...if no such appeal is taken, the decision of the Contracting Officer shall be final and conclusive. In connection with any appeal proceeding under this...Contractor shall be afforded an opportunity to be heard and to offer evidence in support of its appeal. Pending final decision of a dispute hereunder,... | |
| United States. Congress. House. Committee on Armed Services - Legislative hearings - 1960 - 1930 pages
...capricious, or arbitrary, or so grossly erroneous as necessarily to imply bad faith, or not sui>ported by substantial evidence. In connection with any appeal...contractor shall be afforded an opportunity to be heard and to offer evidence in support of its appeal. Pending final decision of a dispute hereunder,... | |
| Administrative law - 1975 - 168 pages
...to have been fraudulent, capricious, arbitrary or so grossly erroneous as necessarily to imply bad faith or not supported by substantial evidence. In...Pending final decision of a dispute hereunder, the Con• .-actor shall proceed diligently with the performance of the contract and in accordance with... | |
| Administrative law - 1979 - 1078 pages
...fraudulent or capricious or arbitrary or so grossly erroneous as necessarily to imply bad faith or is not supported by substantial evidence. In connection...support of his appeal. Pending final decision of a Title 41 — Public Contracts, Property Management dispute hereunder. the Contractor shall proceed... | |
| Administrative law - 1983 - 218 pages
...to have been fraudulent, capricious, arbitrary or so grossly erroneous as necessarily to imply bad faith or not supported by substantial evidence. In...to be heard and to offer evidence in support of his appen.l. Pending final decision of a dispute hereunder, the Contractor shall proceed diligently with... | |
| Administrative law - 1972 - 862 pages
...or so grossly erroneous as necessarily to Imply bad faith, or not supported by substantial evidence. The Contractor shall be afforded an opportunity to...hereunder. the Contractor shall proceed diligently with tne performance of the contract and In accordance with the Contracting officer's declalon. (b) This... | |
| Administrative law - 1982 - 536 pages
...imply bad faith, or not supported by substantial evidence. In connection with any appeal proceedings under this clause, the Contractor shall be afforded...of his appeal. Pending final decision of a dispute hercundcr, the Contractor shall proceed diligently with the performance of the contract and in accordance... | |
| Administrative law - 1981 - 524 pages
...imply bad faith, or not supported by substantial evidence. In connection with any appeal proceedings under this clause, the Contractor shall be afforded...of his appeal. Pending final decision of a dispute liereundcr, the Contractor shall proceed diligently with the performance of Ihc contract and in accordance... | |
| Administrative law - 1964 - 432 pages
...have been fraudulent, or capricious, or arbitrary, or so grossly erroneous as necessarily to imply bad faith, or not supported by substantial evidence. In...Contractor shall be afforded an opportunity to be heard and to offer evidence in support of its appeal. Pending final decision of a dispute hereunder,... | |
| Administrative law - 1978 - 880 pages
...ha<re been fraudulent, or capricious, or arbitrary, or so grossly erroneous as necessarily to Imply bad faith, or not supported by substantial evidence. In...proceeding under this clause, the Contractor shall be Chapter 3 — Dept. of Health, Education, and Welfare afforded an opportunity to be heard and to offer... | |
| |