...writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor...clause of this contract entitled "Disputes." However, nothing in this clause shall excuse the Contractor from proceeding with the contract as changed. *****... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1959 - 1028 pages
...in writing within 30 days from the date of receipt by the Contractor of the notification of extra or change : Provided, however, That the Contracting Officer,...upon any such claim asserted at any time prior to the date of final settlement of the contract. If the parties fail to agree upon the adjustment to be... | |
| Administrative law - 1970 - 260 pages
...price or time of performance, or both, and (i1) in such other provisions of the contract as may be so affected, and the contract shall be modified in writing...clause of this contract entitled "Disputes". However, nothing in this clause shall excuse the contractor from proceeding with the contract as changed. §... | |
| Administrative law - 1983 - 1104 pages
...hourly rates, (iii) delivery schedule, and (iv) in such other provisions of the contract as may be so affected, and the contract shall be modified in writing...to any adjustment shall be a dispute concerning a question of fact within the meaning of the "Disputes" clause of this contract. However, nothing in... | |
| Administrative law - 1978 - 944 pages
...equitable adjustment shall be made in the estimated cost, the completion schedule, or both, and the contract shall be modified in writing accordingly....contract. Failure to agree to any adjustment shall be • dispute concerning a question of fact within the meaning of the "Disputes" clause of this contract.... | |
| Administrative law - 1974 - 788 pages
...writing accordingly. Any claim by the Contractor ior adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor...clause of this contract entitled "Disputes." However, nothing in this clause shall excuse the Contractor from proceeding with the contract as changed. §... | |
| Administrative law - 1978 - 880 pages
...contract price or time of performance, or both, and (it) in such provisions of the contract as may be so affected, and the contract shall be modified in writing...any time prior to final payment under this contract. Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's... | |
| Administrative law - 1979 - 1186 pages
...to be paid to the Contractor; and (iii) in such other provisions of the contract as may be affected, contract shall be modified in writing accordingly....prior to final payment under this contract Failure to 7-404.1 ARMED SERVICES PROCUREMENT REGULATION 7:267 CONTRACT CLAUSES AND SOLICITATION PROVISIONS agree... | |
| Administrative law - 1974 - 918 pages
...fixed fee to be paid to the Contractor; and (III) In such other provisions of the contract as may be so affected, and the contract shall be modified in writing...upon any such claim asserted at any time prior to flnal payment under this contract. Failure to agree to any adjustment shall be a dispute concernIng... | |
| Administrative law - 1974 - 1020 pages
...for adjustment under this clause must be asserted within sixty (60) days from the date of receipt b; the Contractor of the notification of change : Provided,...clause of this contract entitled "Disputes." However, nothing In this clause shall excuse the Contractor from proceeding with the contract as changed. In... | |
| |