inform bidders or offerors of the basis on which their bids or proposals will be evaluated with respect to time of delivery or performance.

§ 1-1.316-3 Factors to be considered.

Factors to be considered in establishing delivery or performance schedules may include one or more of the following:

(a) Urgency of need for the property or services.

(b) Production time due to quantity. complexity of design, etc.

(c) Market conditions.
(d) Transportation time.
(e) Industry practices.

(f) Capabilities of small business concerns.

(g) Time for obtaining and evaluating bids or offers, and for awarding contracts.

(h) Time for contractors to comply with any conditions precedent to performance.

(i) Time for the Government to perform its obligations under the contract (e.g., furnishing of Government property to the contractor, approval or preproduction samples, and inspection). § 1-1.316-4

Terms.

(a) Delivery schedules may be expressed in terms of—

(1) Specific calendar dates (e.g., on or before July 1, 1960);

(2) Specified periods from date of contract (i.e., from date of award or acceptance by the Government, or from date shown on contract document as effective date of contract); or

(3) Specified periods from date of receipt by contractor of notice of award or acceptance by the Government (including notice by receipt of contract document executed by the Government). The full period which the Government holds out as being available for contract performance should not be curtailed to the prejudice of the contractor by delay in giving notice of award. Accordingly, one of the provisions in (b) or (c) of this § 1-1.316-4 shall be used in advertised precurements and may be suitably modifled and used as appropriate in negotiated procurements.

(b) Where the delivery schedule is expressed in terms of specific calendar dates (see (a)(1) of this § 1-1.316-4), invitations for bids shall include one of the following provisions:

[blocks in formation]

(1) The foregoing delivery requirements are based on the assumption that the Government will make award by (procuring activity insert calendar date). Each delivery date in the delivery schedule set forth herein will be extended by the number of calendar days after the above date that the contract is in fact awarded. Attention is directed to paragraph 8(d) of the Terms and Conditions of the Invitation for Bids, which provides that a written award mailed or otherwise furnished to the successful bidder results in a binding contract. Therefore, in computing the available time for performance, the bidder should take into consideration the time required for notice of award to arrive through the ordinary mails.

(2) The foregoing delivery requirements are based on the assumption that the successful bidder will receive that notice of award by (procuring activity insert calendar date). The Government will extend each delivery date in the delivery schedule set forth herein by the number of calendar days after the above date that the contractor receives notice of award, if the contractor promptly acknowledges such receipt.

(c) Where the delivery schedule is based on the date of contract (see (a) (2) of this § 1-1.316-4), the invitations for bids shall include the following provision:

Attention is directed to paragraph 8(d) of the Terms and Conditions of the Invitation for Bids, which provides that a written award mailed or otherwise furnished to the successful bidder results in a binding contract. Any award hereunder, or a preliminary notice thereof, will be mailed or otherwise furnished to the bidder the day the award is dated. Therefore, in computing the time available for performance, the bidder should take into consideration the time required for the notice of award to arrive through the ordinary malls. However, a bid offering delivery based on date of receipt by the contractor of the contract or notice of award (rather than contract date) will be evaluated by adding the maximum number of days normally required for delivery of the award through the ordinary mails. If, as so computed, the delivery date offered is later than the delivery date required in the invitation, the bid will be considered nonresponsive and rejected.

(d) Where the delivery schedule is based on the date of the contract (see (a) (2) and (c) of this § 1-1.316-4), the contract, notice of award, acceptance of proposal, or other contract document executed by the Government shall be mailed or otherwise furnished the contractor on the date shown thereon.

(e) Where the delivery schedule is based on date of receipt by the contractor of notice of award (see (a) (3) of this

§ 1-1.316-4), or where it is expressed in terms of specific calendar dates on the assumption that notice of award will be received by a specified date (see (b) (2) of this § 1-1.316-4), the notice of award, acceptance of proposal, or other contract document executed by the Government shall be sent by certified mail, return receipt requested, or by any other appropriate method which will provide evidence of the date of receipt.

(f) When the required delivery schedule in the invitation for bids is based on date of the contract (see (a) (2) of this § 1-1.316-4), a bid which offers delivery based on date of receipt by the contractor of the contract or notice of award (see (a) (3) of this § 1-1.316-4)

(1) Shall be evaluated by adding the maximum number of days normally required for delivery of the notice of award through the ordinary mails; and

(2) If the delivery date offered by the bid (computed in accordance with (f) (1) of this § 1-1.316-4) is later than the delivery date required in the invitation for bids, the bid shall be considered nonresponsive and rejected; but

(3) If award is made under (1) (1) of this 1-1.316-4, under the terms of the contract the delivery date will be computed on the basis of the number of days after actual receipt by the contractor of the notice of award as specifiled in the bid.

