Reclamation Manual: Design and construction, pt. 2. Engineering design: Design supplement no. 2: Treatise on dams; Design supplement no. 3: Canals and related structures; Design supplement no. 4: Power systems; Design supplement no. 5: Field installation procedures; Design supplement no. 7: Valves, gates, and steel conduits; Design supplement no. 8: Miscellaneous mechanical equipment and facilities; Design supplement no. 9: Buildings; Design supplement no. 10: Transmission structures; Design supplement no. 11: Railroads, highways, and camp facilities, Volume 10 |
From inside the book
Results 1-5 of 100
Page
... Chief Engineer TABLE OF CONTENTS Paragraph 1.1.1 1.1.2 General Statement Work Execution Functions DESIGN 1.1.3 1.1.4 1.1.4A 1.1.4B 1.1.4C 1.1.5 1.1.5A 1.1.5B 1.1.5C 1.1.6 1.1.7 1.1.8 1.1.9 1.1.9A 1.1.9B 1.1.9C 1.1.9D 1.1.9E 1.1.9F 1.1 ...
... Chief Engineer TABLE OF CONTENTS Paragraph 1.1.1 1.1.2 General Statement Work Execution Functions DESIGN 1.1.3 1.1.4 1.1.4A 1.1.4B 1.1.4C 1.1.5 1.1.5A 1.1.5B 1.1.5C 1.1.6 1.1.7 1.1.8 1.1.9 1.1.9A 1.1.9B 1.1.9C 1.1.9D 1.1.9E 1.1.9F 1.1 ...
Page
... CHIEF ENGINEER .1 The principles governing the organization , lines of authority , division of responsibility , and organizational relationships of the Bureau are prescribed in Volume I. The Branch of Design and Construction , as a ...
... CHIEF ENGINEER .1 The principles governing the organization , lines of authority , division of responsibility , and organizational relationships of the Bureau are prescribed in Volume I. The Branch of Design and Construction , as a ...
Page
... Chief Engineer to the Regional Director . The written authorization for work to be performed in the region will include , to the extent practicable , authority to prepare cost estimates and specifications . B. The Chief Engineer may ...
... Chief Engineer to the Regional Director . The written authorization for work to be performed in the region will include , to the extent practicable , authority to prepare cost estimates and specifications . B. The Chief Engineer may ...
Page
... Chief Engineer is the contracting officer administration of construction RESPON- contracts is a line responsibility of the Chief Engineer . When the Chief Engineer SIBILITY determines , in collaboration with the Regional Director , that ...
... Chief Engineer is the contracting officer administration of construction RESPON- contracts is a line responsibility of the Chief Engineer . When the Chief Engineer SIBILITY determines , in collaboration with the Regional Director , that ...
Page
... CHIEF ENGINEER CONSTRUCTION ( Continued ) Likewise , the authorized representative of the contracting officer must recognize his position as an integral part of the regional and operating office organizations as well as a representative ...
... CHIEF ENGINEER CONSTRUCTION ( Continued ) Likewise , the authorized representative of the contracting officer must recognize his position as an integral part of the regional and operating office organizations as well as a representative ...
Other editions - View all
Common terms and phrases
5.2 SPECIFICATIONS aggregate amount approval authorized representative bid opening bidder bond borrow pit Branch of Design BUREAU OF RECLAMATION canal cement central Bureau laboratories CHAP Chapter Chief Engineer Commissioner completion concrete construction contracts Construction Engineer construction materials construction specifications Construction Through Award Cont contracting officer contractor copy cost estimates Design and Construction DESIGN DATA REQUIREMENTS DESIGNS AND ESTIMATES designs and specifications determine drawings embankment equipment Excavation extra work order facilities field furnished geologic Government grouting holes hydraulic inspector Installing instructions investigations Labor liquidated damages MANUAL Volume X maps operating office order for changes Paragraph pay items payment performance bond performed PIEZOMETER plant pozzolan prepared procedures PROPERTY CLASS RECLAMATION MANUAL Volume Regional Director request responsible revised riprap samples Secretary of Labor Sheet SPECIFICATIONS AND CONTRACT spillway structures subcontractor submitted supervision surety technical TION transmission lines transmitted United Volume X Design