...adjustment shall be made (a) in the estimated cost or delivery schedule, or both, and (b) in such other provisions of the contract as may be so affected,...Contracting Officer, if he decides that the facts justify sucn action, may receive and act upon any such claim asserted at any time prior to final payment under... | |
| Administrative law - 1985 - 592 pages
...equitable adjustment shall be made (i) in the contract price or time of performance, or both, and (ii) in such provisions of the contract as may be so affected,...Provided, however, That the Contracting Officer, if he/she decides that the facts justify such action, may receive and act upon any such claim asserted... | |
| Administrative law - 2000 - 568 pages
...equitable adjustment shall be made (1) in the contract price or time of performance, or both, and (ii) in such provisions of the contract as may be so affected,...Provided, however. That the Contracting Officer, if he/she decides that the facts justify such action, may receive and act upon any such claim asserted... | |
| Administrative law - 1999 - 574 pages
...adjustment shall be made (a) in the estimated cost or delivery schedule, or both, and (b) in such other provisions of the contract as may be so affected,...Provided, however, That the Contracting Officer, if he/she decides that the facts justify such action, may receive and act upon any such claim asserted... | |
| Administrative law - 1980 - 874 pages
...equitable adjustment shall be made (i) in the contract price or time of performance, or both, and (il) in such provisions of the contract as may be so affected,...of the notification of change; Provided, however. Title 41 — Public Contract*, Property Management That the Contracting Officer, If he decides that... | |
| Administrative law - 1967 - 2356 pages
...equitable adjustment shall be made in the estimated cost, the completion schedule, or both, and the contract shall be modified in writing accordingly....That the Contracting Officer, If he decides that the fact! justify such action, may receive and act upon any such claim asserted at any time prior to anal... | |
| Administrative law - 1989 - 660 pages
...in such other provisions of the contract as may be so affected, and the contract shall be modifled in writing accordingly. Any claim by the Contractor...Provided, however, That the Contracting Officer, if he/she decides that the facts justify such action, may receive and act upon any such claim asserted... | |
| Administrative law - 1976 - 1202 pages
...to be paid to the Contractor, and (iii) in such other provisions of the contract as may be affected, contract shall be modified in writing accordingly....of the notification of change; provided, however, thai the Contracting Officer, if he decides that the facts justify such action, may receive and act... | |
| Administrative law - 1955 - 1316 pages
...or both, (11) In the amount of any fixed fee to be paid to the Contractor, and (111) In such other provisions of the contract as may be so affected,...must be asserted within thirty (30) days from the day of receipt by the Contractor of the notification of change: Provided, however, That the Contracting... | |
| Administrative law - 1975 - 252 pages
...Any claim by the Contractor for adjustment under this clause must be asserted within 30 calendar days from the date of receipt by the Contractor of the...justify such action, may receive and act upon any such Ğlaim asserted at any tune prior to final payment •under the contract. Failure to agree to any adjustment... | |
| |