tract as a war measure after such completion and settlement; it is held that plaintiff is not entitled to recover. Centaur Construction, 498.
XXIX. Without deciding whether, under the special provisions of Article 9 of the contract in suit, it was essential that the plaintiff file an appeal to the head of the department within 30 days after final rejection of its claims, or whether in the absence of an appeal, the contracting officer might have a reasonable time beyond this period within which to reconsider the merits of the claims; it is held that under the peculiar cir- cumstances of the instant case and the state of the record and the evidence, such a reasonable period, even if allowed, could not be extended as much as 16 months under the provisions of Article 9. King & Co. v. United States, 80 C. Cls. 325, and Rollins and Presbrey v. United States, 23 C. Cls. 106, are distinguished. Id.
'XXX. Under the broad powers of the First War Powers Act of 1941 (55 Stat. 838) and the Executive Order issued pursuant thereto, the contracting officer and the De- partment head had no authority to amend or modify a contract under which the work had been completed and final settlement effected. The First War Powers Act only authorized amendment or modification of future or pending contracts whenever it was deemed that such action would facilitate the prosecution of the war. Id.
XXXI. A traffic regulation at an Army post, which plaintiffs allege increased their cost of performance of a con- tract with the Government, was issued in the perform- ance of a governmental function, and for such an act the Government is not liable. Hallman Bros., 555. XXXII. The provision of the contract in suit relating to changed conditions referred to changed physical conditions af- fecting the performance of the contract and had no reference to such conditions as were brought about by a traffic regulation on an Army post issued subsequent to the signing of the contract. Id.
XXXIII. Where in a lump-sum contract it was provided that there should be an addition to or a deduction from the con- tract amount for rock excavation based on the quantity of rock actually excavated, more or less than the esti- mated quantity; and where the quantity of rock exca- vation was very much less than the estimated quantity and deduction was made accordingly at $7 per cubic yard as stipulated in the contract; it is held that the
plaintiff is not entitled to recover although the cost of rock excavation to the contractor was less than $7 per cubic yard. Hedin et al., 558.
XXXIV. Where the contractor submitted a lump-sum bid based in part upon the yardage of rock excavation estimated in the invitation for bids, and in the contract, which also fixed $7 per cubic yard as the price for excess or defi- ciency in the estimated quantity of rock excavation; and where the contractor, before submitting his bid, made no independent investigation as to the cost of rock excavation in the vicinity; and where the cost to the contractor of rock excavation turned out to be much less than the estimated $7 per cubic yard and the quantity of rock excavated turned out to be much less than the quantity estimated; and where in final settle- ment deduction was made accordingly; it is held that the plaintiff has not shown by the evidence that he is entitled to an equitable adjustment of the deduction. Id.
XXXV. Where plaintiff's construction contract included the in- stallation of plumbing facilities such as water lines, sanitary sewer lines and surface water drain pipes to points outside the exterior walls of the building, at which points connections would be made by other contractors with these facilities, and they would be extended, through ditches, to their destinations away from the new buildings; it is held that the plaintiff has not shown by the evidence that the work of laying sewer, water, and steam service lines, grading, leveling, and road and sidewalk construction, all of which was done by the Government as a W. P. A. project, was done in a manner so inconsiderate of plaintiff's in- terests as to constitute a breach of the contract and plaintiff is not entitled to recover. Id.
XXXVI. Where a considerable part of the blasting done on the W. P. A. project took place at such a distance from plaintiff's work that it could not have amounted to a substantial interference; and where the plaintiff, as shown by the evidence, maintained only incomplete and unsatisfactory records as to the alleged interference with the work by blasting, of which the Government had no notice and no opportunity to check the ac- curacy of such records; it is held that the plaintiff has not adequately proved any damages resulting from illegal interference with its work by the W. P. A. Id.
XXXVII. While discrepancies and inconsistencies are apparent in the evidence presented by the plaintiff, the Court holds that no such lack of good faith in the presentation of evidence has been shown as to amount to fraud within the meaning of section 172 of the Judicial Code (28 U. S. C. 279) and the Government's plea of fraud is dismissed. Id.
XXXVIII. Upon the authority of the decision of the Supreme Court in the case of United States v. Howard P. Foley Co., 329 U. S., it is held that the plaintiff is not entitled to recover. (See page 710, post.) Kelly Company, 594. XXXIX. Where there was unquestionably a delay of 82 days in the completion of the contract in suit; and where it is established that none of this delay was the fault of the plaintiff but since on the evidence adduced it is not possible to determine the portion of the delay for which the defendant was responsible and also not pos- sible to determine from the record the portion of the delay due to each of the two causes for delay; it is held that the record does not afford a sufficient ground for recovery on the part of the plaintiff even if re- covery were not barred by the decision in the Foley case. Id.
