Clean Coal TechnologyDepartment of Energy, Assistant Secretary, Management and Administration, Procurement and Assistance Management, Office of Procurement Operations, 1986 - Clean coal technologies |
From inside the book
Results 1-5 of 100
Page ii
... Cost Evaluation Criteria . " The program policy factors appli- cable to this PON are described in SECTION V.3.5 ... cost and pricing data . DOE may award a cooperative agreement based on initial proposals received , without discussion of ...
... Cost Evaluation Criteria . " The program policy factors appli- cable to this PON are described in SECTION V.3.5 ... cost and pricing data . DOE may award a cooperative agreement based on initial proposals received , without discussion of ...
Page viii
... COST EVALUATION CRITERIA V - 11 3.4 RELATIVE IMPORTANCE OF PROPOSAL VOLUMES V - 11 3.5 PROGRAM POLICY FACTORS V - 11 VI GOVERNMENT FINANCIAL PARTICIPATION VI - 1 1. AMOUNT OF COST - SHARING REQUIRED VI - 1 2 . PROJECT COSTS NOT ALLOWED FOR ...
... COST EVALUATION CRITERIA V - 11 3.4 RELATIVE IMPORTANCE OF PROPOSAL VOLUMES V - 11 3.5 PROGRAM POLICY FACTORS V - 11 VI GOVERNMENT FINANCIAL PARTICIPATION VI - 1 1. AMOUNT OF COST - SHARING REQUIRED VI - 1 2 . PROJECT COSTS NOT ALLOWED FOR ...
Page 11
... cost of overruns in the event that the Government agrees to share such costs . In addition , $ 4.9 million will be reprogrammed for the Small Business and Innovative Research Program , and unavailable to the Clean Coal Technology ...
... cost of overruns in the event that the Government agrees to share such costs . In addition , $ 4.9 million will be reprogrammed for the Small Business and Innovative Research Program , and unavailable to the Clean Coal Technology ...
Page 19
... Cost Proposal - Project cost data shall be excluded from the technical proposal ex- cept for the limited amount of cost data needed to clarify and verify such aspects as marketability and design decisions . Each of III - 19.
... Cost Proposal - Project cost data shall be excluded from the technical proposal ex- cept for the limited amount of cost data needed to clarify and verify such aspects as marketability and design decisions . Each of III - 19.
Page 28
... cost or pricing data , the nego- tiated cost ( including the Government's cost - share ) will be subject to reduction if cost or pricing data furnished are incomplete , inaccurate , or not current . 38. RIGHTS IN TECHNICAL DATA The ...
... cost or pricing data , the nego- tiated cost ( including the Government's cost - share ) will be subject to reduction if cost or pricing data furnished are incomplete , inaccurate , or not current . 38. RIGHTS IN TECHNICAL DATA The ...
Common terms and phrases
activities amount appropriate approved Assistance Budget Information Assistance Management Summary Assistance Reporting Checklist award baseline plans BDOE breakdown structure Budget Information Form budget period clause Clean Air Act clean coal technology commercial completed Compliance Consulting Agencies Contracting Officer Cooperative Agreement Corporation cost or pricing cost-sharing criteria Department of Energy emissions Energy Security Act Enter equipment Evaluation facility Federal Acquisition Regulation Federal Assistance Budget Federal Assistance Management Federal Assistance Reporting fiscal funds Government grant Guidelines identification number identified impacts Item Line Management Summary Report offeror Outlines and Plans paragraph Participant Patent Counsel performance Phase PHYSICAL UNITS plans and reports pricing data project cost proposed project proposed technology real property recipient reporting period reporting requirements request schedule Section share small business concerns solicitation specified Sponsor Stephen Logan subcontract subject invention submitted Supplemental Monitoring Synthetic Fuels Synthetic Fuels Corporation technical data United utility
Popular passages
Page 3 - ... against the United States in the Court of Claims for the recovery of his reasonable and entire compensation for such use and manufacture.
Page 2 - Program; (2) Provide adequate and timely consideration of the potentialities of labor surplus area concerns in all " make-or-buy " decisions; (3) Assure that labor surplus area concerns will have an equitable opportunity to compete for subcontracts, particularly by arranging solicitations, time for the preparation of bids, quantities, specifications, and delivery schedules so as to facilitate the participation of...
Page 5 - Nothing contained in this clause shall imply a license to the Government under any patent or be construed as affecting the scope of any license or other right otherwise granted to the Government under any patent.