1-1.316-5 Time of delivery clauses.

(a) Examples of time of delivery clauses for invitations for bids are set forth below. They may be modified, or other clauses may be used, to state particular delivery requirements or any special procedures to be used in the evaluation, rejection, or award process as regards time of delivery. These clauses also may be suitably modified for use in negotiated procurements where appropriate.

(b) The following clause may be used where delivery by a particular time is necessary to meet the Government's requirements:

[blocks in formation]

filed above will be evaluated equally as regards time of delivery. Bids offering delivery of quantity under such terms or conditions that delivery will not clearly fall within the applicable delivery period specified above will be considered nonresponsive and will be reJected. Where a bidder offers an earlier delivery schedule than that called for above, the Government reserves the right to award either in accordance with the required sched'le or in accordance with the schedule offered by the bidder. If the bidder offers no other delivery schedule, the delivery schedule stated above shall apply.

Bidder's Proposed Delivery Schedule
(To Be Completed by Bidder)

[merged small][ocr errors][merged small][merged small][merged small][merged small][ocr errors][ocr errors][ocr errors]

•Contracting officer shall insert the appropriate one of the following phrases, in both of the indicated spaces:

(1) "On (on or before) the date(s) specined below."

(2) "Within the number of days stated below after the date of contracts."

(3) "Within the number of days stated below after the date of receipt of a written notice of award."

(4) "Within the periods specified below." (NOTE: When this phrase is inserted, the wording "during the month(s) of or "not sooner than than

the periods.)

and not later " should be used to specify

[merged small][merged small][merged small][merged small][merged small][merged small][ocr errors][merged small][merged small][merged small]

If the bidder is unable to meet the above delivery schedule, he may, without prejudice to the evaluation of his bid, set forth his Proposed Delivery Schedule below; but such delivery schedule must not extend the delivery period beyond the time for delivery called for in the following required delivery schedule:

Time

1

[blocks in formation]

-------- ------

[blocks in formation]
[merged small][merged small][merged small][ocr errors][merged small]

• Contracting officer shall insert the appropriate one of the following phrases, in each of the three indicated spaces:

(1) "On (on or before) the date(s) specified below."

(2) "Within the number of days stated below after date of contract."

(3) "Within the number of days stated below after the date of receipt of a written notice of award."

(4) "Within the periods specified below." (NOTE: When this phrase is inserted, the wording "during the month(s) of or "not sooner than than

the periods.)

and not later " should be used to specify

§ 1-1.317 Noncollusive bids and proposals.

(a) In order to promote full and free competition for Government contracts, the certification prescribed by this section shall be included in all (1) invitations for bids and (2) requests for proposals or quotations. Exceptions to this requirement include the following: Small purchases in accordance with Subpart 1-3.6, requests for technical proposals in connection with two-step formal advertising involving firm fixedprice contracts and fixed-price contracts with escalation, and contracts for utility services where rates are set by law or regulation.

CERTIFICATE OF INDEPENDENT PRICE
DETERMINATION

(a) By submission of this bid or proposal, each bidder or offeror certifies, and in the case of a joint bid or proposal each party thereto certifies as to its own organization, that in connection with this procurement:

(1) The prices in this bid or proposal have been arrived at independently, without consultation, communication, or agreement, for the purpose of restricting competition, as to any matter relating to such prices with any other bidder or offeror or with any competitor;

(2) Unless otherwise required by law, the prices which have been quoted in this bid

or proposal have not been knowingly disclosed by the bidder or offeror and will not knowingly be disclosed by the bidder or offeror prior to opening, in the case of a bid. or prior to award, in the case of a proposal, directly or indirectly to any other bidder or offeror or to any competitor; and

(3) No attempt has been made or will be made by the bidder or offeror to induce any other person or firm to submit or not to submit a bid or proposal for the purpose of restricting competition.

