Search Images Maps Play YouTube News Gmail Drive More »
Sign in
Books Books
" ... shall ascertain the facts and the extent of the delay and extend the time for completing the work when in his judgment the findings of fact justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto... "
Cases Decided in the Court of Claims of the United States - Page 396
by United States. Court of Claims - 1948
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 121

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1952 - 1040 pages
...contractor shall within 10 days from the beginning of any such delay notify the contracting officer in writing of the causes of delay, who shall ascertain...such an extension, and his findings of facts thereon snail be final and conclusive on the parties hereto, subject only to appeal, within 30 days, by the...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 147

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1962 - 712 pages
...period of time prior to the date of final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain...fact justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within 30...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 107

United States. Court of Claims - Law reports, digests, etc - 1947 - 806 pages
...Case of time prior to the date of final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain...of fact justify such an extension, and his findings pi fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 145

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1959 - 820 pages
...settlement of the contract) notify the contracting officer in writing of the 145 C. Cte. Findings of Fact causes of delay, who shall ascertain the facts and...fact justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within 30...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 94

United States. Court of Claims - Law reports, digests, etc - 1942 - 818 pages
...notify the contracting officer in writing of the causes 04 C. CIS. Reporter's Statement of the Case of delay, who shall ascertain the facts and the extent...fact justify such an extension, and his findings of fact shall be final and conclusive on the parties hereto, subject only to appeal, within 30 days, by...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 114

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1950 - 824 pages
...period of time prior to the date of final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain...his judgment the findings of fact justify such an extensionj and his findings of fact thereon shall be final and conclusive on the parties hereto, subject...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 122

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1952 - 936 pages
...Contract) notify the Contracting Officer in writing of the causes of delay, 122 C. Gig. Finding! of Fact who shall ascertain the facts and the extent of the...fact justify such an extension, and his findings of fact thereon snail be final and conclusive on the parties hereto, subject only to appeal, within 30...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volumes 120-130

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1955 - 1002 pages
...and unusually severe weather or delays of subcontractors due to such causes. The contracting officer shall ascertain the facts and the extent of the delay...fact justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within thirty...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 104

United States. Court of Claims - Law reports, digests, etc - 1946 - 936 pages
...contract) notify the contracting officer in writing of the causes 01 delay, who shall ascertain the fact and the extent of the delay and extend the time for...fact justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within 30...
Full view - About this book

Cases Decided in the Court of Claims of the United States, Volume 105

United States. Court of Claims - Law reports, digests, etc - 1946 - 920 pages
...because of unforeseeable causes of delay, including strikes, and it provides that the contracting officer "shall ascertain the facts and the extent of the delay...judgment the findings of fact justify such an extension." This, of course, makes it mandatory upon the contracting officer to make findings of fact upon an application...
Full view - About this book




  1. My library
  2. Help
  3. Advanced Book Search
  4. Download EPUB
  5. Download PDF