paragraph (e) (1) (iv) (B) shall be deleted and the following shall be substituted therefor:

(B) In the event of the termination of this contract for default, the total fee payable shall be such proportionate part of the fee as the acceptable work in place bears to the total work in place required by the contract.

(4) The clause set forth in § 1-8.704-1 shall be used in any fixed-price type contract for experimental, developmental, or research work placed with an educational or nonprofit institution on a nofee or no-profit basis. The clause also shall be used in any cost-reimbursement type contract for experimental, developmental, or research work placed with an educational or nonprofit institution on a no-fee or no-profit basis, whenever the procuring activity considers t desirable to provide for termination of the contract for the convenience of the Government.

(5) The clause set forth in § 1-8.703 shall be used, except as otherwise permitted by § 1-8.700-2(a) (6), in any fixed-price construction contract in excess of $10,000 entered into by formal advertising or by negotiation.

(6) The short-form termination clause set forth in § 1-8.705-2 is authorized for use in any fixed-price construction contract which is not in excess of $100,000 in lieu of any other clause providing for termination for the convenlence of the Government. The clause also is authorized for use in contracts in excess of $100,000 when modified in the following manner: Designate the text of the clause prescribed in § 1-8.705-2 as paragraph (a) and add a paragraph (b) as follows:

(b) If this contract exceeds $100,000, the clause in 1-8.703 of the Federal Procurement Regulations (41 CFR 1-8.703) in effect on the date of this contract shall apply in lieu of the provisions set forth in (a), above, such clause being hereby incorporated by reference as fully as if set forth at length herein.

(7) Suggested clauses for use in certain subcontracts are covered in §§ 18.704-2 and 1-8.706.

(b) Termination for default clauses. (1) In any fixed-price supply contract, the clause set forth in § 1-8.707 shall be used when the contract is entered into

.

either (1) by formal advertising, or (ii) by negotiation (when for other than small purchases made in accordance with Subpart 1-3.6).

(2) In any cost-reimbursement type contract for (1) supplies, or (ii) experimental, developmental, or research work where a fee is contemplated, the clause set forth in § 1-8.702 shall be used whenever an agency considers it desirable to provide a termination for default clause in such a contract. The clause shall be used in all cost-reimbursement type construction contracts, as provided in paragraph (a)(3) of this section.

(3) In any fixed-price research and development contract except a contract 'awarded on the basis of no-profit to an educational or nonprofit institution, the clause set forth in § 1-8.710 shall be used whenever an agency considers it desirable to provide a termination for default clause in such a contract.

(4) In any fixed-price construction contract estimated to exceed $10,000, the clause set forth in § 1-8.709-1 shall be used, except as modified by the footnote to § 1-8.709-1, when the contract is entered into either (1) by formal advertising, or (1) by negotiation. During periods of national emergency, agencies may amend paragraph (d) of the clause as provided in § 1-16.404(e).

(5) In any fixed-price construction contract estimated not to exceed $10,000, the clause set forth in § 1-8.709-2 shall be used, except that when Standard Form 19 is used, the prescribed words "the clause of this contract entitled 'Disputes'" shall not be substituted for the words "Clause 3" in that form, when the contract is entered into either (1) by formal advertising, or (ii) by negotiation (when for other than small purchases made in accordance with Subpart 1-3.6).

(c) Excusable delays clause. A clause substantially as set forth in § 1-8.708 shall be used in a contract containing the termination clause set forth in § 1-8.702.

(d) Special termination clauses. Speclal termination clauses may be used in contracts such as letter contracts, time and materials contracts, labor-hour contracts, and facilities contracts for which no clauses are prescribed for use by (a) and (b) of this § 1-8.700-2; however, the

principles set forth in this Part 1-8 should be followed to the extent practicable.

[29 F.R. 10196, July 24, 1964, as amended at 32 F.R. 9683. July 4. 1967: 33 F.R 14287. Sept. 21, 1968; 40 FR 44140, Sept. 25, 1975] § 1-8.701 Termination clause for fixed. price contracts.

