(a) The Act empowers the President to authorize departments and agencies exercising functions in connection with the national defense to enter into contracts or into amendments or modifications of contracts and to make advance payments, without regard to other provisions of law relating to the making, performance, amendment, or modification of contracts, whenever he deems that such action would facilitate the national defense.

(b) The Executive Order authorizes the Administrator of NASA (hereinafter referred to as "the Administrator"), under regulations prescribed by him, to exercise the authority conferred by the Act.

(c) NASA General Management Instruction No. 2-4-4, September 23, 1959, (14 CFR Part 1209) establishes the Contract Adjustment Board (hereinafter referred to as "the Board") to dispose of requests for extraordinary contractual adjustments by NASA contractors.

§ 18-61.102 General policy.

The authority conferred by the Act shall be utilized primarily as an aid to procurement but shall not be utilized so as to encourage carelessness and laxity on the part of contractors nor be relied upon by NASA where other adequate legal authority exists. The actions authorized under the Act shall be processed as expeditiously as practicable but with the care, restraint, and sound judgment appropriate to the exercise of such extraordinary authority.

§ 18-61.103 Standards for deciding

cases.

(a) General. The mere fact that losses occur under a Government contract is not, by itself, a sufficient basis for the exercise of the authority conferred by the Act. Whether, in a particular case, appropriate action such as amendment without consideration, cor

rection of a mistake or ambiguity in a contract, or formalization of an informal commitment, will facilitate the national defense is a matter of sound judgment to be made on the basis of all of the facts of such case. Although it is obviously impossible to predict or enumerate all types of cases with respect to which action may be appropriate, examples of cases or types of cases where action may be proper are set forth in paragraphs (b), (c), and (d) of this section. Even if all of the factors contained in any of the examples are present, other factors or consideration in a particular case may result in a denial of the request. These examples are not intended to exclude other cases where the Board determines that the circumstances warrant action.

(b) Amendments without consideration. (1) Where an actual or threatened loss under a Government contract, however caused, will impair the productive ability of a contractor whose continued operation as a source of supply is found to be essential to the national defense, the contract may be adjusted but only to the extent necessary to avoid such impairment to the contractor's productive ability. (See § 18-61.105(b) and (c) for form of request.)

(2) Where a contractor suffers a loss (not merely a diminution of anticipated profits) on a Government contract as a result of Government action, the character of the Government action will generally determine whether any adjustment in the contract will be made and its extent. Where the Government action is directed primarily at the contractor and is taken by the Government in its capacity as the other contracting party, the contract may be adjusted if fairness so requires; thus, where such Government action, although not creating any liability on its part, increases the cost of performance, considerations of fairness may make appropriate some adjustment in the contract. (See § 1861.105 (b) and (d) for form of request.)

(c) Mistakes. A contract may be amended or modified to correct or mitigate the effect of a mistake, including the following examples:

(1) A mistake or ambiguity which consists of the failure to express or express clearly in a written contract the agreement as both parties understood it;

(2) A mistake on the part of the contractor which is so obvious that it was

74064 O-62-30

or should have been apparent to the contracting officer; and

(3) A mutual mistake as to a material fact.

Amending contracts to correct mistakes with the least possible delay normally will facilitate the national defense by expediting the procurement program and by giving contractors proper assurance that such mistakes will be corrected expeditiously and fairly. (See § 18-61.105 (b) and (e) for form of request.)

(d) Informal commitments. Informal commitments may be formalized under certain circumstances to permit payment to persons who have taken action without a formal contract; for example, where any person, pursuant to written or oral instructions from an official of NASA and relying in good faith upon the apparent authority of the official to issue such instructions, has arranged to furnish or has furnished property or services to NASA or to a Government contractor or subcontractor without formal contractual coverage for such property or services. Formalization of commitments under such circumstances normally will facilitate the national defense by assuring such persons that they will be treated fairly and paid expeditiously. (See § 18-61.105 (b) and (f) for form of request.)

[blocks in formation]

(a) The Act is not authority for: (1) The use of the cost-plus-a-percentage-of-cost system of contracting;

(2) Any contract in violation of existing law relating to limitation of profit or fees;

(3) The negotiation or purchases of or contracts for property or services required by law to be procured by formal advertising and competitive bidding;

(4) The waiver of any bid, payment, performance or other bond required by law;

(5) The amendment of a contract negotiated under 10 U.S.C. 2304 (a) (15) to increase the contract price to an amount higher than the lowest rejected bid of any responsible bidder; or

(6) The formalization or an informal commitment, unless it it found that at the time the commitment was made it was impracticable to use normal procurement procedures.

