the date on which such excess is repaid to the Government: Provided, however, That no interest shall be charged with respect to any such excess payment attributable to a reduction in the Contractor's claim by reason of retention or other disposition of termination inventory until 10 days after the date of such retention or disposition, or such later date as determined by the Contracting Officer by reason of the circumstances.

(k) The provisions of this clause relating to the fee shall be inapplicable if this contract does not provide for payment of a fee. [29 FR 10196, July 24, 1964, as amended at 37 FR 5296, Mar. 14, 1972]

§ 1-8.703 Termination clause for fixed. price construction contracts.

The following clause is applicable as prescribed in § 1-8.700-2(a)(5):

TERMINATION FOR CONVENIENCE OF THE

GOVERNMENT

(a) The performance of work under this contract may be terminated by the Government in accordance with this clause in whole, or from time to time in part, whenever the Contracting Officer shall determine that such termination is in the best interest of the Government. Any such termination shall be effected by delivery to the Contractor of a Notice of Termination specifying the extent to which performance of work under the contract is terminated, and the

date upon which such termination becomes effective.

(b) After receipt of a Notice of Termination, and except as otherwise directed by the Contracting Officer, the Contractor shall:

(1) Stop work under the contract on the date and to the extent specified in the Notice of Termination;

(2) Place no further orders or subcontracts for materials, services, or facilities except as may be necessary for completion of such portion of the work under the contract as is not terminated;

(3) Terminate all orders and subcontracts to the extent that they relate to the performance of work terminated by the Notice of Termination;

(4) Assign to the Government, in the manner, at the times, and to the extent directed by the Contracting Officer, all of the right, title, and interest of the Contractor under the orders and subcontracts so terminated, in which case the Government shall have the right, in its discretion, to settle or pay any or all claims arising out of the termination of such orders and subcontracts;

(5) Settle all outstanding liabilities and all claims arising out of such termination of orders and subcontracts, with the approval or ratification of the Contracting Officer to the extent he may require. which approval or ratification shall be fina! for all the purposes of this clause;

(6) Transfer title to the Government and deliver in the manner, at the times, and to the extent, if any, directed by the Contracting Officer, (1) the fabricated or unfabricated parts, work in process, completed work, supplies, and other material produced as a part of, or acquired in connection with the performance of, the work terminated by the Notice of Termination, and (11) the completed or partially completed plans, drawings, information, and other property which, If the contract had been completed. would have been required to be furnished to the Government;

(7) Use his best efforts to sell, in the manner, at the times, to the extent, and at the price or prices directed or authorized by the Contracting Officer, any property of the types referred to in (6) above: Provided, however, That the Contractor (1) shall not be required to extend credit to any purchaser, and (11) may acquire any such property under the conditions prescribed and at a price or prices approved by the Contracting Officer: And provided further, That the proceeds of any such transfer or dispostion shall be applied in reduction of any payments to be made by the Government to the Contractor under this contract or shall otherwise be credited to the price or cost of the work covered by this contract or paid in such other manner as the Contracting Officer may direct:

(8) Complete performance of such part of the work as shall not have been terminated by the Notice of Termination: and

(9) Take such action as may be necessary, or as the Contracting Officer may direct, for

the protection and preservation of the property related to this contract which is in the possession of the Contractor and in which the Government has or may acquire an interest.

At any time after expiration of the plant clearance period, as defined in Subpart 1-8.1 of the Federal Procurement Regulations (41 CFR 1-8.1), as the definition may be amended from time to time, the Contractor may submit to the Contracting Officer a list certified as to quantity and quality, of any or all items of termination inventory not previously disposed of, exclusive of items the disposition of which has been directed or authorized by the Contracting Officer, and may request the Government to remove such items or enter into a storage agreement covering them. Not later than fifteen (15) days thereafter, the Government will accept title to such items and remove them or enter into a storage agreement covering the same: Provided, That the list submitted shall be subject to verification by the Contracting Officer upon removal of the items or, if the items are stored, within forty-five (45) days from the date of submission of the list, and any necessary adjustment to correct the list as submitted shall be made prior to final settlement.