The following clause is applicable as prescribed in § 1-8.700-2(a)(1):

TERMINATION FOR CONVENIENCE OF THE
GOVERNMENT

(a) The performance of work under this contract may be terminated by the Government in accordance with this clause iD whole, or from time to time in part, whenever the Contracting Officer shall determine that such termination is in the best interest of the Government. Any such termination shall be effected by delivery to the Contractor of a Notice of Termination specifying the extent to which performance of work under the contract is terminated, and the date upon which such termination becomes effective.

(b) After receipt of a Notice of Termination, and except as otherwise directed by the Contracting Officer, the Contractor shall:

(1) Stop work under the contract on the date and to the extent specified in the Notice of Termination;

(2) Place no further orders or subcontracts for materials, services, or facilities. except as may be necessary for completion of such portion of the work under the contract as is not terminated;

(3) Terminate all orders and subcontracts to the extent that they relate to the performance of work terminated by the Notice of Termination;

(4) Assign to the Government, in the manner, at the times, and to the extent directed by the Contracting Officer. all of the right, title, and interest of the Contractor under the orders and subcontracts so terminated, in which case the Government shall have the right, in its discretion, to settle or pay any or all claims arising out of the termination of such orders and subcontracts;

(5) Settle all outstanding liabilities and all claims arising out of such termination of orders and subcontracts. with the approval or ratification of the Contracting Officer. to the extent he may require, which approval or ratification shall be final for all the purposes of this clause:

(6) Transfer title to the Government and deliver in the manner. at the times, and tc the extent, if any, directed by the Contracting officer. (1) the fabricated or unfabri cated parts, work in process. completed work supplies. and other material produced as a part of. or acquired in connection with the performance of, the work terminated by the

Notice of Termination, and (11) the completed or partially completed plans, draw. ings, information and other property which if the contract had been completed, would have been required to be furnished to the Government;

(7) Use his best efforts to sell, in the manner, at the times. to the extent, and at the price or prices directed or authorized by the Contracting Officer, any property of the types referred to in (6) above: Provided. however, That the Contractor (1) shall not be required to extend credit to any pur chaser, and (11) may acquire any such property under the conditions prescribed by and at a price or prices approved by the Contracting Officer: And provided further, That the proceeds of any such transfer or disposition shall be applied in reduction of any payments to be made by the Government to the Contractor under this contract or shall otherwise be credited to the price or cost of the work covered by this contract or paid in such other manner as the Contracting Officer may direct:

(8) Complete performance of such part of the work as shall not have been terminated by the Notice of Termination; and

(9) Take such action as may be necessary. or as the Contracting Officer may direct, for the protection and preservation of the property related to this contract which is in the possession of the Contractor and in which the Government has or may acquire an interest.

At any time after expiration of the plant clearance period. as defined in Subpart 1-8.1 of the Federal Procurement Regulations (41 CFR 1-8.1), as the definition may be amended from time to time, the Contractor may submit to the Contracting Officer a list, certified as to quantity and quality. of any or all items of termination inventory not previously disposed of, exclusive of items the disposition of which has been directed or authorized by the Contracting Officer, and may request the Government to remove such items or enter into a storage agreement covering them. Not later than fifteen (15) days thereafter, the Government will accept title to such items and remove them or enter into a storage agreement covering the same: Provided, That the list submitted shall be subject to verification by the Contracting Officer upon removal of the items or, if the items are stored, within forty-five (45) days from the date of submission of the list, and any necessary adJustment to correct the list as submitted shall be made prior to final settlement.

(c) After receipt of a Notice of Termination, the Contractor shall submit to the Contracting Officer his termination claim, in the form and with certification prescribed by the Contracting Officer. Such claims shall be submitted promptly but in no event later than one year from the effective date of

termination, unless one or more extensions in writing are granted by the Contracting Officer upon request of the Contractor made in writing within such one-year period or authorized extension thereof. However, if the Contracting Officer determines that the facts justify such action, he may receive and act upon any such termination claim at any time after such one-year period or any extension thereof. Upon failure of the Contractor to submit his termination claim within the time allowed, the Contracting Officer may, subject to any review required by the contracting agency's procedures in effect as of the date of execution of this contract, determine, on the basis of information available to him, the amount, if any, due to the Contractor by reason of the termination and shall thereupon pay to the Contractor the amount so determined.

