from license fees and royalties for copyrighted material, patents, patent applications, trademarks, and inventions produced under an award. However, Patent and Trademark Amendments (35 U.S.C. Chapter 18) apply to inventions made under an experimental, developmental, or research award.

§ 600.125 Revision of budget and program plans.

(a) The budget plan is the financial expression of the project or program as approved during the award process. It includes the sum of the Federal and non-Federal share when there are cost sharing requirements. It shall be related to performance for program evaluation purposes whenever appropriate.

(b) Recipients are required to report deviations from budget and program plans, and request prior approvals for budget and program plan revisions, in accordance with this section.

(c) For nonconstruction awards, recipients shall request prior approvals from the DOE for one or more of the following program or budget related

reasons.

(1) Change in the scope or the objective of the project or program (even if there is no associated budget revision requiring prior written approval).

(2) Change in a key person specified in the application or award document.

(3) The absence for more than three months, or a 25 percent reduction in time devoted to the project, by the approved project director or principal investigator.

(4) The need for additional Federal funding.

(5) If required by program regulations, the transfer of amounts budgeted for indirect costs to absorb increases in direct costs, or vice versa.

(6) The inclusion, unless waived by program regulations or the terms and conditions of award, of costs that require prior approval in accordance with OMB Circular A-21, "Cost Principles for Institutions of Higher Education,” OMB Circular A-122, "Cost Principles for Non-Profit Organizations," or 45 CFR part 74 Appendix E, "Principles for Determining Costs Applicable to Research and Development under Grants and Contracts with Hospitals,"

or 48 CFR part 31, "Contract Cost Principles and Procedures," as applicable.

(7) The transfer of funds allotted for training allowances (direct payment to trainees) to other categories of expense.

(8) Unless described in the application and funded in the approved awards, the subaward, transfer or contracting out of any work under an award. This provision does not apply to the purchase of supplies, material, equipment or general support services.

(d) No other prior approval requirements for specific items may be imposed unless a deviation has been approved in accordance with § 600.4.

(e) Except for requirements listed in paragraphs (c)(1) and (c)(4) of this section, program regulations may waive cost-related and administrative prior written approvals required by this subpart and its Appendices. Such waivers may include authorizing recipients to do any one or more of the following.

(1) Incur pre-award costs 90 calendar days prior to award without prior approval or more than 90 calendar days with the prior approval of DOE. All pre-award costs are incurred at the recipient's risk (i.e., DOE is under no obligation to reimburse such costs if for any reason the recipient does not receive an award or if the award is less than anticipated and inadequate to cover such costs).

(2) Initiate a one-time extension of the expiration date of the final budget period of the project of up to 12 months unless one or more of the following conditions apply.

(i) The terms and conditions of award prohibit the extension.

(ii) The extension requires additional Federal funds.

(iii) The extension involves any change in the approved objectives or scope of the project.

(iv) The extension is being exercised merely for the purpose of using unobligated balances. For one-time extensions, the recipient must notify the DOE in writing with the supporting reasons and revised expiration date at least 10 days before the expiration date specified in the award.

(3) Carry forward unobligated balances to subsequent funding periods.

1

(4) For awards that support research, unless the terms and conditions of award provide otherwise, the prior approval requirements described in paragraph (e) of this section are automatically waived (i.e., recipients need not obtain such prior approvals) unless one of the conditions included in § 600.125(e)(2) applies.

(5) For continuation awards within a multiple year project in support of research, prior to receipt of continuation funding, preaward expenditures by recipients are not subject to the limitation or approval requirements of $600.125(e)(1). Nevertheless, incurrence by the recipient does not impose any obligation on DOE if a continuation award is not subsequently made, or if an award is made for a lesser amount than the recipient expected.

(f) Program regulations may restrict the transfer of funds among direct cost categories or programs, functions and activities for awards in which DOE's share of the project exceeds $100,000 and the cumulative amount of such transfers exceeds or is expected to exceed 10 percent of the total budget as last approved by DOE. However, no program regulation shall permit a transfer that would cause any Federal appropriation or part thereof to be used for purposes other than those consistent with the original intent of the appropriation.

