Environmental tests consisted of vibration runs in the X, Y, and Z axis (fig. 25, p. 90) and two complete mission tests performed in real time in the simulated space environment, one above and one below expected flight temperatures. At this point in the test program, limited inspection of spacecraft electronic equipment was carried out to establish that no degradation had resulted from exposure to the environmental testing.

I would like to ask Mr. Schurmeier if he has comments to make about these pictures as you turn through them.

Mr. SCHURMEIER. The first picture shows the complete spacecraft, bus, and TV subsystem on the system test fixture, and in the process of undergoing system tests.

The next picture is just a view showing the ground support equipment that is used to check out the spacecraft for a system test.

The next one shows the process of mating the flight spacecraft to the Agena adapter. Here we check to see if the mechanical fit is correct, that the electrical connections are correct, that there is continuity, that the couplers to the antennas are in the proper position, and that we measure the right signal levels through them.

The following one shows the spacecraft on the larger shaker undergoing Z-axis vibration.

[graphic][subsumed][subsumed][subsumed][merged small]
[graphic][subsumed][subsumed][merged small]

Mr. NICKS. A preshipment system test was performed and the spacecraft was prepared for shipment to AMR on October 21, 1963. On that date, the schedule was delayed and spacecraft operations were suspended because of the discovery of contamination in diodes used in several spacecraft subsystems. While no failures had occurred in

Ranger VI subsystems because of contaminated diodes, a potential failure possibility had been reported by other agencies and confirmed by JPL analysts. Consequently the launch date for Ranger VI was rescheduled from early December 1963, to late January 1964 to permit the replacement of the suspect diodes.

Following delivery of the reworked equipment, a system test was performed and the spacecraft was subject to a real-time mission test in the space simulator. The latter test was used as the preshipment verification test, after which the spacecraft and associated system test complex equipment were shipped to AMR on December 19, 1963. Shipment was accomplished in instrumented and escorted air-ride motorvans to insure the safe transport of the equipment.

After arrival of the spacecraft and system test complex equipment at AMR, the television subsystem was installed on the spacecraft and an initial system test and backup functions system test were performed to insure proper spacecraft performance. The spacecraft was then transported to the explosive safe area (ESA), where the vehicle adapter and flight shroud were installed. Following an electrical check of the spacecraft, it was moved to launch complex 12, where the spacecraft was installed on the Atlas-Agena launch vehicle. A precountdown dummy run and a countdown dummy run were then conducted to establish compatibility between the spacecraft in a launch configuration and the launch checkout equipment in the blockhouse. A joint flight acceptance composite test (J-FACT) was then performed. This test involved the launch vehicle, the spacecraft, and the associated AMR installations in a simulated post liftoff sequence following removal of umbilical plugs from the launch vehicle. Prior to the dummy run and the J-FACT, a joint radiofrequency interference (RFI) test was performed; because of nonstandard results, this test was satisfactorily repeated after the J-FACT was completed. The spacecraft was then removed from the launch pad and transported to the spacecraft checkout facility for final flight preparations. The final system test was performed on January 18 and the spacecraft was taken to the ESA on January 20 where, following installation of the fueled midcourse motor, the television subsystem was mounted on the spacecraft for flight. The final electrical connections were then made and verified. The flight adapter and shroud were installed and an electrical checkout of the spacecraft was performed, including operation of lights in the shroud so as to verify proper functioning of the television cameras. This operation was performed in a reduced power mode because of the live pyrotechnics installed in the spacecraft. The spacecraft was then transported to the launch pad and reinstalled on the launch vehicle. Figure 26, page 92, shows the spacecraft completely enclosed and protected by the shroud and adapter combination being hoisted up the gantry. During the precountdown test, the television subsystem was again checked in the reduced power mode, utilizing the shroud lights to verify proper camera performance. Two days before launch, a simulated launch countdown was conducted, a test similar to the launch countdown and involving the spacecraft, the launch vehicle, and range installations. All operations were performed as in the actual countdown, except for installation of launch vehicle pyrotechnics and fueling of the second stage.

[graphic][merged small]

I think you should look at the chart on the next page before we go on. This shows the configuration in which the spacecraft is delivered to the launch vehicle. You will note that it is completely enclosed. This is a one-piece shroud that comes off over the top, and the power checks are made inside that shroud.

Figure 27, page 93, summarizes how the hours of spacecraft operations were distributed between the various types of tests. It also shows how the problem/failures were distributed between the various phases of the operations.