§ 1-3.405-2 Cost contract.

(a) Description. The cost contract is a cost-reimbursement type contract under which the contractor receives no fee.

(b) Application. The following are illustrative situations in which the use of this type of contract may be appropriate:

(1) Research and development work, particularly with nonprofit educational institutions or other non-profit organizations.

(2) Facilities contracts.

(3) Initial small quantity procurements of new items with anticipated subsequent large production runs.

§ 1-3.405-3 Cost-sharing contract.

(a) Description. A cost-sharing contract is a cost-reimbursement type contract under which the contractor receives no fee but is reimbursed only for an agreed portion of its allowable costs.

(b) Application. A cost-sharing contract is suitable for those procurements which cover production or research projects which are jointly sponsored by the Government and the contractor with benefit to the contractor in lieu of full monetary reimbursement of costs. In consideration of this benefit, the contractor agrees to absorb a portion of the costs of performance. The following are illustrative situations in which this type of contract is generally desirable:

(1) Jointly sponsored research and development work with nonprofit educational institutions or other nonprofit organizations.

(2) Other research and development work where the results of the contract may have commercial benefit to the contractor.

[blocks in formation]

and maximum fee, and a fee adjustment formula. After performance of the contract, the fee payable to the contractor is determined in accordance with the formula. The formula provides, within limits, for increases in fee above target fee when total allowable costs are less than target costs, and decreases in fee below target fee when total allowable costs exceed target costs. The provision for increase or decrease in the fee is designed to provide an incentive for maximum effort on the part of the contractor to manage the contract effectively.

(b) Application. The cost-plus-incentive-fee contract is suitable for use primarily for development and test when a cost-reimbursement type of contract is found necessary in accordance with § 1-3.405-1(b), and when a target and a fee adjustment formula can be negotiated which are likely to provide the contractor with a positive profit incentive for effective management. In particular, where it is highly probable that the development is feasible and the Government generally has determined its desired performance objectives, the cost-plus-incentive-fee contract should be used in conjunction with performance incentives in the development of major systems, and in other development programs where use of the cost and performance incentive approach is considered both desirable and administratively practical (see §§ 1-3.403(c) and 1-3.407-2(b)). Range of fee and the fee adjustment formula should be negotiated so as to give appropriate weight to basic procurement objectives. For example, in an initial product development contract, it may be appropriate to negotiate a cost-plus-incentive-fee contract providing for relatively small increases or decreases in fee tied to the cost incentive feature, balanced by the inclusion of performance incentive provisions providing for significant upward or downward fee adjustment as an incentive for the contractor to meet or surpass negotiated performance targets. Conversely, in subsequent development and test contracts, it may be more appropriate to negotiate an incentive formula where the opportunity to earn additional fee is based pri

marily on the contractor's success in controlling costs. With regard to the cost incentive provisions of a contract, the minimum and maximum fees, and the fee adjustment formula, should be negotiated so as to provide an incentive which will be effective over variations in costs throughout the full range of reasonably foreseeable variations from target cost. Whenever this type of contract, with or without the inclusion of performance incentives, is negotiated so as to provide incentive up to a high maximum fee, the contract also shall provide for a low minimum fee, which may even be a "zero" fee or, in rare cases, a "negative" fee.

(c) Limitations. The maximum fee shall be subject to the limitations stated in § 1-3.405-5(c)(2).

§ 1-3.405-5 Cost-plus-a-fixed-fee contract. (a) Description. The cost-plus-afixed-fee contract is a cost reimbursement type of contract which provides for the payment of a fixed fee to the contractor. The fixed fee once negotiated does not vary with actual cost, but may be adjusted as a result of any subsequent changes in the work or services to be performed under the contract. Because the fixed fee does not vary in relation to the contractor's ability to control costs, the cost-plus-afixed fee contract provides the contractor with only a minimum incentive for effective management control of costs.

(b) Application. The cost-plus-afixed-fee contract is suitable for use when:

(1) A cost-reimbursement type of contract is found necessary in accordance with § 1-3.405-1(b);

(2) The parties agree that the contract should be fee bearing;

(3) The contract is for the performance of research, or preliminary exploration or study, where the level of effort required is unknown; or

(4) The contract is for development and tests where the use of a cost-plusincentive-fee contract is not practical.

(c) Limitations. (1) This type of contract normally should not be used in the development of major weapons and equipment, once preliminary exploration and studies have indicated a

high degree of probability that the development is feasible and the Government generally has determined its desired performance objectives and schedule of completion (see § 1-3.4054).