Page 445

[blocks in formation]

(a) Filing requests. Any contractor seeking an adjustment under the standards set forth may file a request in duplicate with the cognizant contracting officer or his duly authorized representative. If such filing is impracticable, requests will be deemed to be properly filed if filed with the Board or the Administrator.

(b) Form of requests in general. A request shall normally consist of a statement and exhibits covering all of the contractor's allegations and evidence.

(1) Statements. A statement, dated and signed by the contractor, should consist of the following:

(i) A chronological narrative of the essential facts, showing in detail the chain of events leading up to the request;

(ii) The contractor's conclusions based on such facts, showing in terms of the standards set forth in § 18-61.103 and the limitations set forth in § 18-61.104, why the contractor considers itself entitled to the adjustment requested; and

(iii) The precise adjustment requested, showing how it was formulated or computed and the consequences of granting or denying the request, including whether any proceeds from the request, if granted, will be subject to any assignment or other transfer, and to whom.

(2) Exhibits. Exhibits, cross-referenced to the statement, should consist of the following, if such matters are not fully set forth in the statement:

(i) The best evidence available to the contractor in support of any facts al

leged by the contractor, including contemporaneous memorar.da, correspondence, affidavits, and any other material tending to establish matters of fact;

(ii) If written contracts are involved, complete copies of or a brief description of the contracts, indicating the dates of execution and amendments thereto, the items being procured, the price or prices, the delivery schedule and revisions thereof, and such other special contractual provisions as may be relevant to the request;

(iii) A history of performance indicating when work under the contracts or commitments was begun, the progress made to the present, an exact statement of the contractor's remaining obligations, and the contractor's expectations regarding completion thereof;

(iv) A statement of payments received, payments due, and payments yet to be received or to become due, including advance and progress payments, and amounts withheld by the Government, and information as to other obligations of the Government, if any, which are yet to be performed under the contract;

(v) A statement giving a detailed analysis of the monetary elements of the request, including precisely how the actual or estimated dollar amount of the request was arrived at, the effect of approval or denial on the contractor's profits before Federal income taxes, and whether the costs for which reimbursement is requested have been included as a part of its gross costs in statutory renegotiation proceedings, together with the contractor's renegotiation status for the relevant years;

(vi) If a written contract is involved, a statement of the contractor's understanding of why the subject matter of the request cannot now and could not at the time if arose be disposed of under the terms of the contract itself;

(vii) Relevant financial statements, cost analyses, or other such data, preferably certified by a certified public accountant, including such additional financial data as is necessary to explain fully and to support the monetary elements of the request for adjustment;

(viii) A list of persons (in the employ of the Government. in the employ of the contractor, or otherwise connected with the contract) who have some factual knowledge of the subject matter, including where possible the name, office or

title, address and telephone number of each such person;

(ix) A statement and evidence of steps taken to mitigate loss and reduce claims to a minimum; and

(x) Such other statements or evidence as may be requested.

(c) Requests under § 18-61.103(b) (1). In addition to the matters of fact enumerated in § 18-61.105(b), where a request involves possible amendment without consideration, and "essentiality" is a factor, the contractor may be asked to furnish:

(1) A statement and evidence of the contractor's original breakdown of estimated costs, including contingency allowances and profit;

(2) A statement and evidence of the contractor's present estimate of total costs under the contracts involved if enabled to complete. broken down between costs accrued to date of request, and runout costs, and as between costs for which the contractor has made payment and those for which it is indebted at the time of the request;

(3) A statement and evidence of the contractor's estimate of the final price of the contracts involved giving effect to all escalation, changes, extras and the like, known or contemplated by the contractor;

(4) A statement of any claims known or contemplated by the contractor against the Government involving the contracts in question, other than those stated in response to § 18-61.105 (c) (3);

(5) An estimate of the total profit or loss under the contracts involved if enabled to complete at the final contract broken price (see § 18-61.105(c) (3)) down between profit or loss to date, and run-out profit or loss;

(6) An estimate of the total profits from other Government business, and all other sources, during the period from the date of the first contract involved to the estimated date of completion of all the contracts involved;

(7) A statement of the amount of any tax refunds and an estimate of those anticipated during or for the period from the date of the first contract involved through the estimated completion date of all the contracts involved;

(8) A statement in detail as to efforts the contractor has made to obtain funds

from commercial sources to enable it to complete performance of the contracts involved;