(d) Subject to the provisions of paragraph (c), and subject to any review required by the contracting agency's procedures in effect as of the date of execution of this contract, the Contractor and the Contracting Officer may agree upon the whole or any part of the amount or amounts to be paid to the Contractor by reason of the total or partial termination of work pursuant to this clause, which amount or amounts may include a reasonable allowance for profit on work done: Provided, That such agreed amount or amounts, exclusive of settlement costs, shall not exceed the total contract price as reduced by the amount of payments otherwise made and as further reduced by the contract price of work not terminated. The contract shall be amended accordingly, and the Contractor shall be paid the agreed amount. Nothing in paragraph (e) of this clause, prescribing the amount to be paid to the Contractor in the event of failure of the Contractor and the Contracting Officer to agree upon the whole amount to be paid to the Contractor by reason of the termination of work pursuant to this clause, shall be deemed to limit, restrict, or otherwise determine or affect the amount or amounts which may be agreed upon to be paid to the Contractor pursuant to this paragraph (d).

(e) In the event of the failure of the Contractor and the Contracting Officer to agree as provided in paragraph (d) upon the whole amount to be paid to the Contractor by reason of the termination of work pursuant to this clause, the Contracting Officer shall, subject to any review required by the contracting agency's procedures in effect as of the date of execution of this contract, determine, on the basis of information available to him, the amount, if any, due to the Contractor by reason of the termination and shall pay to the Contractor the amounts determined as follows:

(1) For completed supplies accepted by the Government (or sold or acquired as provided in paragraph (b)(7) above) and not theretofore paid for, a sum equivalent to the aggregate price for such supplies computed

in accordance with the price or prices specifiled in the contract, appropriately adjusted for any saving of freight or other charges; (2) The total of

(1) The costs incurred in the performance of the work terminated, including initial costs and preparatory expense allocable thereto, but exclusive of any costs attributable to supplies paid or to be paid for under paragraph (e)(1) hereof;

(11) The cost of settling and paying claims arising out of the termination of work under subcontracts or orders, as provided in paragraph (b)(5) above, which are properly chargeable to the terminated portion of the contract (exclusive of amounts paid or payable on account of supplies or materials delivered or services furnished by subcontractors or vendors prior to the effective date of the Notice of Termination, which amounts shall be included in the costs payable under (1) above); and

(111) A sum, as profit on (1), above, determined by the contracting officer pursuant to § 1-8.303 of the Federal Procurement Regulations (41 CFR 1-8.303), in effect as of the date of execution of this contract, to be fair and reasonable: Provided, however, That if it appears that the contractor would have sustained a loss on the entire contract had it been completed, no profit shall be included or allowed under this subdivision (111) and an appropriate adjustment shall be made reducing the amount of the settlement to reflect the indicated rate of loss; and

(3) The reasonable costs of settlement, including accounting, legal, clerical, and other expenses reasonably necessary for the preparation of settlement claims and supporting data with respect to the terminated portion of the contract and for the termination and settlement of subcontracts thereunder, together with reasonable storage, transportation, and other costs incurred in connection with the protection or disposition of property allocable to this contract.

The total sum to be paid to the Contractor under (1) and (2) of this paragraph (e) shall not exceed the total contract price as reduced by the amount of payments otherwise made and as further reduced by the contract price of work not terminated. Except for normal spoilage, and except to the extent that the Government shall have otherwise expressly assumed the risk of loss, there shall be excluded from the amounts payable to the Contractor as provided in (e) (1) and (2) (1) above, the fair value, as determined by the Contracting Officer, of property which is destroyed, lost, stolen, or damaged so as to become undeliverable to the Government, or to a buyer pursuant to paragraph (b)(7). (1) Costs claimed, agreed to, or determined pursuant to paragraphs (c), (d), and (e) of this clause shall be in accordance with the applicable contract cost principles and procedures in Part 1-15 of the Federal procurement regulations (41 CFR 1-15) in effect on the date of this contract.