(g) All other changes to nonconstruction budgets, except for the changes described in paragraph (j) of this section, do not require prior approval.

(h) For construction awards, recipients shall request prior written approval promptly from the Contracting Officer for budget revisions whenever paragraph (h) (1), (2) or (3) of this section apply.

(1) The revision results from changes in the scope or the objective of the project or program.

(2) The need arises for additional Federal funds to complete the project.

(3) A revision is desired which involves specific costs for which prior written approval requirements may be imposed consistent with applicable OMB cost principles listed in § 600.127.

(1) Except in accordance with the deviation procedures in 600.4 or as may be provided for in program regulations, no

other prior approval requirements for specific items will be imposed by DOE.

(j) When DOE makes an award that provides support for both construction and nonconstruction work, DOE may require the recipient to request prior approval from DOE before making any fund or budget transfers between the two types of work supported.

(k) For both construction and nonconstruction awards, recipients shall notify DOE in writing promptly whenever the amount of Federal authorized funds is expected to exceed the needs of the recipient for the project period by more than $5000 or five percent of the Federal award, whichever is greater. This notification shall not be required if an application for additional funding is submitted for a continuation award. (1) Requests for budget revisions may be made by letter.

(m) Within 30 calendar days from the date of receipt of the request for budget revisions, DOE shall review the request and notify the recipient whether the budget revisions have been approved. If the revision is still under consideration at the end of 30 calendar days, DOE shall inform the recipient in writing of the date when the recipient may expect the decision.

(n) DOE approval or disapproval of a request for a budget or project revision shall be in writing and signed by a DOE Contracting Officer.

(0) A request by a subrecipient for prior approval shall be addressed in writing to the recipient. The recipient shall promptly review such request and shall approve or disapprove the request in writing within 30 days from the date of the recipient's request for the revision. A recipient shall not approve any budget or project revision which is inconsistent with the purpose or terms and conditions of the DOE award. If the revision requested by the subrecipient would result in a change to the recipient's approved budget or approved project which requires DOE prior approval, the recipient shall obtain DOE approval before approving such revision.

§ 600.126 Non-Federal audits.

(a) Recipients and subrecipients that are institutions of higher education or

other non-profit organizations (including hospitals) shall be subject to the audit requirements contained in the Single Audit Act Amendments of 1996 (31 U.S.C. 7501-7507) and revised OMB Circular A-133, "Audits of States, Local Governments, and Non-Profit Organizations."

(b) State and local governments shall be subject to the audit requirements contained in the Single Audit Act Amendments of 1996 (31 U.S.C. 75017507) and revised OMB Circular A-133, "Audits of States, Local Governments, and Non-Profit Organizations."

(c) For-profit organizations that are subrecipients are subject to the audit requirements specified in 10 CFR 600.316.

[59 FR 53266, Oct. 21, 1994, as amended at 62 FR 45939, 45940, Aug. 29, 1997; 68 FR 50650, Aug. 21, 2003]

§ 600.127 Allowable costs.

(a) General. For each kind of recipient, there is a set of Federal principles for determining allowable costs. Allowability of costs shall be determined in accordance with the cost principles applicable to the entity incurring the costs. Thus, allowability of costs incurred by State, local or federally-recognized Indian tribal governments is determined in accordance with the provisions of OMB Circular A-87, "Cost Principles for State and Local Governments." The allowability of costs incurred by non-profit organizations is determined in accordance with the provisions of OMB Circular A-122, "Cost Principles for Non-Profit Organizations." The allowability of costs incurred by institutions of higher education is determined in accordance with the provisions of OMB Circular A21, "Cost Principles for Educational Institutions." The allowability of costs incurred by hospitals is determined in accordance with the provisions of Appendix E of 45 CFR part 74, "Principles for Determining Costs Applicable to Research and Development Under Grants and Contracts with Hospitals." The allowability of costs incurred by commercial organizations and those non-profit organizations listed in Attachment C to Circular A-122 is determined in accordance with the provi

sions of the Federal Acquisition Regulation (FAR) at 48 CFR part 31.