(c) After receipt of a Notice of Termination, the Contractor shall submit to the Contracting Officer his termination claim, in the form and with the certification prescribed by the Contracting Officer. Such claim shall be submitted promptly but in no event later than one year from the effective date of termination, unless one or more extensions in writing are granted by the Contracting Officer upon request of the Contractor made in writing within such one-year period or authorized extension thereof However, if the Contracting Officer determines that the facts justify such action, he may receive and act upon any such termination claim at any time after such one-year period or extension thereof. Upon failure of the Contractor to submit his termination claim within the time allowed, the Contracting Officer may, subject to any review required by the contracting agency's procedures in effect as of the date of execution of this contract, determine, on the basis of information available to him, the amount if any, due to the Contractor by reason of the termination and shall thereupon pay to the Contractor the amount so determined.

(d) Subject to the provisions of paragraph (c), and subject to any review required by the contracting agency's procedures in effect as of the date of execution of this contract, the Contractor and the Contracting Officer may agree upon the whole or any part of the amount or amounts to be paid to the Contractor by reason of the total or partial termination of work pursuant to this clause, which amount or amounts may include a reasonable allowance for profit on work done: Provided, That such agreed amount or

amounts, exclusive of settlement costs, shall not exceed the total contract price as reduced by the amount of payments otherwise made and as further reduced by the contract price of work not terminated. The contract shall be amended accordingly, and the Contractor shall be paid the agreed amount. Nothing in paragraph (e) of this clause, prescribing the amount to be paid to the Contractor in the event of failure of the Contractor and the Contracting Officer to agree upon the whole amount to be paid to the Contractor by reason of the termination of work pursuant to this clause, shall be deemed to limit, restrict, or otherwise determine or affect the amount or amounts which may be agreed upon to be paid to the Contractor pursuant to this paragraph (d).

(e) In the event of the failure of the Contractor and the Contracting Officer to agree as provided in paragraph (d) upon the whole amount to be paid to the Contractor by reason of the termination of work pursuant to this clause, the Contracting Officer shall, subject to any review required by the contracting agency's procedures in effect as of the date of execution of this contract, determine, on the basis of information available to him, the amount, if any, due to the Contractor by reason of the termination and shall pay to the Contractor the amounts determined as follows:

(1) With respect to all contract work performed prior to the effective date of the Notice of Termination, the total (without duplication of any items) of—

(1) The cost of such work;

(11) The cost of settling and paying claims arising out of the termination of work under subcontracts or orders as provided in paragraph (b) (5) above, exclusive of the amounts paid or payable on account of supplies or materials delivered or services furnished by the subcontractor prior to the effective date of the Notice of Termination of work under this contract, which amounts shall be included in the cost on account of which payment is made under (1) above; and

(111) A sum, as profit on (1), above, determined by the contracting officer pursuant to § 1-8.303 of the Federal Procurement Regulations (41 CFR 1-8.303), in effect as of the date of execution of this contract, to be fair and reasonable: Provided, however, That if It appears that the contractor would have sustained a loss on the entire contract had it been completed, no profit shall be included or allowed under this subdivision (ill) and an appropriate aajustment shall be made reducing the amount of the settlement to reflect the indicated rate of loss; and

(2) The reasonable cost of the preservation and protection of property incurred pursuant to paragraph (b) (9); and any other reasonable cost incidental to termination of work under this contract, including expense incidental to the determination of the amount due to the contractor as the result of the termination of work under this contract.

The total sum to be paid to the Contractor under (1) above shall not exceed the total contract price as reduced by the amount of payments otherwise made and as further reduced by the contract price of work not terminated. Except for normal spoilage, and except to the extent that the Government shall have otherwise expressly assumed the risk of loss, there shall be excluded from the amounts payable to the Contractor under (1) above, the fair value, as determined by the Contracting Officer, or property which is destroyed, lost, stolen, or damaged so as to become undeliverable to the Government, or to a buyer pursuant to paragraph (b) (7).