(g) The Contractor shall have the right to appeal, under the clause of this contract entitled "Disputes" from any determination made by the Contracting Officer under paragraph (c) or (e) above, except that, if the Contractor has failed to submit his claim within the time provided in paragraph (c) above and has failed to request extension of such time, he shall have no such right of appeal. In any case where the Contracting Officer has made a determination of the amount due under paragraph (c) or (e) above, the Government shall pay to the Contractor the following: (1) if there is on right of appeal hereunder or if no timely appeal has been taken, the amount so determined by the Contracting Officer; or (2) if an appeal has been taken, the amount finally determined on such appeal.

(h) In arriving at the amount due the Contractor under this clause there shall be deducted (1) all unliquidated advance or other payments on account theretofore made to the Contractor, applicable to the terminated portion of this contract; (2) any claim which the Government may have against the Contract in connection with this contract; and (3) the agreed price for, or the proceeds of sale of, any materials, supplies, or other things acquired by the Contractor or sold, pursuant to the provisions of this clause, and not otherwise recovered by or credited to the Government.

(1) If the termination hereunder be partial, prior to the settlement of the terminated portion of this contract, the Contractor may file with the Contracting Officer a request in writing for an equitable adjustment of the price or prices specified in the contract relating to the continued portion of the contract (the portion not terminated by the Notice of Termination), and such equitable adjustment as may be agreed upon shall be made in such price or prices.

(1) The Government may from time to time, under such terms and conditions as it may prescribe, make partial payments and payments on account against costs incurred by the Contractor in connection with the terminated portion of this contract whenever in the opinion of the Contracting Officer the aggregate of such payments shall be within the amount to which the Contractor will be entitled hereunder. If the total of such payments is in excess of the amount finally agreed or determined to be due under this clause, such excess shall be payable by the Contractor to the Government upon demand, together with interest computed at the rate of 6 percent per annum for the period from the date such excess payment is received by the Contractor to the date on which such excess is repaid to the Government: Provided, however, That no interest shall be charged with respect to any such excess payment attributable to a reduction in the Contractor's claim by reason of retention or other disposition of termina

tion inventory until ten days after the date of such retention or disposition, or such later date as determined by the Contracting Offcer by reason of the circumstances.

(k) Unless otherwise provided for in this contract, or by applicable statute, the Contractor, from the effective date of termination and for a period of three years after final settlement under this contract, shall preserve and make available to the Government at all reasonable times at the office of the Contractor but without direct charge to the Government, all his books, records, documents, and other evidence bearing on the costs and expenses of the Contractor under this contract and relating to the work terminated hereunder, or, to the extent approved by the Contracting Officer, photographs, microphotographs, or other authentic reproductions thereof.

[End of Clause]

[29 F.R. 10196, July 24, 1964, as amended at 35 F.R. 14990, Sept. 26, 1970; 37 FR 5296, Mar. 14, 1972]

§ 1-8.702

Termination clause for costreimbursement type contracts.

The following clause is applicable as prescribed in §§ 1-8.700–2(a) (3) and 1-8.700-2(b) (2):

TERMINATION FOR DEFAULT OR FOR CONVENIENCE OF THE GOVERNMENT

(a) The performance of work under the contract may be terminated by the Government in accordance with this clause in whole, or from time to time in part:

(1) Whenever the Contractor shall default in performance of this contract in accordance with its terms (including in the term "default" any such failure by the Contractor to make progress in the prosecution of the work hereunder as endangers such performance), and shall fall to cure such default within a period of ten days (or such longer period as the Contracting Office may allow) after receipt from the Contracting Officer of a notice specifying the default; or

(2) Whenever for any reason the Contracing Officer shall determine that such termination is in the best interest of the Government.

Any such termination shall be effected by delivery to the Contractor of a Notice of Termination specifying whether termination is for the default of the Contractor or for the convenience of the Government, the extent to which performance of work under the contract is terminated. and the date upon which such termination becomes effective. If, after notice of termination of this contract for default under (1) above, it is determined for any reason that the Contractor was not in default pursuant to (1), or that the Contractor's failure to perform or to make progress in performance is due to causes beyond

the control and without the fault or negligence of the Contractor pursuant to the provisions of the clause of this contract relating to excusable delays, the Notice of Termination shall be deemed to have been issued under (2) above, and the rights and obligations of the parties hereto shall in such event be governed accordingly.