(b) Each person signing this bid or proposal certifies that:

(1) He is the person in the bidder's or offeror's organization responsible within that organization for the decision as to the prices being bid or offered herein and that he has not participated, and will not participate, in any action contrary to (a) (1) through (a) (3) above; or

(2) (1) He is not the person in the bidder's or offeror's organization responsible within that organization for the decision as to the prices being bid or offered herein but that he has been authorized in writing to act as agent for the persons responsible for such decision in certifying that such persons have not participated, and will not participate. in any action contrary to (a)(1) through (a) (3) above, and as their agent does hereby so certify; and (11) he has not participated, and will not participate, in any action contrary to (a) (1) through (a) (3) above.

(c) This certification is not applicable to a foreign bidder or offeror submitting a bid or proposal for a contract which requires performance or delivery outside the United States, its possessions, and Puerto Rico.

(d) A bid or proposal will not be considered for award where (a) (1), (a)(3), or (b) above has been deleted or modified. Where (a) (2) above has been deleted or modified, the bid or proposal will not be considered for award unless the bidder or offeror furnishes with the bid or proposal a signed statement which sets forth in detail the circumstances of the disclosure and the head of the agency, or his designee, determines that such disclosure was not made for the purpose of restricting competition.

(b) The fact that a firm (1) has published pricelists, rates, or tariffs covering items being procured by the Government, (2) has informed prospective customers of proposed or pending publication of new or revised pricelists for such items, or (3) has sold the same items to commercial customers at the same prices being offered the Government does not constitute, without more, a disclosure within the meaning of paragraph (a) (2) of the Certificate.

(c) It is not required that a separate written authorization be given to the signer of the bid or proposal for each procurement involved where the signer

makes the certification provided in paragraph (b) (2) of the Certificate: Provided, That with respect to any blanket authorization given, (1) the procurement to which the Certificate applies is clearly within the scope of such authorization, and (2) the person giving such authorization is the person responsible within the bidder's or offeror's organization for the decision as to the prices being bid or offered at the time the Certificate is made in a particular procurement.

(d) After the execution of an initial certificate and the award of a contract in connection therewith, the contractor need not submit additional certificates in connection with proposals submitted on "work orders" or similar ordering instruments issued pursuant to the terms of that contract. where the government's requirements cannot be met from another source.

(e) The authority to make the determination described in paragraph (d) of the above certification shall not be delegated to an official below the level of the head of a procuring activity of the agency.

(f) Where a certification is suspected of being false or there is indication of collusion. the matter shall be processed in accordance with Subpart 1-1.9 and appropriate agency procedures. For relection of bids which are suspected of being collusive and for the negotiation of procurements subsequent to such rejection, see §§ 1-2.404-1(b) (6) and 1-3.214.

[29 F.R. 10104, July 24, 1964. as amended at 30 F.R. 9589, July 31, 1965; 40 FR 60020, Dec. 31, 1975]

§ 1-1.318 Disputes clause. [33 F.R. 3064, Feb. 16, 1968] $1-1.318-1 Contracting officer's de

cision under a Disputes clause.

(a) When a final decision of the contracting officer concerns a dispute that is or may be subject to the Disputes clause, a paragraph substantially as follows shall be included in the decision:

This decision is made in accordance with the Disputes clause and shall be final and conclusive as provided therein, unless, withIn 30 days from the date of receipt of this decision, a written notice of appeal (in triplicate) addressed to the (Title of the head of the agency) is mailed or otherwise furnished to the Contracting Officer. The notice of appeal, which is to be signed by you as the contractor or by an attorney acting on your behalf, and which may be in letter

form, should indicate that an appeal is intended, should refer to this decision and should identify the contract by number. The notice of appeal may include a statement of the reasons why the decision is considered to be erroneous.

(b) A copy of each contracting offcer's decision shall be furnished to the contractor by certified mail, return_receipt requested, or by any other method which provides evidence of the date of receipt of the decision by the contractor. [33 F.R. 3064, Feb. 16, 1968]

§ 1-1.318-2 Relationship to the Equal Opportunity clause.

See 1-12.805-9 regarding disputed matters related to the equal opportunity program.

[33 F.R. 3064, Feb. 16, 1968]

§ 1-1.319

Procurement of items using jewel bearings.

(a) General. To maintain a jewel bearing production facility in the United States as a part of the industrial mobilization base, the Government owns and, through a contractor, operates the William Langer Jewel Bearing Plant at Rolla, N. Dak. The Director. Office of Emergency Preparedness, has requested that agencies use this source in order to promote the use of this plant as an estatlished domestic source of jewel bearings.

