" Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change: Provided, however, That the Contracting Officer, If he decides that the facts Justify such action, may... "
The Code of Federal Regulations of the United States of America - Page 204
1967
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1977 - 944 pages
...provided they are not Inconsistent with the clause or the provisions of these regulations. § 1-7.102-2 Changes. CHANGES The Contracting Officer may at any...excuse the Contractor from proceeding with the contract и changed. § 1-7.102-3 Extras. EXTRAS Except as otherwise provided In this contract, no payment for...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1979 - 1304 pages
...sureties, make changes, within the general scope of this contract, in any one or more of the following: (i) Drawings, designs, or specifications, where the supplies...Contractor from proceeding with the contract as changed. § 1-7.102-3 Extras. EXTRAS Except as otherwise provided in this contract, no payment for extras shall...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1983 - 716 pages
...sureties, make changes, within the general scope of this contract, in any one or more of the following: (i) Drawings, designs, or specifications, where the supplies...Contractor from proceeding with the contract as changed. Chapter 1 — Federal Procurement Regulation» в 1-7.102-3 Extra«. EXTRAS Except as otherwise provided...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1964 - 432 pages
...of the following: (i) Drawings, designs, or specifications, where the supplies to be furnished arc to be specially manufactured for the Government in...excuse the Contractor from proceeding with the contract aa changed. 3. EXTRAS Except as otherwise provided in this contract, no payment for extras shall be...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1984 - 720 pages
...manufactured for the Government in accordance therewith: (II) method of shipment or packing; and (ill) place of delivery. If any such change causes an increase...Contractor from proceeding with the contract as changed. §1-7.102-3 Extras. EXTRAS Except as otherwise provided in this contract, no payment for extras shall...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1982 - 690 pages
...manufactured for the Government in accordance therewith; (ii) method of shipment or packing; and (ill) place of delivery. If any such change causes an increase...Contractor from proceeding with the contract as changed. § 1-7.102-3 Extras. EXTRAS Except as otherwise provided in this contract, no payment for extras shall...
Full view - About this book

Code of Federal Regulations: 1949-1984

Administrative law - 1977 - 1240 pages
...manufactured for the Government in accordance therewith; (11) method of shipment or packing; and (ill) place of delivery. If any such change causes an Increase...excuse the Contractor from proceeding with the contract ai changed. § 1-7.102-3 Extras. EXTRAS Except as otherwise provided in this contract, no payment for...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1983 - 780 pages
...accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within thirty (30) days from the date of receipt by the Contractor...Contractor from proceeding with the contract as changed. Clause No. 20— Retrocession. (a) The Indian tribe that initially requested this contract may also...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1974 - 720 pages
...accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within thirty (30) days from the date of receipt by the Contractor...excuse the Contractor from proceeding with the contract aa changed. 13. NOTICE TO THE GOVERNMENT OF DELAYS Whenever the Contractor has knowledge that any actual...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1976 - 864 pages
...accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within thirty (30) days from the date of receipt by the Contractor...excuse the Contractor from proceeding with the contract aa changed. 13. NOTICE TO THE GOVERNMENT OP DELAYS Whenever the Contractor has knowledge that any actual...