(f) Costs claimed. agreed to, or determined pursuant to paragraphs (c), (d), and (e) of this clause shall be in accordance with the contract cost principles and procedures in Part 1-15 of the Federal procurement regulations (41 CFR 1-15) in effect on the date of this contract.

(g) The Contractor shall have the right of appeal, under the clause of this contract entitled "Disputes," from any determination made by the Contracting Officer under paragraph (c) or (e) above, except that, if the Contractor has failed to submit his claim within the time provided in paragraph (c) above and has failed to request extension of such time, he shall have no such right of appeal. In any case where the Contracting Officer has made a determination of the amount due under paragraph (c) or (e) above, the Government shall pay to the Contractor the following: (1) if there is no right of appeal hereunder or if no timely appeal has been taken, the amount so determined by the Contracting Officer, or (2) if an appeal has been taken, the amount finally determined on such appeal.

(h) In arriving at the amount due the Contractor under this clause there shall be deducted (1) all unliquidated advance or other payments on account theretofore made to the Contractor, applicable to the terminated portion of this contract, (2) any claim which the Government may have against the Contractor in connection with this contract, and (3) the agreed price for, or the proceeds of sale of, any materials, supplies, or other things kept by the Contractor or sold, pursuant to the provisions of this clause, and not otherwise recovered by or credited to the Government.

(1) If the termination hereunder be partial, prior to the settlement of the terminated portion of this contract, the Contractor may fle with the Contracting Officer a request in writing for an equitable adjustment of the price or prices specified in the contract relating to the continued portion of the contract (the portion not terminated by the Notice of Termination), and such equitable adjustment as may be agreed upon shall be made in such price or prices; however, nothing contained herein shall limit the right of the Government and the Contractor to agree upon the amount or amounts to be paid to the Contractor for the completion

of the continued portion of the contract when said contract does not contain an estabilshed contract price for such continued portion.

(1) The Government may from time to time, under such terms and conditions as It may prescribe, make partial payments and payments on account against costs incurred by the Contractor in connection with the terminated portion of this contract whenever in the opinion of the Contracting Officer the aggregate of such payments shall be within the amount to which the Contractor will be entitled hereunder. If the total of such payments is in excess of the amount finally agreed or determined to be due under this clause, such excess shall be payable by the Contractor to the Government upon demand, together with interest computed at the rate of 6 percent per annum for the period from the date such excess payment is received by the Contractor to the date on which such excess is repaid to the Government: Provided, however, That no interest shall be charged with respect to any such excess pay.nent attributable to a reduction in the Contractor's claim by reason of retention or other disposition of termination inventory until ten days after the date of such retention or disposition, or such later date as determined by the Contracting Officer by reason of the circumstances.

(k) Unless otherwise provided for in this contract, or by applicable statute, the Contractor, from the effective date of termination and for a period of three years after final settlement under this contract, shall preserve and make available to the Government at all reasonable times at the office of the Contractor, but without direct charge to the Government, all his books, records, documents, and other evidence bearing on the costs and expenses of the Contractor under this contract and relating to the work terminated hereunder, or, to the extent approved by the Contracting Officer, photographs, microphotographs, or other authentic reproductions thereof.

[End of Clause]

[29 F.R. 10196. July 24, 1964, as amended at 35 F.R. 14990, Sept. 26, 1970; 37 FR 5296, Mar. 14, 1972]

§ 1-8.704 Research and development contracts with educational and other nonprofit institutions.

§ 1-8.704-1 Termination clause.

The following clause is applicable as prescribed in § 1-8.700-2(a) (4):

TERMINATION FOR CONVENIENCE OF THE
GOVERNMENT

(a) The performance of work under this contract may be terminated, in whole or from time to time in part, by the Government whenever for any reason the Contracting Officer shall determine that such termination is in the best interest of the

Government. Termination of work hereunder shall be effected by delivery to the Contractor of a Notice of Termination specifying the extent to which performance of work under the contract is terminated and the date upon which such termination becomes effective.

