in a district court of the United States or the United States Court of Federal Claims.

433.104 Protests to GAO.

The contracting activity shall furnish a copy of all reports submitted to the GAO, including all relevant documents, to the SPE simultaneously with their submission to the GAO.

Subpart 433.2-Disputes and
Appeals

433.203 Applicability.

The Assistant Secretary for Administration is authorized to determine the applicability of the Contract Disputes

Act to contracts with foreign governments pursuant to FAR 33.203.

433.203-70 Agriculture Board of Contract Appeals.

The organization, jurisdiction, and functions of the Agriculture Board of Contract Appeals, together with its Rules of Procedure, are set out in 7 CFR part 24.

433.209 Suspected fraudulent claims.

The contracting officer shall refer all matters related to suspected fraudulent claims by a contractor under the conditions in FAR 33.209 to the Office of Inspector General for additional action or investigation.

SUBCHAPTER F-SPECIAL CATEGORIES OF CONTRACTING

[blocks in formation]

Subpart 434.0-General

434.001 Definitions.

Pursuant to OMB Circular No. A-109 (A-109) and the definition at FAR 2.101, within USDA, a system shall be considered a major system if:

(a) The total acquisition costs with private industry are estimated to be $50 million or more, or

(b) The system has been specifically designated to be a major system by the USDA Acquisition Executive, even if the acquisition costs are not expected to exceed $50 million.

[61 FR 53646, Oct. 15, 1996, as amended at 63 FR 26995, May 15, 1998]

434.002 Policy.

In addition to the policy guidance at FAR 34.002, the policies outlined in paragraph 6 of A-109 should serve as guidelines for all contracting activities in planning and developing systems, major or otherwise.

434.003 Responsibilities.

(a) The Secretary of Agriculture or other designated USDA key executive is responsible for making four key decisions in each major system acquisition process. These are listed in paragraph 9 of A-109 and elaborated on in paragraphs 10 through 13. The key executives of USDA (Secretary, Deputy Secretary, Under Secretaries and Assistant Secretaries) individually or as a

group will participate in this decision making process.

(b) The Assistant Secretary for Administration (ASA) is the USDA Acquisition Executive. The ASA will ensure that A-109 is implemented in USDA and that the management objectives of the Circular are realized. The ASA is responsible for designating the program manager for each major system acquisition, designating an acquisition to be a major system acquisition, and approving the written charter and project control system for each major system acquisition.

(c) The Procurement and Property Management staff is responsible for assisting the ASA in carrying out the above responsibilities.

(d) Heads of contracting activities must:

(1) Ensure compliance with the requirements of A-109, FAR part 34 and AGAR 434.

(2) Ensure that potential major system acquisitions are brought to the attention of the USDA Acquisition Executive.

(3) Recommend qualified candidates for designation as program managers for each major system acquisition within their jurisdiction.

(4) Ensure that program managers fulfill their responsibilities and discharge their duties.

(5) Cooperate with the ASA in implementing the requirements of A-109.

(e) The program manager is responsible for planning and executing the major system acquisition, ensuring appropriate coordination with the USDA Acquisition Executive and other key USDA executives.

434.004 Acquisition strategy.

(a) The program manager will develop, in coordination with the Acquisition Executive, a written charter outlining the authority, responsibility, accountability, and budget for accomplishing the proposed objective.

(b) The program manager will develop, subject to the approval of the Acquisition Executive, a project control system to schedule, monitor, and regularly report on all aspects of the

[blocks in formation]

436.203 Government estimate of construction costs.

For acquisitions using sealed bid procedures, the contracting officer may disclose the overall amount of the Government's estimate of construction costs following identification of the responsive bid most advantageous to the Government; verification of that bid's price reasonableness; and verification of the bidder's responsibility. For acquisitions using other than sealed bid procedures (e.g., negotiation), the contracting officer may disclose the overall amount of the estimate after contract award.

436.204 Disclosure of the magnitude of construction projects.

In the case of indefinite-delivery type contracts, the reasonable estimate of work to be done or the maximum in the solicitation, both including all options, is to be used to select the price range. Contracting officers may elect to use both a price range for the base period of services and the total, inclusive of options, to best describe the magnitude of the solicitation.

436.205 Statutory cost limitations.

(a) When it appears that funds available for a project may be insufficient for all the desired features of construction, the contracting officer may provide in the solicitation for a base bid item covering the work generally as specified and for one or more additive or deductive bid items which progressively add or omit specified features of the work in a stated order of priority. In this case, the contracting officer shall insert the provision at 452.236-70, Additive or Deductive Items, in solicitations for construction.

(b) In the alternative to the process in paragraph (a) of this section, the contracting officer may use the policies and procedures found in FAR 17.2. 436.209 Construction contracts with architect-engineer firms.

The head of the contracting activity (HCA) is authorized to approve the award of a contract to construct a project, in whole or in part, to the firm (inclusive of its subsidiaries or affiliates) that designed the project.

436.213 Special procedures for sealed bidding in construction contracting.

436.213–2 Presolicitation notices.

The authority to waive a presolicitation notice is restricted to the HCA.

[63 FR 26995, May 15, 1998]

Subpart 436.3 [Reserved]

Subpart 436.5-Contract Clauses 436.500 Scope of subpart.

This subpart prescribes clauses for insertion in USDA solicitations and contracts for construction and for dismantling, demolition, or removal of improvements or structures. The contracting officer shall use the clauses as prescribed, in contracts that exceed the simplified acquisition threshold. The contracting officer may use the clauses if the contract amount is expected to be within the simplified acquisition threshold.

436.571 Prohibition against the use of lead-based paint.

The contracting officer shall insert the clause at 452.236-71, Prohibition Against the Use of Lead-Based Paint, in solicitations and contracts, if the work involves construction or rehabilitation (including dismantling, demolition, or removal) of residential structures. This clause may be used in contracts for other than residential structures.

436.572 Use of premises.

The contracting officer shall insert the clause at 452.236-72, Use of Premises, if the contractor will be permitted to use land or premises administered by USDA.

436.573 Archeological or historic sites.

The contracting officer shall insert the clause at 452.236-73, Archeological or Historic Sites, if the contractor will be working in an area where such sites may be found. Use of the clause is optional in service contracts for on-theground work, e.g. reforestation, silvicultural, land stabilization, or other agricultural-related projects.