(9) A statement of the minimum amount necessary as an amendment without consideration to enable the contractor to complete performance of the contracts involved, and the detailed basis for that amount;

(10) An estimate of the time required to complete each contract if the request is granted;

(11) A statement of the factors which have caused the loss under the contracts involved;

(12) A statement as to the course of events anticipated if the request is denied;

(13) Balance sheets, preferably certified by a certified public accountant, as of the end of the contractor's fiscal year first preceding the date of the first contract, as of the end of each subsequent fiscal year, as of the date of the request, and projected as of the date of completion of all the contracts assuming the contractor is enabled to complete the contracts at the final prices estimated pursuant to § 18-61.105(c) (3), together with income statements for annual periods subsequent to the date of the first balance sheet. Balance sheets and income statements should be both consolidated, and by affiliates, and should show all transactions between the contractor and its affiliates, stockholders, and partners, including loans to the contractor guaranteed by any stockholder or partner; and

(14) A list of all salaries, bonuses and all other forms of compensation of the principal officers or partners and of all dividends and other withdrawals, and all payments to stockholders in any form since the date of the first contract involved.

(d) Requests under § 18-61.103(b) (2). In addition to the matters of fact enumerated in § 18-61.105(b), where a request involves possible amendment without consideration because of Government action, and "essentiality" is not a factor, the contractor may be asked to furnish:

(1) A clear statement of the precise Government action which the contractor considers caused a loss under the contract with evidence to support each essential fact;

(2) A statement and evidence of the contractor's original breakdown of estimated costs, including contingency allowances, and profit;

(3) The estimated total loss suffered under the contract, with detailed supporting analysis; and

(4) The estimated loss resulting from the Government action, with detailed supporting analysis.

(e) Requests under § 18-61.103 (c). In addition to the matters of fact enumerated in § 18-61.105(b), where a request involves possible correction of a mistake, the contractor may be asked to furnish:

(1) A statement and evidence of the precise mistake or error that was made, the ambiguity that exists, or the misunderstanding that arose, showing of what it consisted and how it occurred, and the intention of the parties;

(2) A statement explaining when the mistake was discovered, when notice of mistake was given to the contracting officer, and whether given before completion of work under, or the effective date of termination of, the contract;

(3) An estimate of loss or profit under the contract with detailed supporting analysis; and

(4) An estimate of the increase in cost to the Government resulting from the adjustment requested with detailed supporting analysis.

(f) Requests under § 18-61.103 (d). In addition to the matters of fact enumerated in § 18-61.105(b), where a request involves possible formalization of an informal commitment, the contractor may be asked to furnish:

(1) Copies of any written instructions or assurances, or a statement under oath of any oral instructions or assurances made to the contractor, with identification of the Government officer or official making such statement;

(2) A statement as to when the property or services were furnished or arranged to be furnished, and to whom;

(3) Evidence that the contractor relied upon the instructions or assurances, with a full description of the circumstances which led it so to rely, and that the contractor intended, at the time of performing the word, to be compensated directly for it by the Government and did not anticipate recovery of the costs in some other way;

(4) A cost breakdown supporting the amount claimed as a fair compensation for the work performed; and

(5) A statement and evidence of why it was impracticable to provide for the work performed in an appropriate contractual instrument.

§ 18-61.106 Disposition of cases.

(a) Investigation. A thorough investigation of all facts and issues relevant to a request shall be made. Facts and evidence shall be obtained from contractor and Government personnel, including signed statements of material facts within the knowledge of individuals where documentary evidence is lacking, and audits where considered necessary to establish financial or cost facts.

(b) Disposition. Upon receipt of cases, the Board, in accord with its own procedures, shall render decisions as expeditiously as practicable. A Memorandum of Decision disposing of the case shall be prepared for the signature of the Chairman of the Board, which shall be dated and contain the following information:

(1) The name and address of the contractor, the contract identification, and the nature of the request;

(2) The decision reached and the actual cost or estimated potential cost, if any, of the decision;

(3) A concise description of the property or services involved;

(4) A statement of the circumstances justifying the decision;

(5) If some adjustment action is approved, a statement in substantially the following form "The Board finds that the action authorized herein will facilitate the national defense."

The Memorandum of Decision shall omit any of the foregoing information classified "Confidential" or higher. The Board's decision will be communicated to the appropriate official for implementing action.

(c) Contractual Requirements. Every contract entered into or amended or modified pursuant to this section shall contain:

(1) A citation of the Act and Executive Order;

(2) A brief statement of the circumstances justifying the action;