(b) Definitions. As used in this subpart the following terms have the meanings set forth in this paragraph:

(1) "Jewel bearing" means a piece of synthetic sapphire or ruby of any shape, except a phonograph needle, which has one or more polished surfaces and which is suitable for use in an instrument, mechanism, subassembly, or part without any additional processing. A jewel bearing may be either unmounted or mounted into a ring or bushing. Examples of jewel bearings are: Watch holes olive, watch holes-straight, pallet stones, roller jewels (jewel pins), end stones (caps), vee (cone) jewels, instrument rings, cups, double cups, and orifice jewels. As used herein, the term "jewel bearings" includes "related items."

(2) "Related items" means other synthetic sapphire or ruby components. Examples of related items are pivots, knife edges, insulators, spacers, windows, and striking

stones.

surfaces other than pallet

(3) "Price list" is the official U.S. Government Jewel Bearing Price List for jewel bearings produced by the William

Langer Jewel Bearing Plant. This list is issued periodically by the General Services Administration.

(4) "Plant" means the Governmentowned William Langer Jewel Bearing Plant, Rolla, N. Dak.

(5) "Military Standard Jewel Bearing" means a jewel bearing conforming to Military Specification No. MIL-B27497 (latest revision) entitled "Bearings, Jewel, Sapphire or Ruby, Synthetic."

(c) Policy. (1) The Office of Emergency Preparedness has determined that the William Langer Jewel Bearing Plant is an essential part of the national mobilization base and that its continued operation as a domestic source of jewel bearings is in the interest of the United States. Therefore, all direct Government purchases of jewel bearings shall be made from the Plant. In addition, all procurements of items in the Federal Supply Classes and Groups listed in paragraph (d) of this section, or subassembly, component, or part thereof, whether procured by the Government direct or through contractors, shall provide a requirement in the solicitations and resulting contracts that jewel bearings in the quantities and of the types and sizes (including tolerances) necessary for the end items to be supplied under the contract must be purchased from the Plant and be incorporated in the delivered items, except:

(1) In small purchases using small purchase procedures other than in purchases of jewel bearings as end items;

(ii) For jewel bearings used in items that are to be procured and used outside the United States, its possessions, and Puerto Rico;

(iii) When the procuring contracting officer has positive knowledge that the item being procured does not contain jewel bearings;

(iv) When quality standards and requirements are beyond the production capabilities of the Plant as evidenced by a written statement to that effect from the management of the Plant;

(v) In the case of requirements contracts (see § 1-3.409 (b)) and indefinite quantity contracts (see § 1-3.409 (c)) which authorize more than one activity to place orders upon the contractor. It is not practicable for a contractor to place an order with the Plant within 90 calendar days after the effective date of his contract for the entire amount of jewel bearings and related items that will be

required for the performance of the contract. Where such contracts are involved, the clause in § 1-1.319(e) may be changed by modifying paragraphs (b) and (c) to provide for procurement, on a quarterly or other periodic basis, of an amount of jewel bearings and related items equal to the amount (by type and size) of jewel bearings and related items actually used by the contractor in the performance of the contract during the period immediately preceding the ordering date. In addition, jewel bearings and related items so obtained shall be placed in the contractor's inventory for use in the performance of current or future Government contracts or for use in commercial production. Contracts which provide for periodic ordering on an actual use basis shall not be subject to the equitable adjustment provisions of paragraph (e) of the clause in § 1-1.319(e). Accordingly, the clause may be further modified to delete paragraph (e).

(vi) When the Plant's backlog of current business precludes delivery of the bearings within reasonable time limits, as confirmed in writing by the management of the Plant; or

(vii) When the urgency of the requirement for all or part of the procurement of a jeweled item is such that delivery of prefabricated end items available from the stock of any dealer, wholesaler, distributor, or manufacturer offers the best possible solution. In this event, however, the required source provisions of this § 1-1.319 will be exempted only to the extent that immediate deliveries are to be made of the specified quantity of end items. The required source provisions shall apply to any quantity in excess of that specified for immediate delivery.

(2) Whenever it is necessary to redesign or reengineer jeweled items to satisfy specific performance requirements, the manufacturer of an item shall be required to use military standard jewel bearings in the redesign. This requirement may be excepted only when the dimensional tolerances or configurations of the military standard jewel bearings are such that their use in the product would prevent attainment of the required level of performance specified for the items. However, when one or more nonstandard bearings must be used to satisfy the performance requirements of certain applications of a jeweled item but military standard jewel bearings will function satisfactorily for other applications of that item, the item shall be