(b) After receipt of a Notice of Termination and except as otherwise directed by the Contracting Officer. the Contractor shall:

(1) Stop work under the contract on the date and to the extent specified in the Notice of Termination;

(2) Place no further orders or subcontracts for materials, services, or facilities. except as may be necessary for completion of such portion of the work under the contract as is not terminated;

(3) Terminate all orders and subcontracts to the extent that they relate to the performance of work terminated by the Notice of Termination;

(4) Assign to the Government in the manner and to the extent directed by the Contracting Officer, all of the right, title, and interest of the Contractor under the orders or subcontracts so terminated, in which case the Government shall have the right, in its discretion, to settle or pay any or all claims arising out of the termination of such orders and subcontracts;

(5) With the approval or ratification of the Contracting Officer, to the extent he may require, which approval or ratification shall be final and conclusive for all purposes of this clause, settle all outstanding liabilities and all claims arising out of such termination of orders and subcontracts, the cost of which would be reimbursable in whole or in part, in accordance with the provisions of this contract;

(6) Transfer title to the Government (to the extent that title has not already been transferred) and deliver in the manner, at the times, and to the extent directed by the Contracting Officer, (1) the fabricated or unfabricated parts, work in process, completed work, supplies, and other material produced as a part of, or acquired in respect of the performance of. the work terminated by the Notice of Termination; (11) the completed or partially completed plans, drawings, information, and other property which. if the contract had been completed, would be required to be furnished to the Government; and (111) the jigs, dies, and fixtures, and other special tools and tooling acquired or manufactured for the performance of this contract for the cost of which the Contractor has been or will be reimbursed under this contract:

(7) Use his best efforts to sell, in the manner, at the times, to the extent. and at the price or prices directed or authorized by the Contracting Officer, any property of the types referred to in (6) above: Provided. however. That the Contractor (1) shall not be required to extend credit to any purchaser, and (ii) may acquire any such property

under the conditions prescribed by and at a price or prices approved by the Contracting Officer: And provided further, That the proceeds of any such transfer or disposition shall be applied in reduction of any payments to be made by the Government to the Contractor under this contract or shall otherwise be credited to the price or cost of the work covered by this contract or paid in such other manner as the Contracting Officer may direct;

(8) Complete performance of such part of the work as shall not have been terminated by the Notice of Termination; and

(9) Take such action as may be necessary, or as the Contracting Officer may direct, for the protection and preservation of the property related to this contract which is in the possession of the Contractor and in which the Government has or may acquire an interest.

The Contractor shall proceed immediately with the performance of the above obligations notwithstanding any delay in determining or adjusting the amount of the fee. or any item of reimbursable cost, under this clause. At any time after expiration of the plant clearance period, as defined in Subpart 1-8.1 of the Federal Procurement Regulations (41 CFR 1-8.1), as the definition may be amended from time to time, the Contractor may submit to the Contracting Officer a list, certified as to quantity and quality, of any or all items of termination inventory not previously disposed of, exclusive of items the disposition of which has been directed or authorized by the Contracting Officer, and may request the Government to remove such items or enter into a storage agreement covering them. Not later than fifteen (15) days thereafter, the Government will accept such items and remove them or enter into a storage agreement covering the same: Provided, That the list submitted shall be subject to verification by the Contracting Officer upon removal of the items or. If the items are stored, within forty-five (45) days from the date of submission of the list, and any necessary adjustment to correct the list as submitted shall be made prior to final settlement.

(c) After receipt of a Notice of Termination, the Contractor shall submit to the Contracting Officer his termination claim in the form and with the certification prescribed by the Contracting Officer Such claim shall be submitted promptly but in no event later than one year from the effective date of termination, unless one or more extensions in writing are granted by the Contracting Officer upon request of the Contractor made in writing within such one-year period or authorized extension thereof. However, if the Contracting Officer determines that the facts justify such action, he may receive and act upon any such termination claim at any time after such one-year period or any extension thereof. Upon failure of the Contractor to submit his termination claim