(2) The fixed fees shall not exceed those prescribed by agency procedures within the limitations set forth in the first sentence of section 304(b) of the Act (41 U.S.C. 254(b)), which sentence reads in part as follows:

[ocr errors]

⚫ in the case of a cost-plus-a-fixed-fee contract the fee shall not exceed 10 per centum of the estimated cost of the contract, exclusive of the fee, as determined by the agency head at the time of entering into such contract (except that a fee not in excess of 15 per centum of such estimated cost is authorized in any such contract for experimental, developmental, or research work and that a fee inclusive of the contractor's costs and not in excess of 6 per centum of the estimated cost, exclusive of fees, as determined by the agency head at the time of entering into the contract, of the project to which such fee is applicable is authorized in contracts for architectural or engineering services relating to any public works or utility project)."

(d) Contractors' investment in workin-process. Contractors having costreinbursement type contracts shall be required to maintain a reasonable investment in the property and facilities acquired and in the services rendered in the performance of such contracts. This investment provides a strong incentive for the contractor to strive for greater efficiency and economy and better management, with resultant lower costs to the Government.

(1) In keeping with this policy, costreimbursement type contracts other than those set forth below shall provide for interim payment of not to exceed 80 percent of the costs incurred by the contractor in the performance of the contract.

(i) Contracts under which the contractors receive no fee or profit.

(ii) Contracts with educational institutions or nonprofit organizations.

(iii) Contracts solely for the operation of Government-owned plants or vessels.

(iv) Contracts with small business concerns.

(v) Contracts for research and development which do not provide for quantity production.

(vi) Contracts for performance outside the United States, its possessions, and Puerto Rico.

(vii) Contracts having an estimated cost not in excess of $250,000.

(viii) Contracts for construction and architect-engineer services.

(ix) As determined by the agency head concerned, contracts in which the application of the policy would impose undue hardship on the contractor or adversely affect the interests of the Government.

(2) An appropriate clause imple

menting this policy shall be inserted in all cost-reimbursement type supply contracts.

(3) Application of this policy need not affect the method of payment of the fee, but the extent of the contractor's capital investment in the performance of the contract will be taken into consideration in fixing the amount of fee or profit.

(e) Completion or Term form. The cost-plus-fixed-fee contract can be drawn in one of two basic forms, Completion or Term.

(1) The Completion form is one which describes the scope of work to be done as a clearly-defined task or job with a definite goal or target expressed and with a specific end-product required. This form of contract normally requires the contractor to complete and deliver the specified endproduct (in certain instances, a final report of research accomplishing the goal or target) as a condition for payment of the entire fixed-fee established for the work and within the estimated cost if possible; however, in the event the work cannot be completed within the estimated cost, the Government can elect to require more work and effort from the contractor without increase in fee provided it increases the estimated cost.

(2) The Term form is one which describes the scope of work to be done in general terms and which obligates the contractor to devote a specified level of effort for a stated period of time for

the conduct of research and development. Under this form, the fixed-fee is payable at the termination of the agreed period of time on certification of the contractor that he has exerted the level of effort specified in the contract in performing the work called for, and such performance is considered satisfactory by the Government. Renewals for further periods of performance are new procurement and involve new fee and cost arrangements.

(3) The Completion form of contract, because of differences in obligation assumed by the contractor, is to be preferred over the Term form whenever the work itself or specific milestones can be defined with sufficient precision to permit the development of estimates within which prospective contractors can reasonably be expected to complete the work, as is usually the case in advanced development and engineering development. A milestone is a definable point in a program when certain objectives can be said to have been accomplished.

(4) In the case of research and exploratory development work, it is rarely possible to define the scope of work with the degree of precision necessary for contracting on a Completion basis because of the nature of the work to be performed. Hence in such cases, the Term form of contract may be considered preferable in that it provides more flexibility for effective conduct of the research effort.

(5) In no event should the Term form of contract be used unless the contractor is obligated by the contract to provide a specific level-of-effort within a definite period of time.

§ 1-3.406 Other types of contracts.

§ 1-3.406-1 Time and materials contract.

(a) Description. The time and materials type of contract provides for the procurement of property or services on the basis of (1) direct labor hours at specified fixed hourly rates (which rates include direct and indirect labor, overhead, and profit) and (2) material at cost. Material handling costs may be included in the charge for "material at cost," to the extent they are clearly excluded from any factor of the charge computed against direct

labor hours. This type of contract does not afford the contractor with any positive profit incentive to control the cost of materials or to manage his labor force effectively.

(b) Application. The time and materials contract is used only where it is not possible at the time of placing the contract to estimate the extent or duration of the work or to anticipate costs with any reasonable degree of confidence. Particular care should be exercised in the use of this type of contract since its nature does not encourage effective management control. Thus it is essential that this type of contract be used only where provision is made for adequate controls, including appropriate surveillance by Government personnel during performance, to give reasonable assurance that inefficient or wasteful methods are not being used. This type of contract may be used in the procurement of (1) engineering and design services in connection with the production of supplies; (2) the engineering, design and manufacture of dies, jigs, fixtures, gauges, and special machine tools; (3) repair, maintenance, or overhaul work; and (4) work to be performed in emergency situations.