XL. Where plaintiff, a manufacturer, entered into a con- tract with the Government for the manufacture of a certain number of metal "waterproof" blanket con- tainers for use on life rafts carried on ships; and where certain tests made by the Government as to containers submitted under the contract were proper and reasonable and were sufficient to show that the containers were not "waterproof" within the intent and meaning of the contract; it is held that in the circumstances the defendant was justified in reject- ing the containers submitted and in terminating the contract as to the remainder, and its action in doing so did not constitute a breach of the contract, for which plaintiff would be entitled to recover. Newark Fire- proofing, 606.
XLI. It is immaterial, so far as plaintiff's right to recover is concerned, that defendant predicated its rejection of the manufactured containers and the termination of the contract as to the balance called for on the er- roneous ground that the containers did not satisfy a "watertight" test. See College Point Boat Co. v. United States, 267 U. S. 12. Id.
XLII. The terms "waterproof" and "watertight" are not used interchangeably either generally or in marine matters. While both terms generally signify imperviousness to water, the important difference between them, which is generally accepted and understood, is one of de- gree; "waterproof" signifying the lesser and "water- tight" the greater degree of imperviousness. Id. XLIII. Where plaintiff entered into a construction contract with the Government for the erection of temporary bar- racks, in response to an invitation for bids in which bidders were advised to visit the proposed sites and become acquainted with conditions; and where plain- tiff submitted its bid without inspecting the sites; it is held that plaintiff is not entitled to recover for ex- tra expense in excavations, since the conditions en- countered were not subsurface and latent conditions within the meaning of the contract. Walsh Brothers, 627.
XLIV. Where it was provided in the contract that the contractor should pay the prevailing wages in the vicinity; and where instead of paying carpenters 80 cents per hour, which was the minimum wage named in the specifica- tions and contract, it was necessary for plaintiff to pay carpenters $1.00 per hour; it is held that the Govern- ment's statement in the specifications was only a state- ment of an existing fact at the time and was not a war- ranty that, within the period of the performance of the contract, workmen would not demand an increase in wages, and plaintiff is not entitled to recover. Al- bert & Harrison, Inc. v. United States, ante 292, dis- tinguished, in which case the Government's statement as to what the prevailing wage had been found by the Secretary of Labor to be was erroneous. Id.
XLV. Where, on the one hand, the specifications stated that the natural grades of the respective sites would be the finished grades, and where, on the other hand, in the case of several of the buildings, when the sites were staked out, the grade marks on the stakes showed that they were to be built on a level terrace, formed by a considerable excavation on the uphill side and a corresponding fill on the downhill side of the build- ings; it is held that the plaintiff, without inspecting the sites, had a right to rely on the clear statement in the specifications as to how the buildings were to be located with reference to the natural grade and is entitled to recover on its claims (3 and 6) for extra excavation and fill. Id.
XLVI. Plaintiff is not entitled to recover on its claim for extra expense incurred by reason of alleged interference and delay by the work of other contractors engaged in installation of necessary utilities, since this was a condition reasonably to be expected in the circum- stances. Id.
XLVII. Delay in the work of plaintiff's subcontractor caused by difficulty in obtaining heating equipment was not ex- cusable within the meaning of article 9 of the contract, and plaintiff is not entitled to recover liquidated dam- ages deducted for late completion of the contract. Id. XLVIII. In a suit involving the title to certain real property in California, and plaintiff's claim that under a deed executed in 1909 she is entitled to either the royalties from an existing compensatory royalty agreement sub- sequently executed by the United States covering that land or to the value of the land itself; defendant's demurrer is overruled. Deterding, 656.
XLIX. Where the plaintiff's predecessor in title in 1909 made a deed providing that the land conveyed was to be used for the stated purpose of widening and straightening the Sacremento River in California "or for works or purposes incidental thereto or in connection there- with" with the stated understanding "that the grantors or their assigns shall have at all times the right to make such use of the lands hereby conveyed as may in the judgment of the grantee or his assigns hereunder be made without interfering in any manner with the said works or purposes for which this deed is made;" it is held that grantor's successor owned the exclusive right to take gas from the land conveyed, since the deed conveyed an easement to grantee and grantor retained the corporeal and residuary interest in the land. Id. L. Where grantee in deed which conveyed easement for the purpose of widening a river transferred grantee's inter- est to the United States, grantor retaining residuary interest in the land, the relation between grantor's successor and the United States in relation to their re- spective rights in the land involved was a conventional or contractual relation within the meaning of the stat- ute giving the Court of Claims jurisdiction of such rela- tions. (28 U. S. Code 250). Id.
LI. The provision in deed that grantor and his successor should have use of land for all purposes except the purpose of widening a river, for which grantee might use it, constituted an agreement that grantee and its
« PreviousContinue » |