(b) Indirect costs. Unless restricted by Federal statute or program rule, DOE shall provide for the reimbursement of appropriate indirect costs.

(1) DOE shall include an amount for indirect costs in an award only if the applicant requests reimbursement of such costs and

(i) Submits evidence that a cognizant Federal agency has been assigned to establish indirect cost rates for the applicant and indicates or provides evidence that

(A) A current agreement containing an applicable approved indirect cost rate(s) covering all or part of the budget period for which DOE may provide funding has been established; or

(B) An indirect cost proposal has been submitted to the cognizant agency in order to establish an applicable approved indirect cost rate(s) covering all or part of the budget period for which DOE may provide funding; or

(C) An indirect cost proposal covering all or part of the budget period and applicable to the activities for which DOE may provide funding will be submitted to the cognizant agency for approval no later than three months after the beginning date of the initial budget period of the DOE award or, for subsequent budget periods, in accordance with any schedule established by the cognizant agency; or

(ii) If not assigned to a cognizant agency, the applicant includes, in the application, data that is current, complete, accurate, and sufficient to allow the Contracting Officer to determine a rate(s) for indirect costs. If the total approved budget will not exceed $100,000 or if the amount requested for indirect costs does not exceed $5,000, DOE may waive the requirement for negotiation of a rate and, in lieu thereof, provide a reasonable allowance for such costs.

(2) Indirect cost proposals shall be prepared and submitted in accordance with the applicable Federal cost principles and instructions from the cognizant agency or from DOE, as appropriate.

(3) If a subaward under an award or subaward provides for the payment of

indirect costs, the recipient or subrecipient shall be responsible for negotiating appropriate indirect costs, using the cost principles applicable to the subrecipient or contractor, unless the subrecipient or contractor has negotiated an applicable rate directly with DOE or another Federal department or agency. DOE may review and audit the procedures a recipient or subrecipient uses in conducting indirect cost negotiations.

(c) Fee or profit. No increment above cost may be paid to a recipient or subrecipient under a DOE award or subaward. A fee or profit may be paid to a contractor providing goods or services under a contract with a recipient or subrecipient.

[59 FR 53266, Oct. 21, 1994, as amended at 68 FR 50650, Aug. 21, 2003]

$600.128 Period of availability of funds.

Where a funding period is specified, a recipient may charge to the award only allowable costs resulting from obligations incurred during the funding period and any pre-award costs authorized by DOE.

Property Standards

$600.130 Purpose of property standards.

Sections 600.131 through 600.137 set forth uniform standards governing management and disposition of property furnished by the Federal Government or whose cost was charged to a project supported by a Federal award. Recipients shall observe these standards under awards and shall not impose additional requirements, unless specifically required by Federal statute or program regulations. The recipient may use its own property management standards and procedures provided it observes the provisions of §§ 600.131 through 600.137.

$600.131 Insurance coverage.

Recipients shall, at a minimum, provide the equivalent insurance coverage for real property and equipment acquired with DOE funds as provided to property owned by the recipient. Federally-owned property need not be in

sured unless required by the terms and conditions of the award.

§ 600.132 Real property.

Unless otherwise provided by statute or program regulations, the requirements concerning the use and disposition of real property acquired in whole or in part under awards are as follows.

(a) Title to real property shall vest in the recipient subject to the condition that the recipient shall use the real property for the authorized purpose of the project as long as it is needed and shall not encumber the property without approval of DOE.

(b) The recipient shall obtain written approval by DOE for the use of real property in other federally-sponsored projects when the recipient determines that the property is no longer needed for the purpose of the original project. Use in other projects shall be limited to those under federally-sponsored projects (i.e., awards) or programs that have purposes consistent with those authorized for support by DOE.

