Cases Decided in the Court of Claims of the United States, Volume 98U.S. Government Printing Office, 1943 - Law reports, digests, etc |
From inside the book
Results 1-5 of 100
Page 11
... additional work required in connection , with the underpinning , " that due note had been made of " this additional delay , " and that at the time of final settle- ment consideration would be given if necessary to the waiver of ...
... additional work required in connection , with the underpinning , " that due note had been made of " this additional delay , " and that at the time of final settle- ment consideration would be given if necessary to the waiver of ...
Page 14
... additional delay due to suspension of the bookstack detail- ing of 56 calendar days , due note of which had been made for the purpose of consideration in final settlement with a view to waiver of liquidated damages over a corresponding ...
... additional delay due to suspension of the bookstack detail- ing of 56 calendar days , due note of which had been made for the purpose of consideration in final settlement with a view to waiver of liquidated damages over a corresponding ...
Page 15
... additional work . Accordingly , plaintiff on February 19 , 1934 , submitted a proposal to the contracting officer for rerouting the air ducts at cost only , not including overhead or profit , in the sum of $ 467.45 and Change Order No ...
... additional work . Accordingly , plaintiff on February 19 , 1934 , submitted a proposal to the contracting officer for rerouting the air ducts at cost only , not including overhead or profit , in the sum of $ 467.45 and Change Order No ...
Page 18
... additional days on account of Sundays and holidays , or a total of 36 days . Because of the delays in the early part of the work , certain work that otherwise would have been done in summer or fall was done in the winter , and certain ...
... additional days on account of Sundays and holidays , or a total of 36 days . Because of the delays in the early part of the work , certain work that otherwise would have been done in summer or fall was done in the winter , and certain ...
Page 21
... addition which was re- flected in plaintiff's bid . The major part of the addition was made of newly quarried granite obtained from the same quarry as the original granite . Fabrication of the granite blocks was not done at the quarry ...
... addition which was re- flected in plaintiff's bid . The major part of the addition was made of newly quarried granite obtained from the same quarry as the original granite . Fabrication of the granite blocks was not done at the quarry ...
Other editions - View all
Common terms and phrases
additional agreement air mail alleged amended amount approved April asphaltic August Aviation Boeing Air Transport bricks Civil Service Civilian Conservation Corps claim for refund Commissioner Company completion Comptroller concrete conference Congress construction contracting officer contractor Corps Court 98 decedent defendant defendant's delay Director duty employees enactment entitled to recover extension extra fact February February 19 filed finding follows furnish Government increased costs Industrial Recovery Act issued January July June 16 labor lease letter liquidated damages March material ment National Industrial Recovery November October operators Opinion Pacific Air Transport paid paragraph Parker Pen Company patent payment period piles plaintiff Postmaster President prior Progress Administration Quartermaster Rankin & Kellogg Reemployment rental Reporter's Statement request Route A. M. route certificate space specifications Stat statute subcontractor submitted terra cotta thereof tiff tion transcontinental trust United United Air Lines Western Air Express
Popular passages
Page 305 - ... in such full, clear, concise, and exact terms as to enable any person skilled in the art or science to which it appertains, or with which it is most iiearly connected, to make, construct, compound, and use the same...
Page 123 - Title II of the National Industrial Recovery Act of June 16, 1933 (48 Stat.
Page 815 - The Secretary of War is the regular constitutional organ of the President for the administration of the military establishment of the nation, and rules and orders publicly promulgated through him must be received as the acts of the Executive, and, as such, be binding upon all, within the sphere of his legal and constitutional authority.
Page 678 - General may make such rules, regulations, and orders as may be necessary to carry out the provisions of this Act...
Page 605 - ... shall be paid just and reasonable wages which shall be compensation sufficient to provide, for the hours of labor as limited, a standard of living in decency and comfort...
Page 155 - Disputes. — Except as otherwise specifically provided in this contract, all disputes concerning questions of fact arising under this contract shall be decided by the contracting officer subject to written appeal by the contractor within 30 days to the head of the department concerned or his duly authorized representative, whose decision shall be final and conclusive upon the parties thereto. In the meantime the contractor shall diligently proceed with the work as directed.
Page 93 - ... laborers and mechanics employed by the contractor or any subcontractor on the work the...
Page 854 - That in making any reduction of force in any of the Executive Departments, the head of such Department shall retain those persons who may be equally qualified who have been honorably discharged from the military or naval service of the United States and the widows and orphans of deceased soldiers and sailors.
Page 94 - ... the Government may, by written notice to the Contractor, terminate his right to proceed with the work or such part of the work as to which there has been delay. In...
Page 187 - An act to codify, revise, and amend the laws relating to the judiciary...