(b) After receipt of the Notice of Termination the Contractor shall cancel his outstanding commitments hereunder coverIng the procurement of materials, supplies, equipment, and miscellaneous items. In addition, the Contractor shall exercise all reasonable diligence to accomplish the cancellation or diversion of his outstanding commitments covering personal services and extending beyond the date of such termination to the extent that they relate to the performance of any work terminated by the notice. With respect to such canceled commitments the Contractor agrees to (1) settle all outstanding liabilities and all claims arising out of such cancellation of commitments, with the approval or ratification of the Contracting Officer, to the extent he may require, which approval or ratification shall be final for all purposes of this clause, and (2) assign to the Government. in the manner, at the time, and to the extent directed by the Contracting Officer, all of the right, title, and interest of the Contractor under the orders and subcontracts so terminated, in which case the Government shall have the right, in its discretion, to settle or pay any or all claims arising out of the termination of such orders and subcontracts.

(c) The Contractor shall submit his termination claim to the Contracting Officer promptly after receipt of a Notice of Termination, but in no event later than one year from the effective date thereof, unless one or more extensions in writing are granted by the Contracting Officer upon written request of the Contractor within such oneyear period or authorized extension thereof. Upon failure of the Contractor to submit his termination claim within the time allowed, the Contracting Officer may, subject to any review required by the contracting agency's procedures in effect as of the date of execution of this contract, determine, on the basis of information available to him, the amount, if any, due to the Contractor by reason of the termination and shall thereupon pay to the Contractor the amount so determined.

(d) Any determination of costs under paragraph (c) shall be governed by the contract cost principles and procedures in Subpart 1-15.3 of the Federal Procurement Regulations (41 CFR 1-15.3) in effect on the date of this contract, except that if the Contractor is not an educational institution any costs claimed, agreed to, or determined pursuant to paragraphs (c) or (e) hereof shall be in accordance with Subpart 1-15.2 of the Federal Procurement Regulations (41 CFR 115.2) in effect on the date of this contract.

(e) Subject to the provisions of paragraph (c) above, and subject to any review required by the contracting agency's procedures in effect as of the date of execution of this contract, the Contractor and the Contracting Officer may agree upon the whole or any part of the amount or amounts to be paid to the Contractor by reason of the termination under this clause, which amount or amounts may include any reasonable cancellation charges thereby incurred by the Contractor and any reasonable loss upon outstanding commitments for personal services which he is unable to cancel: Provided, however, That in connection with any outstanding commitments for personal services which the Contractor is unable to cancel, the Contractor shall have exercised reasonable diligence to divert such commitments to his other activities and operations. Any such agreement shall be embodied in an amendment to this contract and the Contractor shall be paid the agreed amount.

(1) The Government may from time to time, under such terms and conditions as it may prescribe, make partial payments against costs incurred by the Contractor in connection with the terminated portion of this contract, whenever, in the opinion of the Contracting Officer, the aggregate of such payments is within the amount to which the Contractor will be entitled hereunder. If the total of such payments is in excess of the amount finally agreed or determined to be due under this clause, such excess shall be payable by the Contractor to the Government upon demand: Provided, That if such excess is not so paid upon demand, interest thereon shall be payable by the Contractor to the Government at the rate of 6 percent per annum, beginning 30 days from the date of such demand.

(g) The Contractor agrees to transfer title to the Government and deliver in the manner, at the times, and to the extent, if any, directed by the Contracting Officer, such information and items which, if the contract had been completed, would have been required to be furnished to the Government, including:

(1) Completed

or partially completed plans, drawings, and information; and

(2) Materials or equipment produced or in process or acquired in connection with the performance of the work terminated by the notice.

Other than the above, any termination inventory resulting from the termination of the contract may, with the written approval of the Contracting Officer, be sold or acquired by the Contractor under the conditions prescribed by and at a price or prices approved by the Contracting Officer. The proceeds of any such disposition shall be applied in reduction of any payments to be made by the Government to the Contractor under this contract or shall otherwise be credited to the price or cost of work covered by this contract or paid in such other

« PreviousContinue »