(c) When the real property is no longer needed as provided in paragraphs (a) and (b) of this section, the recipient shall request disposition instructions from DOE or its successor Federal awarding agency. DOE will give one or more of the following disposition instructions.

(1) The recipient may be permitted to retain title without further obligation to the Federal Government after it compensates the Federal Government for that percentage of the current fair market value of the property attributable to the Federal participation in the project.

(2) The recipient may be directed to sell the property under guidelines provided by DOE and pay the Federal Government for that percentage of the current fair market value of the property attributable to the Federal participation in the project (after deducting actual and reasonable selling and fix-up expenses, if any, from the sales proceeds). When the recipient is authorized or required to sell the property, proper sales procedures shall be established that provide for competition to the extent practicable and result in the highest possible return.

(3) The recipient may be directed to transfer title to the property to the Federal Government or to an eligible third party provided that, in such cases, the recipient shall be entitled to compensation for its attributable percentage of the current fair market value of the property.

$600.133 Federally-owned and exempt property.

(a) Federally-owned property.

(1) Title to federally-owned property remains vested in the Federal Government. Recipients shall submit annually an inventory listing of federally-owned property in their custody to DOE. Upon completion of the award or when the property is no longer needed, the recipient shall report the property to DOE for further Federal agency utilization.

(2) If DOE has no further need for the property, it shall be declared excess and reported to the General Services Administration, unless DOE has statutory authority to dispose of the property by alternative methods (e.g., the authority provided by the Federal Technology Transfer Act (15 U.S.C. 3710 (i)) to donate research equipment to educational and non-profit organizations in accordance with E.O. 12821, "Improving Mathematics and Science Education in Support of the National Education Goals.") Appropriate instructions shall be issued to the recipient by DOE.

(b) Exempt property. When statutory authority exists, DOE may vest title to property acquired with Federal funds in the recipient without further obligation to the Federal Government and under conditions DOE considers appropriate. For example, under 31 U.S.C. 6306, DOE may so vest title to tangible personal property under a grant or cooperative agreement for basic or applied research in a nonprofit institution of higher education or in a nonprofit organization whose primary purpose is conducting scientific research. Such property is "exempt property." Program regulations or the terms and conditions of award may establish provisions for vesting title to exempt property. Should such conditions not be established and the recipient has no need for the equipment, the recipient

shall request disposition instructions from DOE. If DOE does not issue disposition instructions within 120 calendar days of receipt of the request, title to the property shall vest in the recipient without further obligation to the Federal Government. If, at the end of the project, DOE fails to issue disposition instructions within 120 calendar days of the receipt of a final inventory, title to the property shall vest in the recipient without further obligation to the Federal Government.

$600.134 Equipment.

(a) Title to equipment acquired by a recipient with Federal funds shall vest in the recipient, subject to conditions of this section.

(b) The recipient shall not use equipment acquired with Federal funds to provide services to non-Federal outside organizations for a fee that is less than private companies charge for equivalent services, unless specifically authorized by Federal statute, for as long as the Federal Government retains an interest in the equipment.

(c) The recipient shall use the equipment in the project or program for which it was acquired as long as needed, whether or not the project or program continues to be supported by Federal funds and shall not encumber the property without approval of DOE. When no longer needed for the original project or program, the recipient shall use the equipment in connection with its other federally-sponsored activities, in the following order of priority:

(1) Activities sponsored by DOE, then (2) Activities sponsored by other Federal agencies.

(d) During the time that equipment is used on the project or program for which it was acquired, the recipient shall make it available for use on other projects or programs if such other use will not interfere with the work on the project or program for which the equipment was originally acquired. First preference for such other use shall be given to other projects or programs sponsored by DOE that financed the equipment; second preference shall be given to projects or programs sponsored by other Federal awarding agencies. If the equipment is owned by the