(c) Limitation. Because this type of contract does not encourage effective cost control and requires almost constant Government surveillance, it may be used only after determination that no other type of contract will suitably serve. This type of contract shall establish a ceiling price which the contractor exceeds at his own risk. The contracting officer shall document the contract file to show valid reasons for any change in the ceiling and to support the amount of such change.

(d) Optional method of pricing material. When the nature of the work to be performed requires the contractor to furnish material which is regularly sold to the general public in the normal course of business by the contractor, the contract may provide for charging material on a basis other than at cost if:

(1) The total estimated contract price does not exceed $25,000 or the estimated price of material so charged

does not exceed twenty percent of the estimated contract price.

(2) The material to be so charged is identified in the contract;

(3) No element of profit on material so charged is included in the profit in the fixed hourly labor rates; and

(4) The contract provides that the price to be paid for such material shall be on the basis of an established catalog or list price, in effect when material is furnished, less all applicable discounts to the Government, but in no event shall such price be in excess of the contractor's sales price to his most favored customer for the same item in like quantity, or the current market price, whichever is lower.

§ 1-3.406-2 Labor-hour contract.

(a) Description. The labor-hour type of contract is a variant of the time and materials type contract differing only in that materials are not supplied by the contractor.

(b) Application. See § 1-3.406–1(b). (c) Limitations. See § 1-3.406-1(c).

§ 1-3.407 Additional incentives.

§ 1-3.407-1 General.

In addition to the profit incentives to control costs, inherent in many of the contract types, and combinations thereof, described in §§ 1-3.404 through 1-3.406, there are other means of providing profit incentives to contractors, which are described in this § 1-3.407, to obtain extra management attention and effort. Increases in profits or fees resulting from the use of incentive provisions are made only because cost, performance or other contractual goals or standards have been surpassed.

§ 1-3.407-2 Contracts with performance incentives.

(a) Description. A contract with a performance incentive is one which incorporates an incentive to the contractor to surpass stated performance targets by providing for increases in the fee or profit to the extent that such targets are surpassed and for decreases to the extent that such targets are not met. Salient features and con

siderations in the use of this type of contract are as follows:

(1) "Performance", as used in this § 1-3.407-2, refers not only to the performance of the article being procured, but to the performance of the contractor as well. Performance which is the minimum which the Government will accept shall be mandatory under the terms of the Completion form contract and shall warrant only the minimum profit or fee related thereto. Performance which meets the stated targets will warrant the "target" profit or fee. Performance which surpasses these targets will be rewarded by additional profit or fee. The incentive feature (providing for increases or decreases, as appropriate) is applied to performance targets rather than performance requirements.

(2) The incentive, when applied to the product, should relate to specific performance characteristics, such as range of a missile, speed of an aircraft or ship, thrust of an engine, maneuverability of a vehicle, and fuel economy. However, high overall performance of the end item is the primary objective of such contracts. Accordingly, the incentive feature should reflect a balancing of the various characteristics which together account for overall performance, so that no one characteristic will be exaggerated to the detriment of the end item as a whole. When applied to the performance of the contractor, the incentive should relate to specific performance areas or milestones, such as delivery or test schedules, quality controls, maintenance requirements, and reliability standards.

(3) Since performance tests generally are essential in order to determine the degree of attainment of performance targets, the contract must be as specific as possible in establishing test criteria, such as conditions of testing. precision of instrumentation, and interpretation of test data.

(4) It is essential that there be explicit agreement between the Government and the contractor as to the effect on performance of contract changes (e.g., pursuant to the Changes clause).

(5) Care must be exercised, in establishing performance criteria, to give recognition to the fact that the contractor should not be rewarded or penalized for attainments of Government-furnished components.

(6) In establishing incentives in connection with delivery schedules, it is important to determine the Government's primary objectives in a given contract. In some instances, earliest possible delivery is of paramount importance. In others, early quantity production is essential. On the other hand, it may be that maintaining an established delivery schedule is all that is desired, and that a bettering of such schedule may distrupt continuity of production or run counter to funding limitations.

(b) Application. Contracts with performance incentives are suitable for use in procurements where it is desired to provide the contractor with an incentive in the form of financial reward for surpassing stated performance targets, counterbalance by a penalty in the form of decreased profit or fee for failure to achieve such targets. Performance incentives are particularly appropriate for inclusion in contracts for major weapons and equipment, both in development when desired performance objectives are known and the fabrication of prototypes for test and evaluation is required, and in production where there is potential for improved performance that would be highly desirable to the Government. Effort always should be made in these procurement situations to include a performance incentive in the contract. Performance incentives present complex problems in contract administration and should be negotiated and administered by contracting officers with the full cooperation of Government engineering and pricing specialists.

(c) Limitations. (1) Performance incentives, when related to the performance of the product, may result in increased costs and shall always be coupled with a balancing of range of fee or profit on the cost and performance aspects, negotiated so as to give appropriate weight to basic procurement objectives. Where incentives relating to